Jim Mather MSP Minister for Enterprise, Energy & Tourism
2
Mike McElhinney Head of Energy Projects Scottish Government
3
Dana Dutianu Executive Agency for Competitiveness and Innovation (EACI)
4
Partners The Norwegian Institute for Nature Research SQW Energy Scottish Power Renewables Royal Society for the Protection of Birds, Scotland Administration of the Province of Savona, Italy Apere The Region of Western Greece The Western Isles Council Sustainable Energy Authority Ireland Leitat Technological Centre Speed Development Consultants SSE Renewables Agenzia ASEA Spa University of Thessaloniki A.D.E.P.S.A Projects in Motion Scottish Government
5
Good Practice Wind Project GP WIND Stuart Mckay
6
STRUCTURES – Funding Executive Agency for Competitiveness & Innovation Intelligent Energy Europe Project Partner Organisations
7
STRUCTURES – Work Packages I.E.E Scottish Government Work Package Leaders
8
Countries involved Scotland Ireland Spain Greece, Italy Norway Belgium Malta.
9
Achieving Renewable Energy Targets Renewable Energy Objectives Community Needs Wider Environmental Concerns
10
Single issue focus can upset the balance… Renewable Energy Objectives Community Needs Wider Environmental Concerns
11
Change of focus… Renewable Energy Objectives Community Needs Wider Environmental Concerns
12
Licenses Processes HabitatWildlife Shipping Displacement aquaculture Fishing Community issues Policy V’s Reality AcceptabilityConstruction disturbance Process Failures
13
Balancing the equation... Renewable Energy Objectives Community Needs Wider Environmental Concerns
14
The challenge is… Renewable Energy Objectives Community Needs Wider Environmental Concerns
15
Whist looking after these…
22
GP WIND’s contribution… Address barriers to the deployment of onshore and offshore wind generation. Bring together developers, regional and local government, environmental agencies and NGOs from differing countries to share experiences Recording and sharing good practice. Develop a guide to good practice and a 'how to' toolkit, which will be used to facilitate deployment of renewable energy in support of the 2020 targets.
23
The goal… Renewable Energy Objectives Community Needs Wider Environmental Concerns
24
Who will help ?
25
Work Package High Level Programme WP 1 – Management WP 2 – Common Methodology for case studies WP 5 – Communications / adoption of best practices WP 3 – Case Studies WP 4 – Guide to Good Practice Toolkit WP 6 – IEE Dissemination Activities Time Line
26
Work Package Leaders The Norwegian Institute for Nature Research SQW Energy Scottish Power Renewables Royal Society for the Protection of Birds, Scotland Administration of the Province of Savona, Italy Apere The Region of Western Greece The Western Isles Council Sustainable Energy Authority Ireland Leitat Technological Centre Speed Development Consultants SSE Renewables Agenzia ASEA Spa University of Thessaloniki A.D.E.P.S.A Projects in Motion Scottish Government
27
Responsibilities : Work Package Partners Work together to: Agree the overall approach Common methodologies Allocate and carry out tasks Compile reports The success of your WP is in your hands.
28
Responsibilities : Work Package Co-ordinators Overall co-ordination of the work package Defining detailed work plans with participating partners Organising the WP contribution Arranging meetings Managing partner inputs Compilation of WP activity reports Identification and escalation of issues
29
Scottish Government Work Package 1
30
STRUCTURES – Management I.E.E Scottish Government Partner Organisations
31
Work Package 1 Description Overall management of the consortium ensuring that the following activities are undertaken: Steering group meetings Work Package Co-ordination Group meetings Preparation and circulation of regular project updates Clear definition of KPI’s Provision of guidance to partners and monitoring of progress Preparation of reports and financial statements for IEE programme Management of Project Budget Co-ordination with other related projects (IEE and other EU projects) Minutes / Reports of the project meetings Completion of the final publishable report
32
Work Package 1 Management structure Steering Group Work Programme Co-ordination Group Work Package 2 Co-ordinator Work Package 3 Co-ordinator Work Package 4 Co-ordinator Work Package 5 Co-ordinator
33
Work Package 1 Likely Issues / Problems Confusion due to communication errors Disagreement around the definition of performance indicators and measurement Precise accounting of expenditure Not meeting reporting schedules Misunderstanding of partner roles and responsibilities
34
Work Package 1 Deliverables 1.Organisation of Steering group meetings 2.Attendance at Steering group meetings 3.Organisation of Work Package Co- ordination Group meetings 4.Attendance at Work Package Co- ordination Group meetings 5.Preparation and circulation of regular project update quarterly bulletins on a quarterly 6.Definition of performance indicators 7.Completion of monitoring templates Preparation of partner / Work Package progress reports 8. Preparation of partner interim report and final report 9. Monitoring of expenditure against budget and profile 10. Resolution of budget issues 11.Meetings with up to 6 related projects 12.Sharing of information with related projects 13.Delivery of Final publishable report
35
Work Package 1 Top 3 Risks 1.Communication errors 2.Misunderstanding of roles and responsibilities between partners 3.Poor financial reporting from partners
36
Work Package 1 Next Steps Appointment of full time Project Manager with appropriate support structures in place. Kick off organisational activities (Steering Group & WP Coordination Groups) Define and agree clear and unambiguous roles and responsibilities of all partners
37
Work Package 2 Methodology for case studies Scottish Government NINA APEREAUTHSQW ADEP
38
Work Package 3: Case Studies NINA The Norwegian Institute for Nature Research Western Isles CouncilRSPB APERESQWSCOTTISH POWER RENEWABLES SSE RENEWABLES All other Partners
39
Work Package 4: Guide to Good Practice and Toolkit APERE LEITAT SGAUTHSQWSPEED SA ASEA All other Partners
40
Work Package 5: Communication and adoption of best practice LEITAT PIM SP RENEWABLES SAVONA RWG SSE RENEWABLES All other Partners
41
Work Package 6: IEE Dissemination Activities SCOTTISH GOVERNMENT All other Partners
42
END – Part 1
43
Giulia Cammozzini Project Manager Scottish Government
44
Management of the project I.E.E Scottish Government Partner Organisations
45
In setting out a large scale project like this there will always be some of this…
47
A little of this…
50
But mostly, lots of this…
52
A critical issue for me is…
53
PROJECT SCOPE
58
Project Scope The project’s outputs and recommendations will focus on off-shore and on-shore wind energy.
59
Giulia Cammozzini Project Manager Scottish Government
60
The Methodology Surveys Detailed case studies of onshore and offshore wind energy projects. Identifying market barriers and process failures Pulling together good practice which can be transferred to other regions and technologies.
61
The Project Outputs Increase the consenting rate for on and offshore wind projects Build evidence based support for the design, planning and implementation of projects which are sensitive to environmental and community concerns; Assist quicker, more transparent and less costly deployment of wind energy across Europe, Secure endorsement of project outputs
62
End result …
64
Any Questions?