Presentation is loading. Please wait.

Presentation is loading. Please wait.

Mississippi River Bridge Project Commission Meeting December 1, 2010 Mississippi River Bridge Project Commission Meeting December 1, 2010 Greg Horn, MoDOT.

Similar presentations


Presentation on theme: "Mississippi River Bridge Project Commission Meeting December 1, 2010 Mississippi River Bridge Project Commission Meeting December 1, 2010 Greg Horn, MoDOT."— Presentation transcript:

1 Mississippi River Bridge Project Commission Meeting December 1, 2010 Mississippi River Bridge Project Commission Meeting December 1, 2010 Greg Horn, MoDOT Project Director

2 Mississippi River Bridge Update

3 Main Span Awarded $230 million MO. Approach Awarded $11 million IL. Approach Awarded $47 million Bids April 2011 $42 million Multiple Bids 2009-2013 $220 million Bids Year 2 $75 million Cass Bridge Awarded $4 million

4 MRB Construction Contracts 32 Total Construction Contracts 32 Total Construction Contracts 18 Contracts Awarded 18 Contracts Awarded $361 Million Under Construction $361 Million Under Construction 1% Under Budget 1% Under Budget

5 Mississippi River flooding

6 Building the foundation

7 Shaft Rock Cores

8 Concrete Delivery

9 Cofferdam

10 Business and Workforce Development

11 DBE Update 17.3 percent on MRB Projects 17.3 percent on MRB Projects 81 firms 81 firms 118 contracts 118 contracts $62 million in subcontracted work $62 million in subcontracted work 14 projects remaining 14 projects remaining

12 Workforce Update Hours worked on MRB Projects Hours worked on MRB Projects 20% minority 20% minority 6.7% female 6.7% female Federal Goals Federal Goals 14.7% minority 14.7% minority 6.9% female 6.9% female

13 Public Tours

14 Aesthetic Lighting

15 Mississippi River Bridge On Schedule On Schedule On Budget On Budget Opening 2014 Opening 2014

16 www.newriverbridge.org MRB Project Director Greg Horn, (314) 453-1827 gregory.horn@modot.mo.gov gregory.horn@modot.mo.gov


Download ppt "Mississippi River Bridge Project Commission Meeting December 1, 2010 Mississippi River Bridge Project Commission Meeting December 1, 2010 Greg Horn, MoDOT."