Download presentation
Presentation is loading. Please wait.
1
Economic Analysis of Projects
Afghanistan Energy Team World Bank Dubai, January 23-24, 2019
2
Maximize net benefit to society as a whole
Why bother? Scarcity of resources Land Labour Materials Capital Capital is a key resource Can generally be used to purchase others How should scarce capital be allocated? Maximize net benefit to society as a whole Other scarce resources? What about air, water?
3
Which projects? Projects that draw on government’s capital
Directly – government pays from revenues Indirectly – government takes on debt obligations Conditionally – government guarantees returns to a third party Thus, IPPs can also warrant analysis from the economic perspective if there is a PPA backed by government commitment
4
Examples of Projects Infrastructure Social Roads and bridges
Power plants Transmission and distribution networks Ports and waterways Social Health care – hospitals, health centers Education Environmental protection/rehabilitation Can programs be subject to analysis? - e.g. child vaccination,
5
Economic vs Financial Analysis
Perspective of project implementing entity Costs based on financial prices Benefits generally limited to gain in revenues and/or reduction in costs Designed to assess project’s financial sustainability Perspective of country as a whole Costs based on opportunity cost of inputs Benefits not limited to project revenues Designed to ensure that benefits to society exceed costs
6
Least Cost Analysis First step is to ensure that proposed project is least cost Define objective and desired outcome Identify alternative ways of achieving outcome Adjust for lack of comparability Life cycle cost analysis Identification of least cost alternative Want to be comparing apples with apples, so first define ann objective and a desired outcome
7
But …. Just because a project is least cost doesn’t make it economically viable Benefits to society must exceed costs Not sufficient simply to say that project is less costly than alternatives Examples of least cost but not economic
8
Cost Benefit Analysis Measures relationship between project costs and project benefits Cost Benefit ratio Benefits ÷ Costs - > 1 Economic Internal Rate of Return (EIRR) Discount rate (i) at which stream of benefits equals stream of costs Measures performance against a defined benchmark Net Present Value (NPV) at i Net value of future cost, benefit streams discounted to present at i How we typically carry out an economic analysis of a project
9
With/without Most benefits are measured relative to some alternative
What would happen without the investment? Before/after vs with/without Economic analysis looks into future Before/after wouldn’t reflect impact of growth on situation without project EA requires with/without scenarios Without scenario is the ‘counterfactual’ Without case is typically called a counterfactual Fake news?
10
Opportunity Cost of Inputs
Investment capital – discount rate Imported materials, equipment – Border prices – net of taxes and duties, plus transport to site Traded goods – Border price at exit port Unskilled labour Wage rate unless in surplus/shortage Less than wage rate if in surplus, greater if shortage Skilled labour Foreign exchange Official rate if freely traded Watch for currency controls, black markets
11
Economic Costs Capital cost of project Includes: Excludes:
Border price of imported equipment and materials plus transport to site Domestic land, labour and materials used in construction Land returned to its original use? Use cost of mitigation Excludes: taxes and duties on imported equipment, value added tax on domestic equipment, income taxes paid by foreign contractors, Any other ‘transfer’ payment
12
Incremental operating and maintenance costs
Includes Labour and materials used to maintain facility Operating and management labour Materials used in operations – e.g. fuel for power plant, lighting, heating and other utilities Equipment used in operations Excludes Subsidies paid to users Income and other taxes on wages
13
Other Economic Costs Environmental costs
Damage to physical environment: Temporary or permanent destruction of natural resources – forests, agricultural land, streambeds, wetlands, lakes and waterways, wildlife Negative Socio-economic impacts Temporary or permanent resettlement of sections of the population Health problems Lost income due to land expropriation
14
Economic Benefits Avoided use of alternatives Access to new services
Kerosene lamps Solar lamps/panels/SHS Generators Batteries Access to new services Refrigeration Air conditioning Heavy duty tools Computers Other user cost savings Time savings Reduced damage to equipment
15
Customer Benefit of Increased Access
Willingness to pay for electricity supply – Equal to area under the demand curve up to the point of price/quantity intersection Electricity tariff PLUS Consumer surplus
16
Customer Benefits – Willingness to Pay
17
Non-linear demand curve
18
Electricity Demand Curve – DABS Customers
19
Sources for WTP Data Tariff and consumption data
Information on cost of alternative energy sources Kerosene Solar LPG Batteries Generators Surveys on use of alternatives
20
Other Economic Benefits
Income-earning opportunities Machine shop Irrigated farming Beauty salon Retail/commercial Employment opportunities Social benefits Better health care Improved schools/learning opportunities Access to news and other information Safety Recreation opportunities
21
Environmental benefits
Reduced carbon emissions Flood control Preservation of forests, grasslands Not using wood fuel
22
Non-monetary costs and benefits
Unmitigated environmental impacts Improved health/education outcomes Time savings Some are hard to value but should at least be measured – what impacts? How many people?
23
Discounting Time value of money Financial Analysis Economic Analysis
Preference for payment now rather than later Interest rate on bonds, bank accounts Dividends on equities Capital gains on equities, real estate, other assets Financial Analysis Look at stream of costs and revenues Apply discount rate to determine yield Value in year n – Cost/Revenue / 1 + 𝑖 𝑛 i = interest rate, n = year Economic Analysis Same Principle Uses economic costs and benefits Uses economic discount rate
24
Economic Discount Rate
Social discount rate Foregone investment alternatives Alternative uses of government funds Foregone benefits Social perceptions regarding value of benefits now rather than later Low income, limited benefits, assign high value at margin Economic growth, assign lower value to benefits Thus with high economic growth projections, use a higher discount rate Typical Discount Rates – WB Projects 10 – 12% opportunity cost of capital +/- 6% based on social perceptions of benefits, historic growth rates
25
Net Cash Flow Net Cash Flow Stream of costs and benefits
Project economic life Do discounted benefits exceed discounted costs? Cost and Benefit Stream Year 1 2 3 4 5 6 7 8 9 10 11 12 Capital Investment 250 500 50 Operating Cost 1 Operating Cost 2 Operating Cost 3 14 16 15 18 A Total Cost 67 21 23 22 25 19 Benefit 1 85 90 95 92 100 Benefit 2 Benefit 3 35 B Total Benefits 130 135 140 137 145 B - A Net Cash Flow -250 -500 63 114 117 115 120 111 113 Net Present 6% $29.62 EIRR 6.8%
26
Sensitivity and Risk Analysis
How robust are the findings? Test sensitivity of EIRR, NPV to key inputs/assumptions Sensitivity analysis Vary value of key assumptions over a range of values Switching values What value of each input causes the NPV to become negative Use ‘what if’ analysis in Excel (under Data), and ‘goal seek’ Integrated risk analysis Uses Monte Carlo simulation to calculate probability distribution for EIRR/NPV using probability-weighted values for inputs
27
Distribution Analysis
Identify winners and losers Poverty level Gender Age Ethnicity Religion Is the project well targeted in terms of national goals, priorities?
28
Shindand Electrification
What is our objective? What were the alternatives? Is our proposal least cost?
29
Cost-benefit stream - Shindand
Cost Benefit Analysis -- Shindand 2018 2019 2020 2021 2022 2023 2024 2025 2026 2039 Costs Benefits Net Cash Flow NPV EIRR
30
Shindand – Demand Forecast Number of New Customers
Number of Customers Notes Year 1 Year 5 Year 15 Residential 10000 Annual Growth rate of 8%, years 1-5, 5% years 6-15 Commercial 2000 Initial connections 10% of ultimate demand Government 15 20 25 Agricultural 200 700 1000 Military Airport 1 50% load in year 1, 80% in year 5, 100% in year 15 Industrial Customers 10 40 100 Big Health Facility 4 Small Clinic 45 50 Mosque 35 38 Education Institutes From feasibility study
31
Shindand – Forecast Peak Demands
Total Estimated Demand (kVA) Total Active Demand (kVA) Year 1 Year 5 Year 15 Residential 5000 6802 11080 Commercial 1000 1360 2216 Government 1500 2000 2500 Agricultural 1200 4200 6000 Military Airport 8000 10000 Industrial Customers 15000 Big Health Facility 200 800 Small Clinic 300 540 600 Mosque 350 380 Education Institutes 100 250 Total Active Demand 9950 18083 34027 Total Diversified Demand 7960 14466 27221
32
Shindand – Forecast Demand - MWh
Year/Tariff Class 1 2 3 4 - Residential Commercial Government --
33
Herat Region – Average Tariffs
Average Electricity Tariff - Herat - $/kWh Residential 0.0534 0.0667 Commercial 0.1379 0.1724 Government 0.1365 0.1707 Holy places 0.0536 0.0670 NGOs 0.1372 0.1716 Registered Companies 0.0819 0.1024 Unregistered Companies 0.1419 0.1773 All 0.0669 0.0836
34
Consumption and Payments - Without project case
Newly Connected Customers Average Consumption & Price without grid kWh/mo Source $/kWh Residential 21.09 Survey 0.40 Commercial 96.59 1/3 grid 0.29 Petrol Gen Government Holy places 87.85 1/2 grid 0.49 1 MWp SHS NGOs Registered Companies 3,010.52 25% grid 0.26 Diesel Gen Unregistered Companies 638.37 Average for Companies 1,824.44 School = mosque Health Centre =commercial
35
Consumer Surplus For each class of customer –
Total consumption per year without grid X [Cost per kWh without grid minus Tariff] = Total consumer surplus per customer per year
36
WTP Benefits in year n – for each customer class
Number of new customers in year n X kwH per customer per year Tariff + Surplus benefit per customer
37
Costs Capital Cost Operating and maintenance costs
Cost estimate Adjusted for amount spent in each year Minus taxes and duties Operating and maintenance costs 15.5 % of sales based on financial statements Cost of incremental power supply Marginal source is imports Adjust cost per kWh to reflect transmission/distribution losses
38
Other Avoided carbon emissions from diesel/gasoline generators
Offset by incremental generation in source country Diesel emissions 780 t/GWh CCGT 370 – 403 t/GWh Carbon – USD 30/ton
39
Further reading L. Squire, H. VanderTak, ECONOMIC ANALYSIS OF PROJECTS, Baltimore, Johns Hopkins University Press, 1975 J. Price Gittinger, ECONOMIC ANALYSIS OF AGRICULTURAL PROJECTS. Economic Development Institute The World Bank. 1984 Guidelines for Economic Analysis of Power Sector Projects : Renewable Energy Projects. World Bank Washington, DC. © World Bank. (2 volumes) Handbook on Economic Analysis of Investment Operations, World Bank, 1998 Guidance Note: Greenhouse Gas Accounting for Energy Investment Operations, World Bank, Washington, DC, 2013
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.