1 Update on FCPS Construction/Renovation Projects April 2009

2 Cassidy Elementary – Renovation  Architect: Tate.Hill.Jacobs: Architects  General Contractor: D.W. Wilburn, Inc.  Substantial Completion Date:August, 2010  Contract Sum:$9,061,000  Change Orders to Date:$0  Current Phase:1 (On Schedule) April 2009

3 Cassidy Elementary – Renovation Rendering of Final Façade April 2009

4 Cassidy Elementary – Renovation  Work Completed in Last 30 Days:  GC Construction Office located on site  Perimeter fencing in place  Barriers erected to separate demolition and construction activities from school operations  Music room and stage structure demolished  Current Work Effort (April):  New parking lot will be cut and temp stone placed for construction parking and staging  Foundations will begin to be poured  Plumbing and Electrical rough-ins below slab on grade to start  Other Notes of Interest:  Safety Committee created consisting of staff and parents working in conjunction with Risk Management & Safety April 2009

5 Cassidy Elementary – Renovation New 2-Story Admin. Addition Site Existing Music Room/Stage Demo April 2009 Interior Classroom Demo

6 Russell Cave Elementary – Renovation  Architect: Pearson & Peters Architects  General Contractor: Congleton-Hacker Construction  Substantial Completion Date:August, 2010  Contract Sum:$5,001,150  Change Orders to Date:$0  Current Phase:1 April 2009

7 Russell Cave Elementary – Renovation Rendering of Final Façade April 2009

8 Russell Cave Elementary – Renovation  Work Completed in Last 30 Days:  GC staging area and construction site fenced  Demolition of library building  Portable classrooms installed  Current Work Effort (April):  Excavation and geotechnical work to begin April 2009

9 Russell Cave Elementary – Renovation Site Work 4/7/09 April 2009

10 Arlington Elementary – Renovation  Architect: RossTarrant Architects  General Contractor: TBD  Substantial Completion Date:August, 2010  Contract Sum:TBD  Change Orders: $36,900 (#1--Demo)  Current Phase:Demolition Complete April 2009

11 Arlington Elementary – Renovation Rendering of Final Façade April 2009

12 Arlington Elementary – Renovation  Work Completed in Last 30 Days:  Demolition completed  Work at Site to begin in May April 2009

13 Arlington Elementary – Renovation Demo – Main Bldg. April 2009 Demo – Gym

14 Bryan Station Middle – Renovation  Architect: Clotfelter-Samokar Architects  General Contractor: Preston Construction Group  Substantial Completion Date:August, 2010  Contract Sum:$10,769,400  Change Orders to Date:$0  Current Phase:Phase 1 to begin June 1 April 2009

15 Bryan Station Middle – Renovation Rendering of Final Façade April 2009

16 Bryan Station Middle – Renovation  Work Completed in Last 30 Days:  GC conducting preparatory activities  Work at Site to Begin June 1 April 2009

17 Leestown Middle – Renovation  Architect: Lucas/Schwering Architects  General Contractor: D.W. Wilburn, Inc.  Substantial Completion Date:August, 2010  Contract Sum:$11,182,000  Change Orders to Date:$0  Current Phase:Phase 1a, 1b, 1c to begin June 1 April 2009

18 Leestown Middle – Renovation Rendering of Final Façade April 2009

19 Leestown Middle – Renovation  Work Completed in Last 30 Days:  GC conducting preparatory activities  Work at Site to Begin June 1 April 2009

20 Lafayette High Stadium – Replacement  Architect: Strand & Associates  General Contractor: Set to bid mid-June  Substantial Completion Date:July, 2010  Contract Sum:TBD  Change Orders to Date:$0  Current Phase:Construction Documents April 2009

21 Lafayette High Stadium – Replacement UPDATED Site Plan of Stadium April 2009

22 Central Bus Garage – Adaptive Reuse  Architect: Lucas/Schwering Architects  General Contractor: James R. Leake & Sons, Inc.  Substantial Completion Date:August, 2009  Contract Sum:$2,782,000  Change Orders to Date:$0  Current Phase:Construction April 2009

23 Central Bus Garage – Adaptive Reuse Façade April 2009

24 Central Bus Garage – Adaptive Reuse Proposed Floor Plan April 2009

25 Tonight’s Agenda Items Project Agenda Item  Central Bus Garage  Approval of Bid, Revised BG-1 & GC Contract James R. Leake & Sons: $2,782,000 Total Project Cost: $5,672,810  Leestown Middle  Approval of Bid, Revised BG-1 & GC Contract D.W. Wilburn, Inc.: $11,182,000 Total Project Cost: $13,682,854  New Elementary @ Keithshire  Approval of BG-1 Total Estimated Cost: $17,137,625  Veterans Park Roof Replacement  Approval of BG-1, Construction Documents & Advertise for Bids Total Estimated Cost: $1,422,400  Sandersville Elementary  Approval of Change Order # 3 Total Credit for Unused DPOs: ($15,167.67) April 2009