Presentation is loading. Please wait.

Presentation is loading. Please wait.

Presented By: Marvin Burns, PE Janssen & Spaans Engineering, Inc.

Similar presentations


Presentation on theme: "Presented By: Marvin Burns, PE Janssen & Spaans Engineering, Inc."— Presentation transcript:

1 Presented By: Marvin Burns, PE Janssen & Spaans Engineering, Inc.
Practices needed during design, shop drawing preparation and construction of long span post-tensioned bridges 2 Construction Techniques Spliced, Post-tensioned, Precast Girders Cast-In-Place Balanced Cantilever I-355 Bridge over Des Planes River Valley 270’ main span - Illinois Tollway Authority Design Build SMART Bridge 472’ main span - Virginia DOT Construction Engineering Presented By: Marvin Burns, PE Janssen & Spaans Engineering, Inc.

2 Responsibilities Design Engineer Adequacy of design
Provide details that are workable with only minor conflicts that can be resolved in the shop drawings Erection Scheme that meets industry practices Construction Engineer Preparation of Shop Drawings for each segment that combines various elements shown on contract plans with erection hardware and post-tensioning hardware. These items often have proprietary details and cannot be finalized until the Supplier has been selected. Shop Drawings showing placement of rebar with minor repairs from that shown on contract plans to avoid post-tensioning anchorages and ducts.

3 Responsibilities Construction Engineer for Cast-In-Place Balanced Cantilevers Provide detailed erection analysis based on Contractors Erection Sequence and Calendar. Analysis includes stress/capacity design checks for each step of erection; including time effects for creep and unbalance moments during weekly cycles. Services include camber diagrams made from the deflections and procedures to control geometry for erection segments. Calculations for tendon forces and elongations using friction coefficients associated with the tendon duct supplied by the post-tensioning supplier.

4 Contractor / Construction Engineer
The Construction Engineer’s duties and responsibilities are described in, and governed by, a written contract with the Contractor. Duties will generally include requirements imposed by the Owner in the special provisions. Contract documents usually contain minor conflicts. Although many of these are caught and cleaned up during preparation of the shop drawings there is an expense in money and time associated with how much detail is needed by the Contractor to be able to build from the shop drawings. The Contractor has tight schedules and cannot wait for shop drawings to be perfect before work proceeds. At a certain point the Contractor has to cut off the planning stage and get on with the work.

5 Spliced, Post-tensioned, precast concrete girder
US 27 over Caloosahatchee Canal Moore Haven, FL 3 Spans (210’-320’-210’) 320’ National Record held by JSE Completed Winter 2001 KY 22 over Kentucky River Gratz, Ky 4 Spans (175’-200’-325’-200’) 325’ National Record held by JSE Completed Summer 2010 Featured in Aspire magazine in Winter 2011

6 I-355 Bridge over Des Plaines River Valley Illinois Tollway Authority Performance Based Alternate
35 Spans divided into 8 Units - 2 structures at 6,600 ft each 102” Deep Post-Tensioned Bulb Tees, PT Beams Haunched to 120” on Main Spans 90” Prestressed Beams Post-tensioned Spans Ranged from 216’ to 271’ Prestressed Spans Ranged from 114’ to 170’ Completed Winter 2007

7 Post-Tensioned Beams Spans Ranged from 216 ft to 270 ft
Beams Ranged from 113 ft to 150 ft

8 Post-Tensioned Beams Typical Beam Depth – 102 in
Beams haunched over Piers to 120 in Brian

9 Post-Tensioned Beams Falsework Required Strongbacks Brian

10 Post-Tensioned Beams 4 Tendons Per Beam Line Brian

11 Post-tensioning

12 Post-tensioning

13 Tendon Grouting

14 Final Cost $125M Low bid - including engineering fees
$133M Second-place bid for Segmental Concrete Box Alternate $147M Third-place bid for Steel Performance-Based Alternate Bids include approach roadway and adjustment of features crossed Brent

15 SMART Bridge – Virginia DOT Christiansburg, Virginia Construction Engineering
Contractor: PCL Civil Constructors Construction Cost: 15 Million Completion: 2000 5 Spans (284’-3 at 472’- 284’) = 1984’ Width = 36’-4” Single Cell Box (2 Webs)

16 SMART BRIDGE Concrete Pour using Tire Crane

17 SMART BRIDGE Erection of Pier Table Erection of Form Traveler

18 SMART BRIDGE

19 EB Wakota Bridge– Minnesota DOT Minneapolis, Minnesota Construction Engineering
Contractor: Lunda Construction Construction Cost: $63 million x 2 bridges = $126 million Completion: 2010 5 Spans (272’-328’-2 at 466’,358’) = 1890’ Width = 85’ typical and 105’ at end spans for acceleration lanes DoubleCell Box (3 Webs)

20 EB Wakota Bridge Front View Side View Erection of Pier Table

21 EB Wakota Bridge Erection of Form Traveler

22 EB Wakota Bridge Pouring of Segment using Pair of Pump Trucks

23 EB Wakota Bridge

24 Construction Loading PERMANENT EQUIPMENT Shear Transverse
Shear on Leading Edge Actual Wt. vs. Plan COG 1.4x Shear at Leading Edge

25 Construction Loading PERMANENT EQUIPMENT Shear Transverse
Shear on Leading Edge Actual Wt. vs. Plan CONSERVATIVE MAX IDEALIZED ORIGINAL DESIGN CONST. DISTRIBUTION

26 EB Wakota Bridge Inside View of Left Cell of Double Cell Box

27 General Structure Size Balanced Cantilever Construction

28 Rebar Congestion Double Cell Box
Wide double cell boxes can have larger tendon forces. It would make it easier to install confinement rebar for the anchorages if the concrete dimensions could be enlarged. Single Cell Box

29 Rebar Congestion

30 Vertical Tendon Radial Force
Tendon Stressing Operation Concrete Spall

31 Vertical Tendon Radial Force
Tendon Pop-Out Vertical Radial Force

32 Vertical Tendon Radial Force
Tendon Radial Force is Unrestrained Vertical Legs are Too Far Apart Tendon Radial Force is Restrained

33 Stirrups to Restrain Angle Change at Bulkheads

34 Tendon Radial Force Variable Height Box

35 Horizontal Tendon Radial Force

36 Horizontal Tendon Radial Force

37 Tendon Cross Over into Adjacent Duct

38 Horizontal Tendon Radial Force Concrete Removal

39 Tendon Duct is Crowding Anchorage Reinforcing

40 Tendon Duct is Crowding Anchorage Reinforcing

41 Questions Thank You


Download ppt "Presented By: Marvin Burns, PE Janssen & Spaans Engineering, Inc."

Similar presentations


Ads by Google