Building 100 Remodel - Feasibility Chabot College 11.12.2009
2
AGENDA Background Assumptions Scope and Cost Layouts Pros and Cons Next Steps
3
User Group Involvement June - September 2009 Dean Corcoran, Dean Vo-Kumamoto, Cindy Hicks, Jim Matthews Previous Library/Learning Connection FPP in 2007 Extensive Remodel of All Floors New Entry/Lobby/Stairs/Elevator Series of Large User Group Meetings, Interviews and Tours Previous Budget: $16M - $20M Feasibility Study No Demolition, Minimal Renovation, Moderate Remodel Current Budget: $3.1M Construction Budget, $4M Total Project Budget BACKGROUND
4
ASSUMPTIONS
5
ALL 3 OPTIONS: Construction Timeline: April – October 2010 Per DSA 8/24/09: No Sprinkler, No Seismic, No Elevator Upgrade Not included: Soft Cost, Fees, Sitework Areas to Remain: TV, Radio, Telecon, Media, Health, Restrooms All 3 Options include: Library Circulation Desk, A/V Changes and Wall Removal New Carpet/Paint, New FF&E Budget Security Adjustments, Select CCTV, Elevator Controls Associated Hazmat Connection Loop to C.U.P. COST ASSUMPTIONS
6
SCOPE AND COST
7
NO DEMOLITION ~12,800 asf, ~18,300 gsf All walls stay as is New carpet & paint Min M/E adjustments No new lighting Study Rooms on perimeter Estimate = $1.79M, ~$98/sf MINIMAL RENOVATION ~13,500 asf, ~18,300 gsf Perimeter offices stay as is New carpet & paint Some M/E adjustments 2/3 new lighting Some walls with glazing Existing offices on perimeter Study Rooms on perimeter Estimate = $3.13M, ~$171/sf MODERATE REMODEL ~14,300 asf, ~18,300 gsf All walls new configuration New carpet & paint More M/E/P adjustments All new lighting More walls with glazing New offices on perimeter Study Rooms in center More open areas Estimate = $4.42M, ~$241/sf SCOPE AND COST
8
LAYOUTS
9
NO DEMOLITION – Space Layout
10
NO DEMOLITION – Furniture Layout
11
MINIMAL – Space Layout
12
MINIMAL – Furniture Layout
13
MODERATE – Space Layout
14
MODERATE – Furniture Layout
15
LIBRARY – Space Layout
16
LIBRARY – Furniture Layout
17
MEZZANINE – Space Layout
18
PROS AND CONS
19
Centralizes Learning Support Services Provides ‘inviting’ and ‘welcoming’ space Provides spaces that stimulate O social interaction Enhances Library & Learning O O Connection relationship Supports collaboration and O integration of Programs Collects groups into ‘open areas’ O Multi-functional dynamic spaces O adaptable to pedagogy Creates intuitive wayfinding Offers convenient Study Rooms Safe and supervisable areas Relative Construction Timeline 3m 4m 6m Construction Cost 1.7M 3.1M 4.4M Total Units (Student Seats) 219 258 324 VISIONARY FUNCTIONAL PRAGMATIC NO DEMO PRO CON MINIMAL PRO CON MODERATE PRO CON
20
NEXT STEPS Recommended Feasibility Begin Detailed Design Phase