Endcap Module Status Agreed Responsibilities Overall Production UK Situation Global Schedule Issues General Production Issues.

Similar presentations


Presentation on theme: "Endcap Module Status Agreed Responsibilities Overall Production UK Situation Global Schedule Issues General Production Issues."— Presentation transcript:

1 Endcap Module Status Agreed Responsibilities Overall Production UK Situation Global Schedule Issues General Production Issues

2 Agreed Module Distribution InnerMiddle Outer TotalInnerMiddleOuterTotal UK160 208528UK192 250634 VLC80104184VLC96125221 GVA520 GVA624 Melb104 ContingencyMelb125 MPI400 × 1.2MPI480 NIKHEF80 NIKHEF96 Freib.160 Freib.192 Total4006409361976Total48076811232371

3 Overall Production Proceeds smoothly –~816 module starts (35% of total) 70% tested of which –Yield: 88% (good), 92%(good+pass) Still OK but seems to be dropping slightly Components: –No stocks building up for spines or hybrids Very vulnerable to component delays http://ific.uv.es/~lacasta/ECproduction/

4 SummaryBuiltGoodPassHoldFailedNot testedYield (G)Yield (G+P) All8163611724940587.8%92.0% ClustersBuiltGoodPassHoldFailedNot testedYield (G)Yield (G+P) UK-V4102151421815283.3%88.8% CS2221332108697.8%99.3% CE1841312116776.5%82.4% TypesBuiltGoodPassHoldFailedNot testedYield (G)Yield (G+P) Outer4532421013518389.6%93.3% Inner10100011000.0% MidL1791066935585.5%90.3% MidS83131206781.2%87.5% SitesBuiltGoodPassHoldFailedNot testedYield (G)Yield (G+P) Freiburg290000 NaN Geneva2211332108597.8%99.3% Manchester306135913614382.8%88.3% Manchester-Inn000000NaN Manchester-Mid83261115489.7%93.1% Manchester-Out22310981258981.3%87.3% Melbourne100001NaN MPI83131206781.2%87.5% Nikhef720001710.0% Valencia10480582984.2%89.5% Valencia-Mid9680582184.2%89.5% Valencia-Out800008NaN

5 Glasgow64442012 75%416399 48 Liverpool14112417100 92%9109275 32 Manchester250 0 00232 25 In Transit7070 0061 7 Other0000 0000 0 Totals23716869112 90%131259517 112 Site Starts Bonded Unbonded Good Tested Total Incomplete Failing Tested OK Fail Total Glasgow0000 00000 Liverpool82602249 94%35229130 Manchester1010 0 0 011 In Transit0000 00000 Other0000 00000 Totals83602349 94%05229231 UK Outers in Database as of 31/8/04 UK Middles in Database as of 31/8/04 Thanks to Joe Foster for summary

6 Overall Schedule Still some delay –Foreseen to finish last module by end June 2005 –GVA and MPI have increased their production rates –Could be earlier (during May) if sites soon approaching their agreed number of modules, keep their production lines running. VLC helps MPI with middles NIKHEF helps Freiburg with Inners –Melbourne has to start very soon. Already pre-qualified. UK Modules

7 Production Issues Disk measurements showed redundancy link operation increases noise: –Trials have led to new (screened) links and requirement to change module 5.1kΩ resistor on redundancy line –All UK modules at Liverpool now have shorted out resistor with 0Ω resistor following procedure proposed by Freiburg 20% sample test show identical normal electrical performance after change –All new hybrids have 0Ω resistor –Disk results with these changes greatly improved, disc9C mounting to begin Repeat of contamination/erosion of tracks on fan-in after thermal cycling. Seen in one early Liverpool Module Now seen on two MPI modules in the same place as at Liverpool Chemical analysis soon at CERN Spine QA and delivery still critical Prague CTU and Melbourne still to qualify Most other sites producing at or above original envisaged rates and UK is nearing half-way


Download ppt "Endcap Module Status Agreed Responsibilities Overall Production UK Situation Global Schedule Issues General Production Issues."