2 www.dot.state.pa.us ENGINEERING DISTRICT 3-0 9 Counties 2,901 State Bridges –5.5% Structurally Deficient 4,500 Miles of State Highways –20% Poor IRI

3 www.dot.state.pa.us ENGINEERING DISTRICT 3-0 FUNDING 2015-18 TIP Northern Tier Federal: $47.5 M State: $87.8 M WATS Federal: $28.8 M State: $43.7 M SEDA-COG Federal: $194.6 M State: $235.4 M (Includes CSVT )

4 www.dot.state.pa.us DISTRICT PRIORITIES Provide the highest quality projects, safely, and on-time Deliver the first contract for the Central Susquehanna Valley Transportation Project (CSVT) in August 2015 Deliver $279 million of projects to letting in 2015

5 www.dot.state.pa.us SAFETY Do you know how many crashes occurred in work zones in Calendar Year 2014? –45 Do you know which county had the most crashes in work zones? –Columbia 5

6 www.dot.state.pa.us CONSTRUCTION CONTRACT TRENDS

7 www.dot.state.pa.us CENTRAL SUSQUEHANNA VALLEY TRANSPORTATION PROJECT

8 www.dot.state.pa.us CENTRAL SUSQUEHANNA VALLEY TRANSPORTATION PROJECT Estimated Major Milestones Northern Section: August 2015 – Let first contract (river bridge) 2021 – Complete construction Southern Section: 2019 – Let first contract (earthwork) 2024 – Complete construction

9 www.dot.state.pa.us FUTURE CONSULTANT NEEDS: DESIGN In January 2015 advertised for a project specific agreement for the Access Management Project on TR 220 By June 2015 will advertise a $3 to $4 million Open-End

10 www.dot.state.pa.us FUTURE CONSULTANT NEEDS: CONSTRUCTION INSPECTION Upcoming Agreement Advertisements 2015-16 –CSVT project specific for river bridge (2015-16) –CSVT project specific for northern section earthwork and structures (early 2016) –One open-end for consultant inspection Man-Power Needs –52 inspectors in 2015 –72 inspectors in 2016

11 www.dot.state.pa.us QUESTIONS??