CAMPAN VALLEY RESIDENTIAL LAYOUT PROJECT PHOTOS-FEBRUARY 15 th 2015
4
VIEW-1: BITUMEN MACADAM, SEWERLINES & WATER SUPPLY LINES COMPLETED & FOOTPATH FORMATION WORK IN PROGRESS BETWEEN BLOCK 32 & COMPOUND
5
VIEW-2: SEWER LINE, STORM WATER DRAIN, WATER SUPPLY LINES, BITUMEN MACADAM COMPLETED & FOOT PATH FORMATION WORK IN PROGRESS BETWEEN BLOCK 19 & COMPOUND
6
CLUB HOUSE: NORTH SIDE ELEVATION-PLINTH BEAM & COLUMNS CASTING WORK IN PROGRESS
7
CLUB HOUSE: EAST SIDE ELEVATION-PLINTH BEAM & COLUMNS CASTING WORK IN PROGRESS
8
CLUB HOUSE: SOUTH SIDE ELEVATION-PLINTH BEAM & COLUMNS CASTING WORK IN PROGRESS
9
CLUB HOUSE: WEST SIDE ELEVATION-PLINTH BEAM & COLUMNS CASTING WORK IN PROGRESS
10
MODEL VILLA FOUNDATION- FOUNDATION WORK IN PROGRESS
11
TRANSFORMERS ERECTED IN PLACE