Update on FCPS Construction/Renovation Projects April 2009
2
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 Contract Sum:$9,061,000 Change Orders to Date:$0 Current Phase:1 (On Schedule) April 2009
3
Cassidy Elementary – Renovation Rendering of Final Façade April 2009
4
Cassidy Elementary – Renovation Work Completed in Last 30 Days: GC Construction Office located on site Perimeter fencing in place Barriers erected to separate demolition and construction activities from school operations Music room and stage structure demolished Current Work Effort (April): New parking lot will be cut and temp stone placed for construction parking and staging Foundations will begin to be poured Plumbing and Electrical rough-ins below slab on grade to start Other Notes of Interest: Safety Committee created consisting of staff and parents working in conjunction with Risk Management & Safety April 2009
5
Cassidy Elementary – Renovation New 2-Story Admin. Addition Site Existing Music Room/Stage Demo April 2009 Interior Classroom Demo
6
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August, 2010 Contract Sum:$5,001,150 Change Orders to Date:$0 Current Phase:1 April 2009
7
Russell Cave Elementary – Renovation Rendering of Final Façade April 2009
8
Russell Cave Elementary – Renovation Work Completed in Last 30 Days: GC staging area and construction site fenced Demolition of library building Portable classrooms installed Current Work Effort (April): Excavation and geotechnical work to begin April 2009
9
Russell Cave Elementary – Renovation Site Work 4/7/09 April 2009
10
Arlington Elementary – Renovation Architect: RossTarrant Architects General Contractor: TBD Substantial Completion Date:August, 2010 Contract Sum:TBD Change Orders: $36,900 (#1--Demo) Current Phase:Demolition Complete April 2009
11
Arlington Elementary – Renovation Rendering of Final Façade April 2009
12
Arlington Elementary – Renovation Work Completed in Last 30 Days: Demolition completed Work at Site to begin in May April 2009
13
Arlington Elementary – Renovation Demo – Main Bldg. April 2009 Demo – Gym
14
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August, 2010 Contract Sum:$10,769,400 Change Orders to Date:$0 Current Phase:Phase 1 to begin June 1 April 2009
15
Bryan Station Middle – Renovation Rendering of Final Façade April 2009
16
Bryan Station Middle – Renovation Work Completed in Last 30 Days: GC conducting preparatory activities Work at Site to Begin June 1 April 2009
17
Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 Contract Sum:$11,182,000 Change Orders to Date:$0 Current Phase:Phase 1a, 1b, 1c to begin June 1 April 2009
18
Leestown Middle – Renovation Rendering of Final Façade April 2009
19
Leestown Middle – Renovation Work Completed in Last 30 Days: GC conducting preparatory activities Work at Site to Begin June 1 April 2009
20
Lafayette High Stadium – Replacement Architect: Strand & Associates General Contractor: Set to bid mid-June Substantial Completion Date:July, 2010 Contract Sum:TBD Change Orders to Date:$0 Current Phase:Construction Documents April 2009
21
Lafayette High Stadium – Replacement UPDATED Site Plan of Stadium April 2009
22
Central Bus Garage – Adaptive Reuse Architect: Lucas/Schwering Architects General Contractor: James R. Leake & Sons, Inc. Substantial Completion Date:August, 2009 Contract Sum:$2,782,000 Change Orders to Date:$0 Current Phase:Construction April 2009
23
Central Bus Garage – Adaptive Reuse Façade April 2009
24
Central Bus Garage – Adaptive Reuse Proposed Floor Plan April 2009
25
Tonight’s Agenda Items Project Agenda Item Central Bus Garage Approval of Bid, Revised BG-1 & GC Contract James R. Leake & Sons: $2,782,000 Total Project Cost: $5,672,810 Leestown Middle Approval of Bid, Revised BG-1 & GC Contract D.W. Wilburn, Inc.: $11,182,000 Total Project Cost: $13,682,854 New Elementary @ Keithshire Approval of BG-1 Total Estimated Cost: $17,137,625 Veterans Park Roof Replacement Approval of BG-1, Construction Documents & Advertise for Bids Total Estimated Cost: $1,422,400 Sandersville Elementary Approval of Change Order # 3 Total Credit for Unused DPOs: ($15,167.67) April 2009