Community Update Project Overview Maximizing Benefits

Similar presentations


Presentation on theme: "Community Update Project Overview Maximizing Benefits"— Presentation transcript:

1

2 Community Update Project Overview Maximizing Benefits
Minimizing Impacts LADOT Preferential Parking Community Update

3 Much-Needed Affordable Housing/Housing and Community-Oriented Design
Project Overview HERE IS A SITE OVERVIEW, YOU CAN ALSO SEE WHERE THE PROPERTY LINE RUNS BY THE COLORED SHADING

4 Much-Needed Affordable Housing/Housing and Community-Oriented Design
221 apartment rental homes; including 19 affordable 4 stories Two-levels of underground parking; 384 parking spaces 294 bike parking stations 5,000 sq ft publicly accessible green and open space Project Overview

5 Maximizing Benefits Increasing the Number of Street Trees
Our team will be removing 36 trees on the project site and replacing them with 102 new trees. Maximizing Benefits TREES: ON WEST SIDE OF PROPERTY ARE ELMS (OF WHICH 3 ARE DISEASED) AND PEPPER TREE (WHICH ARE CONSIDERED A WEED), IF ASKED [WHAT TYPE OF TREES WILL BE THE REPLACEMENTS?] THE TYPES OF TREES TO BE PLANTED ARE AS FOLLOWS: MARINA STRAWBERRY TREE PURPLE LEAF EASTERN REDBUD DESERT WILLOW DYNAMITE CRAPE BLUE PALO VERDE CANARY ISLAND PINE CHINESE ELM TREE

6 Maximizing Benefits Dedicating a Rideshare Drop-Off/ Pick Up Area
As a volunteered condition, a dedicated rideshare drop off/pick up located outside separate from the the street to preserve the path of travel. Maximizing Benefits

7 Maximizing Benefits Enhancing Walkability and Safety
Clean up / design / installation of beautified landscaping Creation / improvement of sidewalks Installation of enhanced lighting Maximizing Benefits

8 Implementing Community-Sensitive Construction Measures: Parking
Construction worker parking will be prohibited on residential streets around the project site Minimizing Impacts

9 Implementing Community-Sensitive Construction Measures: Pile Driving Reduction
Pile install is required for foundation support of the building. La Terra dedicated time and resources to redesign of the foundation to reduce the required number of piles from 100 to only 3. As a result, the pile driving is reduced to a 2-4 day construction process, while still maintaining the structural stability of the building. Minimizing Impacts

10 Implementing Community-Sensitive Construction Measures: Hours
Construction hours will comply with LAMC allowed hours indicated in their “Good Neighbor Construction Practices” guidelines We will collectively coordinate with neighbors to best attempt to schedule construction activity that may be intrusive to avoid early morning hours on Saturdays Minimizing Impacts

11 LADOT Preferential Parking
Area Overview LADOT Preferential Parking Above: Map of the community-proposed streets for the LADOT Preferential Parking District. Please note, this process will be initiated and lead by residents working in conjunction with LADOT

12 LADOT Preferential Parking
Process LADOT Preferential Parking

13 LADOT Preferential Parking
Permit LADOT Preferential Parking

14 Thank You! Pinnacle360hoover.com | | Hotline: (213)