Presentation is loading. Please wait.

Presentation is loading. Please wait.

USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 1 Tridas Status Drew Baden University of Maryland October 2003.

Similar presentations


Presentation on theme: "USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 1 Tridas Status Drew Baden University of Maryland October 2003."— Presentation transcript:

1 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 1 Tridas Status Drew Baden University of Maryland October 2003

2 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 2 HTR Status Dual-LC O-to-E VME Deserializers Xilinx XC2V3000-4 Stiffeners SLBs (6) TTC mezzanine Rev 3 – 30 boards made in March 2003 –Board production changes: New assembler, in-house X-ray, DFM review, QC Gold plated (Rev 1 was white-tin) for better QC –Changes to HTR: Change from FBGA (1.00mm) to BGA (1.27mm) Added stiffeners Moved all SLB/TPG output to front-panel daughterboards Modified Rx refclk scheme (the usual TTC/refclk clocking concerns) –Full 48 channel capability Rev 1 in 2002 was “half HTR”

3 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 3 Changes to HTR for Rev4 Moved 2 LC’s down to giver more clearance for fibers –Upper rear of card Spread out routing of differential pairs for 6 SLB and 2 FPGA system clocks Removed hot swapping circuits –Worry about noise, decided not to require HTR to be hot swappable Front-panel changes –Rotary switch, LEDs, eliminate REFCLK mux via jumper, etc Miscellaneous changes –Fixed what was found to be wrong with Rev3 board, add test points, terminate all unterminated I/O lines to SLB, VME byte swapping, other minor stuff

4 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 4 TODO - TPG HTR production can begin after: –SLB/HTR/Wisconsin check Check that we can maintain link Setup ready…so far so good Measure BER, etc. –SLB/HTR connectivity check Logic analyzer card on SLB site already shows connectivity Waiting for firmware for SLB to verify for sure –Should be this week or next TPG Data validation –Will build a 6U VME board with sites for the Wisconsin Vitesse receiver boards –Will fifo data and read out over VME –Use this to check data validity, try different TPG tests, etc. –Plan to start on this board by Nov 1 –Ready in a few months. Will use this for the early slice tests to test TPG output. FPGA Clock Input

5 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 5 TTC receiver - TTCumd General purpose TTC receiver board (TTCumd) –TTCrx ASIC and associated PMC connectors Will be used to receive TTC signal by HTR, DCC, and clock fanout boards No signal receivers –Copper/fiber receivers must be on the motherboard –Signal driven through TTC connectors Tested successfully –Maryland, Princeton, BU, FNAL –Testbeam H2 Production: –Need 1 per HTR (~260) + DCC (20) + Fanout (10) –Need ~500 TTCrx for HCAL –Will layout test board for rapid testing en mass

6 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 6 Clocks and Synchronization Clocking considerations can be divided into 2 parts: –Deserializers REFCLK: stability critical (80MHz frame rate) Stability: must have a very low jitter – 40ps pkpk spec Frequency: TI TLK2501 spec is 100ppm (8kHz) to lock – Measured ~350ppm (30kHz) needed to establish link »LHC variation expected to be few kHz – Once link is established, just needs to be stable (it’s a REFCLK!!!) Phase: relationship to LHC clock totally irrelevant –Phase critical clock for pipeline synchronization Must be in phase with LHC clock Jitter spec is less stringent –For FPGA sequential logic –For SLB transmission 80ps pkpk

7 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 7 HCAL Clock Fanout HTR clocks provided by a single 9U VME board –Chris Tully/Jeremy Mans from Princeton –Has fiber TTC input Signals fanned out over Cat6 twisted pair: –TTC stream To be used by each HTR and by DCC to decode commands & L1A –BC0 To be used by SLBs to synchronize TPGs –“40MHz” clock To be used by FPGA and SLBs to maintain pipeline – Comes from QPLL –“80MHz” clean clock To be used for deserializer REFCLK – Comes from QPLL Status –Final layout in hand. Waiting till the last minute. –Production can start mid January

8 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 8 Clock Distribution HTR TTC fiber TTC CLK80 BC0 CLK40 distribution to 6 SLBs and to 2 Xilinx Brdcst, BrcstStr, L1A O/E BC0 TTC FPGA.. Test Points for RxCLK and RxBC0.. 80.18 MHz.. TTCrx to Ref_CLK of SERDES (TLK2501) CLK40 CLK80 Princeton Fanout Board TTCrx QPLL HTR Cat6E or Cat7 Cable

9 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 9 Testbeam 2003 Lack of a QPLL – we had to improvise: –Front-end used commercial Cypress PLL Beats GOL 100ps pkpk jitter spec in the lab Terry Shaw measured sufficiently small jitter on backplane –Fanout card No clean 80MHz REFCLK, so provided 2 alternatives: – 2xLHC clock from crystal oscillator – High quality clock from HP signal and pulse generators – Jumper selectable on mezzanine cards No clean 40MHz system clock – Just used 40MHz output from TTCrx chip anyway – Worked well enough »The system clock doesn’t need a low jitter spec, and Xilinx has a DLL to clean it up –Much struggling with the fiber links, synchronization issues, etc.

10 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 10 Testbeam 2003 What we struggled with and learned about –Fiber links FE Tx clock critical. No QPLL so we used backup plan. Great deal of experience gained here. –TTC Had a few minor issues, discover how to best synch L1A with pipeline –DAQ Production DCC logic board –Able to operate SLINK64 smoothly –Logic in place for inline error checking, data integrity, etc XDAQ implementation experience –Calorimeter Took useful calorimeter data. –HB, HE, HO, HF

11 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 11 Testbeam Experience Fiber synchronization –FE With crystal oscillator on FE, few troubles –Still some mysteries…much better results in US tests TTC 40MHz clock cleaned up by Cypress “roboclock” chip (Cy7B993) –Many synch errors, varied from fiber-to-fiber, hard to maintain link on all fibers over ~few hours time period –During synchronized beam running, sent reset between spills to ensure link. This seemed to work ok. Exploring using rescynch in abort gap… –Fanout card Fanout from onboard ~80MHz crystal oscillator for REFCLK Fanout TTC 40MHz clock for system clock –HTR 40MHz system clock scheme worked –Some firmware changes necessary to synchronize with L1A TLK2501 link circuitry always enabled.

12 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 12 Fiber Links (cont) Tests at Maryland using TI eval board and Stratos transmitter –Link exceedingly stable (see slides below) Current plan –Study FE → HTR link at FNAL FNAL test stand is setup, link tests underway, more to come this fall –Investigate noise characteristics of H2 environment H2 is clearly different than FNAL, Maryland (and BU) experience –Review of HTR and Fanout card Will learn what we need to do from the above Best guess –All tests in US indicate solid link, but experience in H2 disagree –Probably a linear combination of: TTC clock jitter (most likely) Some kind of new noise component (less likely – FE works with crystal oscillators) Bottom line: –We have a system that works in our labs (BER<10 -14 ) but… H2 environment? Need more studies during the next 6-12 months Lack of working QPLL. Looking forward to getting correct QPLL/crytals

13 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 13 Optical Attenuation and BER “Typical setup” –VECSEL transmitter, coupled to fiber via LC connector Not locked, but fixed in place –Fiber to LC to 8-way MTP male on HTR front panel –Single fiber to LC connector for connection to STRATOS receiver Output power: –VECSEL advertised to put out 500  W (-3dBm) Terry Shaw measured 570  W for a particular VECSEL –UMD uses STRATOS LC transmitter Advertised output 100-400  W (-4 to -10dBM) Measured to be 90  W for a particular STRATOS About 6dB below what we will use in CMS Working on FE emulator now using GOL+VECSEL… Attenuations measured: –At each LC connector, 10 – 50% (0.5 to 1.5 dB) –At MTP connector, same thing (.75dB advertised) –Fibers are about ¼ dB per 100m FE VECSEL LC MTP (8-way) LC Stratos HTR

14 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 14 Optical Power (cont) What do we need at the receiver to maintain link? –Did a series of measurements with known attenuator –Varied attenuation, looked at: BER TTL “signal detect” (SD) signal provided by Stratos part –Found: SD signal goes away when power is below about 2  W –Measured 1.5  W but accuracy of meter is probably ±.2  W BER climbs very fast right at this shoulder NB: achieved BER<10 -15 with multiple fibers in parallel with crystals Measured ~5k errors in 10sec Points with error bars are worst case BER: <1 error See next slide

15 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 15 Link Loss Observation Ran a test at 7.4  W (-21dBm), found 44 errors in 18 hours Simultaneously triggered scope on VCC to transmitter and crate Found that the scope had triggered on transmitter voltage but not crate –Voltage spike - 1-2V oscillation with ~50ns rise time –Crate was isolated through UPS These errors were due to a spike on the A/C line from equipment being power cycled, noise in building, etc. Moral: noise in the power/grounds will be our nightmare

16 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 16 Optical Attenuation (cont) Input power required to maintain link: –Measured failure for power < ~2  W (-33dBm) Power output by VECSEL: –500  W output Divide by 2 for digital averaging Gives 250  W (-6dBm) output at source Expected Attenuations –Maximum of 8 couplings until the signal gets to the Stratos receiver on the HTR 8x(0.5 - 1.5)dB = (4 – 12)dB –Add another ~1dB due to fibers Total power at inputs to HTRs: –-6dBm – (4-13)dB = -10 to -19 dBm –FNAL measured/calculated 7.3dB Operating would be -13dBm We should have about 10dB margin –Probably more like 15dB VECSEL Operating

17 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 17 Longitudinal Separation Attenuation MTP connector ends are spring loaded into adapter Measured attenuation as a function of the separation –Separation should be ~0 if keys and adapters are working well –This should not be an issue for us (famous last words….)

18 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 18 Project Timeline 2003 2004 Firmware TB 03 firmware should be adequate Boards Can use current crop of Rev3 To do: Commission QPLL, global clocking. Level 1 Trigger: SLB, TPG, latency… “Vertical Slice” (~March) 2005 HB, HE, and ME plus Level 1/TPG Fiber synchronization Check in alcove…compare environments Firmware TPG firmware has to be ready. Fall 03 task. Boards Must have Rev4. How many TBD. FE Commissioning (~Feb) “Magnet” Tests (no HCAL) CMS Magnet Integration System Test Boards Will have Rev4. H2 Testbeam Fiber synchronization Check in H2…compare environments Boards Will have Rev4. How many TBD.

19 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 19 HTR Firmware

20 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 20 TPG Path Still under development –The following is already coded/simulated but not tested in HTR TPG path tasks (not necessarily in order) –Linearize QIE data to 10 bits With.5GeV resolution gives 512 GeV max –Apply BCID filter Probably will sum over 2 buckets and assign based on high/low patter around the bucket that has the max energy –Sum or divide depending on HB, HE, or HF –Extract a muon window for the “feature bit” –Apply logic to eliminate false muons from shower leakage, etc. –Compress and send to SLB

21 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 21 TPG Path Schematic

22 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 22 TODO (cont) Firmware –Focus on L1 latency optimization Measure full latency, scheme for random TLK latency, how to meet L1 latency budget, etc. This will be the main activity from now until we go into production. –Bells and whistles for error reporting/recover Meeting next week in Princeton to finalize what we learned in 2003 More to be learned in 2004 HTR boards –Make Rev4 this fall, go into production early 04 ASAP given schedule Depends on results from above

23 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 23 Latency Definition: from BX to input to RCT HCAL O-E QIECCA HTR SLB RCT BX TOF To RBX DataTo RCT RBX HPD or PMT (HF) 46 clocks = 1,147.7ns GOL

24 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 24 TOF+Y11/fiber to RBX 10.855 4.332 HCAL O-E QIECCA HTR SLB RCT BX TOF To RBX DataTo RCT RBX HPD or PMT (HF) 46 clocks = 1,147.7ns GOL TOFTx to RBX (7ns/m)TOTAL HB  =1 layer 1 (1.8m) 6.1ns(4.9m) 34.1ns40.2ns HB  =15 layer 9 (4.6m) 15.4ns(0.6m) 4.2ns19.6ns HE  =34 layer 1 (4.0m) 13.3ns(3.3m) 22.9ns36.2ns HB  =17 layer 14 (5.7m) 19.1ns(0.3m) 2.0ns21.1ns HF(10.9m) 36.3ns(2m quartz) 14ns50.3ns

25 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 25 Inside RBX CCA delays will be set using LED system TOF+TxO-ETotal to CCAClocksQIECCA+GO L Total HB40.2(HPD) 0ns40.2ns1.6 (1)43+210 HE36.2(HPD) 0ns36.2ns1.5 (1)43+210 HF50.3(1.5kv PMT + 6m coax) 14ns + 30ns = 44ns 94.3ns3.8 (3)43+212 Assumes CCA can absorb <1 clock tick phase (?) HCAL O-E QIECCA HTR SLB RCT BX TOF To RBX DataTo RCT RBX HPD or PMT (HF) 46 clocks = 1,147.7ns GOL

26 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 26 Digital Data Fiber Measured  = 2/3 (51m adds 250ns delay) –Gives 4.99 m/clock tick (@40.08MHz LHC RF frequency) Default fiber length 90m gives 18.036 clocks –Use 18, make fibers <90m –HE is longest due to routing around ME outer radius Change HE fiber routing to go via EE inner radius –We believe we can shave off 15-20m 3 clocks – 15 total maybe more? Thru RBXData FiberTotal HB101525 HE101525 HF121527 HCAL O-E QIECCA HTR SLB RCT BX TOF To RBX DataTo RCT RBX HPD or PMT (HF) 46 clocks = 1,147.7ns GOL

27 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 27 Random Latencies in HTR Latency due to –TI deserializer (TLK2501) Advertised random latency with respect to reset 76 to 106 bit times –Remember, TLK2501 has 20-bit frames –Latency will be 47.5 to 66.9 ns random We measured the random latency at UMD –Latency difference is randomly distributed between 0 and 6ns. –Factor of ~1/3 of TI spec. Will investigate if this is “typical” –Asynchronous fifo Relative phase between recovered clock and refclk will introduce a random latency of 0 to 1 clock tick TLK2501 Common 80MHz system clock = 40MHz clock/2 from TTC

28 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 28 Latency in HTR Input to GOL, 7m fiber, HTR firmware to SLB –395ns = 16 clock ticks –GOL has 2, 7m fiber has 1.4, remainder is ~12 clock ticks Relative phase between GOL and HTR system clock and TLK refclk varied –Latency seen is some combination of TLK and asynchronous fifo –Measured for a single Temp and VCC Need to repeat with variations Thru RBXData FiberHTRTotal HB10151237 HE10151237 HF12151239 HCAL O-E QIECCA HTR SLB RCT BX TOF To RBX DataTo RCT RBX HPD or PMT (HF) 46 clocks = 1,147.7ns GOL

29 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 29 SLB + TPG Cables SLB nominal latency 3 clock ticks –SLB job is to make sure all HCAL/ECAL towers from same BX arrive at RCT in synch by… Histogram TPGs to find the LHC beam structure –Find “BC0_DATA” Adjust with BC0 broadcast timing (TTCvi) so all partitions are in synch –“BC0_TTC” Delay accordingly knowing | BC0_DATA  BC0_TTC | We might have to suffer 1 or 2 clock ticks here – we don’t know yet TPG Cables –20m nominal “Wesley cables”, 5m/clock tick –Wesley will cave on these. We believe we can count on 15m cables. –3 clock ticks for TPG cables Total 3(SLB nominal) + 1 (SLB contingency) + 3 (TPG cables) = 7 clock ticks

30 USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 30 Grand Total Caveats: –Numbers for TOF+prog delay are correct (please check!) –75m max for all fiber cables (saves 3 clocks) –CCA can take up some of the slack for TOF+propogation delays (<1clock) –CCA can be run with a latency of 3 and still do its job (5 max for the chip) –3m TPG cables –No summing in HTR firmware –Total delay through SLB < 4 (1 for contingency, need experience here) Possible further additions to total latency –TOF+propogation (+HF delays thru PMT and coax) –Digital fiber cabling could go back to 90? –Need to implement summing in HTR firmware – we need a MC study to tell us we need this. Default should be no summing unless MC study tells us otherwise –Difficulties with SLB Possible further scrubbing –Digital fiber cabling (Ianos and Laza are on top of this…) –“Tricks” in HTR firmware –Perhaps save another clock in CCA for HF (discussing with Terry) –Any other clever ideas? Thru RBX Data Fiber HTRSLB/ TPG Total HB 1015127 44 HE 1015127 44 HF 1215127 46


Download ppt "USCMS/HCAL/TriDas. October, 2003 HCAL TriDAS 1 Tridas Status Drew Baden University of Maryland October 2003."

Similar presentations


Ads by Google