Presentation is loading. Please wait.

Presentation is loading. Please wait.

EXAMPLE 9.2 – Part I PCI Bridge Design Manual

Similar presentations


Presentation on theme: "EXAMPLE 9.2 – Part I PCI Bridge Design Manual"— Presentation transcript:

1 EXAMPLE 9.2 – Part I PCI Bridge Design Manual
2011/12 Edition EXAMPLE 9.2 – Part I PCI Bridge Design Manual BULB “T” (BT-72) THREE SPANS, COMPOSITE DECK LRFD SPECIFICATIONS Materials copyrighted by Precast/Prestressed Concrete Institute, All rights reserved. Unauthorized duplication of the material or presentation prohibited.

2 BRIDGE LAYOUT - Longitudinal
Continuous for Live Load

3 BRIDGE LAYOUT – Cross Section

4 DESIGN SPECIFICATIONS
LRFD – 5th Edition (2010) HL-93 Truck Loading No Skew Composite Deck

5 DESIGN SPECIFICATIONS
Concrete: fc’ = days fci’ = 5.5 release wc = kcf Ecb = 33000w1.5 (fc’)0.5 (LRFD ) = 33000(0.150)1.5(7.0)0.5 = 5072 ksi Prestressing Steel: GR 270 (fpu = 270 ksi; fpy = 243 ksi) ½” strand (Ap = in2 / strand) Ep = ksi

6 DESIGN SPECIFICATIONS
Mild Steel GR 60 (fy = 60 ksi) Es = ksi Future Wearing Surface 2” thick wws =0.150 kcf Barriers New Jersey type 0.300 k/ft

7 DESIGN SPECIFICATIONS
Deck 7.5” Structural thickness 0.5” wearing surface Total thickness = 8” fc’ = days wc = kcf Ecs = 33000w1.5 (fc’)0.5 (LRFD ) = 33000(0.150)1.5(4)0.5 = ksi Note – LRFD uses kip, inch, foot units in formulae

8 CONTINUOUS FOR LL PRECAST BRIDGES
Precast beams are made in a factory and shipped to site. The beam is set on simple supports – beam carries self weight and prestressing force as a simple beam.

9 CONTINUOUS FOR LL PRECAST BRIDGES
The deck is formed and poured. Since the beams are NOT shored, the beams carry the deck load as simple beams.

10 CONTINUOUS FOR LL PRECAST BRIDGES
The deck is cast continuous over the piers. When the deck hardens, a continuous structure is formed. The negative moment connection is usually made with non-prestressed steel over the piers. Thus, the negative moment region is conventionally reinforced.

11 CONTINUOUS FOR LL PRECAST BRIDGES
Once the deck hardens and continuity is established, any superimposed dead load (asphalt surfaces, barriers, utilities) is carried by the beams as a continuous structure. All live load is carried as a continuous structure.

12 CONTINUOUS FOR LL PRECAST BRIDGES
After the slab is poured, the beams will continue to creep and shrink; cambering up. Temperature will also cause camber. Positive moments will form causing cracking.

13 CONTINUOUS FOR LL PRECAST BRIDGES
A positive moment connection is required. The requirements for this will be discussed later. (LRFD )

14 CONTINUOUS FOR LL PRECAST BRIDGES
It is thought that creep and shrinkage will redistribute dead load, so some states design using simple spans for all dead load and assuming a continuous bridge for live load only. Some states completely ignore the continuity and design as simple span for all loads.

15 DESIGN SPANS Beams: Overall Length Design Spans –Simple Span beam
110 ft. end spans 119 ft center span Design Spans –Simple Span beam 109 ft. end spans 118 ft. center span Design Spans – Continuous Beam 120 ft. center span

16 PROPERTIES OF BT-72 A = 767 in.2 h = 72 in. I = in. 4 yb = in. yt = in. Sb = in. 3 St = in. 3 w = k/ft

17 PROPERTIES OF COMPOSITE BT-72
Ecs = 3834 ksi Ecb = 5072 ksi (prev. defined) Modular ratio: n = Ecs /Ecb = 3834/5072 = LRFD (NEW IN 2009): The effective flange width is now the TRIBUTARY AREA: bf = 144 inches

18 PROPERTIES OF COMPOSITE BT-72
Note: ½ inch haunch assumed. Shaded area is transformed.

19 PROPERTIES OF COMPOSITE BT-72
Transformed Flange Width = (Effective Flange Width)*n = 144(0.756)= in. Transformed Flange Area = 108.9”(7.5”) = in2 Note: only 7.5” of deck thickness is structural.

20 PROPERTIES OF COMPOSITE BT-72
Haunch – assumed ½” over BT-72 flange width to account for differential camber in the beams. Transformed Haunch Width = 0.756(42”) = in. Transformed Haunch Area = 31.75”(0.5”) = in2

21 PROPERTIES OF COMPOSITE BT-72
Atr in2 yb in. Ayb in.3 A(ybc-yb)2 in.4 I I+A(ybc-yb) Beam 767.00 36.60 28072 325484 545894 871378 Haunch 15.87 72.25 1147 3601 Deck 816.8 76.25 62280 296420 3829 300249 Sum 1599.7 91500 ybc = 91500/ = in. (distance to bottom of composite)

22 PROPERTIES OF COMPOSITE BT-72
Ac = 1599 in2 Ic = in4 hc = 80 in. ybc = 91477/ = in. (distance to bottom of composite) ytc = 80 – = in. (distance to top of composite) ytg = 72 – = in. (distance from composite neutral axis to top of beam)

23 PROPERTIES OF COMPOSITE BT-72
Composite Section Modulus to Bottom: Sbc = Ic / ybc = /57.20 = in.3 Composite Section Modulus to Top of Composite: Stc = Ic /nytc = /(0.756*22.8) = in.3 Note: 1/n converts stress in transformed concrete to stress in actual concrete. Composite Section Modulus to Top of Beam: Stg = Ic / ytg = /14.8 = in.3

24 DEAD LOADS - DC DC – Applied to precast only.
Beam self weight wg = kip/ft. Slab weight – include ½” integral wearing surface. ws = (8”/12”/ft)(12 ft.)(0.150 kcf) = 1.20 kip/ft Haunch wh = (0.5”/12)(42”/12)(0.150 kcf) = kip/ft

25 DEAD LOADS - DC DC – Applied to composite section. To determine if the barrier weight and the future wearing surface can be equally distributed, the following must be met (LRFD ): Width of deck constant OK Number of beams > OK Curvature < specified in OK straight Cross section matches one given in LRFD Spec. table OK type “k”

26 k

27 DEAD LOADS - DC The overhang of the roadway, from the outside of the web, de < 3.0 ft. de = 3 ft OK Def. of de changed in 2008 interim (LRFD ).

28 DEAD LOADS - DC DC – Applied to composite section
Barrier weight – 0.30 kip/ft wb = 2 barriers (0.3 k/ft) / (4 beams) = 0.150 k/ft/beam Diaphragm weight – assumed steel X braces. Weight ignored in this example. Typically, they weigh a few hundred pounds.

29 DEAD LOADS - DW DW – Future wearing surface and utilities.
Future wearing surface kcf (2”/12)(0.150 kcf) = ksf 0.025 ksf (42’ roadway width) / 4 beams = k/ft /beam

30 UNFACTORED DEAD LOADS All loads are uniform. DL moments and shears on the precast can be found from: Use overall length at initial (release) condition. Center to center of bearing at deck placement.

31 UNFACTORED DEAD LOADS The shears and moments due to the future wearing surface and the barrier weight are computed by considering the bridge as a continuous, three span structure. The span lengths after continuity is established are center of support to center of pier for end spans and center of pier to center of pier for the middle span. Shears and moments can be found using any analysis program or by a hand calculation.

32 Unfactored DL Moments End Spans Middle Span

33 LIVE LOAD DISTRIBUTION FACTORS
To use distribution factors, the following must be met: Width of deck constant OK Number of beams > OK Curvature < specified in OK straight Cross section matches one given in LRFD Spec. table OK type “k” de < 3 ft. OK 3 ft. Beams parallel and approximately same stiffness. OK

34 LIVE LOAD DISTRIBUTION FACTORS - MOMENT
Number of design lanes = integer part of 42 ft. / (12 ft./lane) = 3 lanes 42 ft. is clear roadway width. Interior Beams (Table b-1):

35 LIVE LOAD DISTRIBUTION FACTORS - MOMENT
To use these factors: 3.5’ < S < 16’ S = 12 ft. OK 4.5” < ts < 12” ts = 7.5 in. OK 20’ < L < 240’ L = 120 ft. OK Nb > 4 beams Nb = 4 beams OK Note: Although this is a 3 lane bridge, there is NO reduction to the LL for multiple presence. The distribution factors already account for multiple presence.

36 LIVE LOAD DISTRIBUTION FACTORS - MOMENT
eg = (7.5/2) = 39.65 = distance between centroids of beam and slab A = area of non-composite beam I = moment of inertia of non-composite beam

37 LIVE LOAD DISTRIBUTION FACTORS - MOMENT
Kg = (1.323)[ (39.65)2] = in4

38 LIVE LOAD DISTRIBUTION FACTORS - MOMENT
S = 12 ft. L = 120 ft. Kg = in4 ts = 7.5” DFM = lanes/beam

39 LIVE LOAD DISTRIBUTION FACTORS - MOMENT
S = 12 ft L = 120 ft Kg = in ts = 7.5” DFM = lanes/beam DFM = lanes/beam –two lanes CONTROLS

40 LIVE LOAD DISTRIBUTION FACTORS - SHEAR
Interior Beams:

41 LIVE LOAD DISTRIBUTION FACTORS - SHEAR
To use these factors: 3.5’ < S < 16’ S = 12 ft. OK 4.5” < ts < 12” ts = 7.5 in. OK 20’ < L < 240’ L = 120 ft. OK Nb > 4 beams Nb = 4 beams OK < Kg < Kg = OK

42 LIVE LOAD DISTRIBUTION FACTORS - SHEAR
S = 12 ft. DFV = lanes/beam two lane CONTROLS DFV = lanes/beam one lane


Download ppt "EXAMPLE 9.2 – Part I PCI Bridge Design Manual"

Similar presentations


Ads by Google