LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Similar presentations


Presentation on theme: "LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001."— Presentation transcript:

1 LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001

2 Farias Elementary School Construction Committee Meeting Tuesday, December 11, 2001

3 THIS VIEW IS LOOKING NORTH WEST AT THE BUILDING PAD. PAD IS WET DUE TO RECENT RAINS.

4 THIS VIEW IS LOOKING NORTHEAST AT THE BUILDING PAD. SURVEYORS ARE SETTING THE CORNER PINS FOR THE BUILDING.

5 Santa Maria Elementary School Construction Committee Meeting Tuesday, December 11, 2001

6 PLUMBING SUBCONTRACTOR TRENCHING FOR THE INSTALLATION OF PLUMBING LINES.

7 THE PLUMBING LINES PREFABRICATED ON SITE FOR INSTALLATION IN THE PLUMBING TRENCH.

8 PREPARATION OF THE BUILDING PAD AT THE BUILDING.

9 Dovalina Elementary School Construction Committee Meeting Tuesday, December 11, 2001

10 VIEW LOOKING NORTH WEST AT THE CONCRETE FOUNDATION. MASONRY BLOCK WALLS BEING CONSTRUCTED.

11

12 SOUTHEAST VIEW OF THE COMPLETED FOUNDATION SYSTEM.

13

14 Project:Christen Middle School Architect: Sepulveda Associates Architects, Inc. Status: Design Development Budget: $7,193,380. Timeline: Start of Final Design Phase: Jan 2002 Present Final Contract Dwgs: Mar 2002 Completion of Construction: Dec 2003

15 Project: Martin High School Architect: Sepulveda Associates Architects, Inc. Status: Design Development Budget: $7,823,946. Timeline: Start of Final Design Phase: Dec 2001 Present Final Contract Dwgs: Feb 2002 Completion of Construction: May 2003

16 Ochoa/T. Sanchez Elementary School Construction Committee Meeting Tuesday, December 11, 2001

17 THIS VIEW IS LOOKING SOUTH EAST AT THE BUILDING PAD.

18

19

20 EXISTING CITY SEWER LINE BEING REROUTED. NEW SEWER LINE BEING INSTALLED.

21 Project: K.Tarver Elementary School Architect: Cavazos & Associates Architects Status: Design Development Budget: $ 4,606,191.00 Dlls. Timeline: Start of Final Design Phase: Feb 2002 Present Final Contract Dwgs: April 2002 Completion of Construction: June 2003

22 C.L. Milton Elementary School Construction Committee Meeting Tuesday, December 11, 2001

23 THIS VIEW IS OF THE PAD PREPARATION FOR THE NEW PORTABLE CLASSROOMS. THIS IS A SOUTH EAST VIEW. THIS VIEW IS OF THE PAD PREPARATION FOR THE NEW PORTABLE CLASSROOMS. THIS IS A SOUTH EAST VIEW.

24 NORTH EAST VIEW OF THE PAD PREPARATION FOR THE PORTABLE BUILDINGS.

25 Project: J.C. Martin Elementary School Architect: Ashley Humphries & Sanchez Architects Status: Preliminary Design Budget: $1,997,044. Timeline: Start Design Development : Feb 2002 Start of Final Design Phase: April 2002 Present Final Contract Dwgs: June 2002 Completion of Construction: Aug 2003

26 Project: Lamar Middle School Architect: Cavazos & Associates Architects Status: Final Design Phase Budget: $ 7,358,620. Timeline: Start of Final Design Phase: Aug 2001 Present Final Contract Dwgs: Feb 2002 Completion of Construction: June 2003

27 J.W. NIXON HIGH SCHOOL Construction Committee Meeting Tuesday, December 11, 2001

28 THIS IS A VIEW LOOKING WEST AT THE CANOPY ON THE SOUTH END OF THE PORTABLE BUILDING.

29 THIS VIEW IS LOOKING NORTH ALONG THE NEW SIDE WALK FOR THE STUDENTS.

30 THIS VIEW SHOWS THE FENCING ON TOP OF THE EXISTING BLOCK WALL.

31 MAIN PATIO DECK. MAIN ENTRANCE TO BUILDINGS.

32 Project: Daiches Elementary School Architect: Turner Hickey & Associates, Inc. Status: Design Development Budget: $5,191,225. Timeline: Start of Final Design Phase: Dec 2001 Present Final Contract Dwgs: March 2002 Completion of Construction: April 2003

33 Project: Heights Elementary School Architect: Pending Status: Pending Budget: Pending Timeline: Pending

34 Project: Santo Nino Elementary School Architect: Frank Architects Inc. Status: Final Design Phase Budget: $5,191,225. Timeline: Start of Final Design Phase: Sept. 2001 Present Final Contract Dwgs: Jan 2002 Completion of Construction: March 03

35 Project: Kawas Elementary School Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase Budget: $4,211,386. Timeline: Start of Final Design Phase: July 2001 Present Final Contract Dwgs: Oct 2001 Completion of Construction: Dec 2002

36 Project: H.B. Zachry Elementary School Architect: Design Group International, Inc. Status: Construction Documents Phase Budget: $1,456,725. Timeline: Start of Final Design Phase: Oct 2001 Present Final Contract Dwgs: Dec 2001 Completion of Construction: Dec 2002

37 Project: H. Ligarde Elementary School Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase Budget: $3,388,153. Timeline: Start of Final Design Phase: Oct 2001 Present Final Contract Dwgs: Dec 2001 Completion of Construction: Dec 2002

38 Project: Cigarroa Middle School Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase Budget: $3,314,867. Timeline: Start of Final Design Phase: July 2001 Present Final Contract Dwgs: Dec 2001 Completion of Construction: June 2003

39 Project: Cigarroa High School Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase Budget: $8,168,516. Timeline: Start of Final Design Phase: July 2001 Present Final Contract Dwgs: Dec 2001 Completion of Construction: June 2003