Presentation is loading. Please wait.

Presentation is loading. Please wait.

Liquid Xenon Detector Xenon Detector Group 2018/11/18.

Similar presentations


Presentation on theme: "Liquid Xenon Detector Xenon Detector Group 2018/11/18."— Presentation transcript:

1 Liquid Xenon Detector Xenon Detector Group 2018/11/18

2 Cryostat Construction PMT Cryogenic/Gas System
Contents Cryostat Construction PMT Cryogenic/Gas System (Calibration  Carlo’s presentation) Liquid H2 Target and NaI Detector Slow Control Measurements of UV Light Reflection on Al and PEEK Schedule 2018/11/18

3 Vessels Windows Status & Schedule
Cryostat Vessels Windows Status & Schedule 2018/11/18

4 Cryostat Construction
The main construction activities: The main flanges are assembled, welded and pre-machined. All parts of the vessels are prepared and assembled. The cold and warm vessel are leak tested using provisory covers. The two vessels are machined, providing the necessary apertures. The windows are welded on the body. Leak and pressure tests are performed. The phototube support structure is installed and adjusted. The attachments to fix the structure are welded on the cold vessel. Temperature sensors and heaters are installed. The two vessels are assembled together. The connection between them are done. Bellows are welded. A leak test of those weld is done. A cryogenic test is performed. Another leak test after the cryogenic test is repeated. The windows construction are done in parallel: Prepare frames, steel sheet, honeycomb panel, and test box. Welding of the parts. Leak test of the welding Installing the honeycomb panel Pressure test with instrumentation is repeated. Leak test after the pressure test. The window are installed on the chamber. } Step 1 } Step 2 } Step 3 } Step 4 } Step 1 } Step 2 } Step 3 2018/11/18

5 Construction Procedure
Assemble and weld Leak test Machining Warm Pressure & Leak test Assemble and weld Assemble two vessels Weld Chimneys Leak & Cryogenic tests Install Windows Install sensor, PMT support attachment, etc. Assemble and weld Leak test Machining Cold Assemble and weld Pressure & Leak test Step Step Step Step 4 2018/11/18

6 Warm/Cold Vessels Dec/ 2005 Feb/ 2006 Apr/ 2006 Apr/ 2006 2018/11/18

7 Leak Test before Machining
The cold and warm vessels were leak tested using provisory covers. Cold vessel test April-2006, Warm vessel 8-May-2006 Some problems were found in the cold vessel Excessive deformation were found during the test. The provisory covers were only touching the flanges. Sealing plaster was used to make them vacuum tight. An internal structure were added to control the deformation of the cold vessel. No Cover 1Bar Pressure Outer Vessel OK provisory Covers Finite Element Analysis Excessive deformation of the inner flange. The real covers maintain the shape. However we have a concern on the integrity of cold sealing, whether a local slip can occur between the cover and flange. With Cover 1Bar Pressure 2018/11/18

8 Machining 1 Cold Vessel 3 Warm Vessel 2 Middle of June 4
Cu cooling pipe will be welded on the back Warm Vessel 3 2 Middle of June 4 2018/11/18

9 Bellows/Chimneys Pressure Test OK Up to Dp=4Bar 2018/11/18

10 Windows Honeycomb/CF panel Cold Window Intermediate 5mm frame
A thin foil is welded to a 5mm thick intermediate frame. Backing with a honeycomb/carbon fiber panel for the cold window. Honeycomb/CF panel Cold Window Intermediate frame Honeycomb/CF panel Weld Weld Cross section A-A’ Al honeycomb 0.4mmt window CF Intermediate 5mm frame Intermediate 5 mm frame Weld weld 2018/11/18

11 Window Test Preparation
A 5 mm intermediate frame was welded to the test box. After that the frame is cut out and welded to the vessel. Preparation of test box. 14-May-2006 Warm window test box Cold Window Warm Window Pressure Pressure Cold window test box Honeycomb/CF panel Leak test 2018/11/18

12 Warm Window Test One warm window was tested: Mechanically it was O.K.
However during the test leak was found SIMIC realized that their construction proposal for windows was not feasible. They took three days to weld the foil to the 5 mm intermediate frame and 10 days to find leaks. After that the window was leaking during the test. 2018/11/18

13 Cold Window Test One cold window was tested:
Mechanically it was NOT O.K.  Next slide The welds were leaking. SIMIC tried to repair the TIG weld using a brazing material, causing a disaster on the intermediate frame. 2018/11/18

14 Honeycomb/Carbon Fiber Panel Trouble
Mechanically the honeycomb/CF panel was NOT O.K. at Dp=3.7 bar. (Design value of the cryostat pressure tolerance is 3.0Bar) The honeycomb/CF panel broke at one side. FEA with sophisticated laminated elements  OK This buckling is attributed to local defects. Carbon Fiber Al honeycomb Transition area OK on this side 2018/11/18

15 New Design of the Windows
New design proposed by SIMIC The windows are welded directly on the bodies. A leak test is performed on this weld on the body. This design implies modification of the honeycomb… Weld weld Cold Vessel Warm Vessel Honeycomb/CF panel Cold Vessel Weld Weld Warm Vessel Turn up the edges and weld along them 2018/11/18

16 New Honeycomb/CF Panel Design
How can we solve the problem on the Honeycomb/CF panel? Change the material to avoid transition from the high modulus fiber to low modulus fiber around the edge and replace the filler material. We are contacting Hexcel ( experts for advice. Previous design 5 plies of fiber sheets on each side of the panel +45/-45/0/-45/+45 Total thickness of 0.7 mm. Around the edge we use low modulus fiber sheets to make the bend (inter laminar method) and a filler material of epoxy with glass micro spheres (beads) inside. The honeycomb thickness is 19 mm and the density is 50 kg/m3. New design 8 piles of fibers Total thickness of 1.0mm A thicker honeycomb 24 mm with the same density (50kg/m3) to increase the inertia A fabric fiber with an intermediate modulus will be used to avoid the transition. Thus internal reinforcement will be made around the edges. 2018/11/18

17 Xenon Detector Platform Installation
Movable stage for the xenon detector Operating position “Parking” position Mounting activity at PSI by Pisa group started on 4/June and finished on 9/June Tested successfully with ton weights on it. 2 1 3 2018/11/18

18 Necessary Operation After the windows are welded on the two vessel, we need to do the following operation: A leak test on the window welds A pressure test closing all the aperture and covers. After pressure tests of two vessels are done, we have to perform a leak test again. The PMT support structure is installed and adjusted. The attachments are welded on the cold vessel. A temperature sensors, heaters are installed. The two vessels are assembled together. The connection between them are done. Bellows are welded. A leak test of those weld is done. A cleaning and hand polishing is done on the cold vessel. A cryogenic test is performed. After the cryogenic a leak test is performed again. 2018/11/18

19 Cryostat Construction Schedule
Week June: Warm vessel: Complete welding of all nozzle (3 days). Cold vessel: Complete welding of CF 100 flanges, braze the cooling tube (3 days) Welding test of the windows (2days) New foil fabrications (4 days). Define Honeycomb materials and geometry (2 days) delivery (15 days) Week June: Test box preparation: warm window test box (1day); cold window test box (3days). Welding of warm window on the test box (2 days) + helium leak test (1day)+ mechanical test (1day). Machining of cold vessel (5 days). Week 3-7 July: Welding of cold window on the test box (2days)- helium lesk test (1day). New honeycomb delivered – mechanical test cold window (1day). Welding window on cold vessel (2days) Week July: Test warm vessel (2days). Helium test of cold window (1day) Honeycomb mounting and cold test preparation (1day) Pressure test cold vessel, 4 bar, (1day) Week July: Dry out cold vessel (1day)- helium leak test of metallic sealing on covers (1day). Mounting of the phototube supporting structure (2days) Welding of the L bracket to hold the arches (phototube supporting structure) (1day) Installation of super insulation and temperature sensors (1day) Week July: Alignment and vessel integration (3days) Bellows welding (3day) Week 31July - 4 Agust: Helium leak test on the welds (1day) Internal polishing (3days) Cleaning and dryout (2days) Week August: Preparation and installation of equipmnets for the cryocenic test (1day) Cryogenic test (4days) Week August: Helium leak test of cold vessel (2days) Prepartation of shipmenet (2days) Week August: Delivery to PSI 2018/11/18

20 Final Delivery Insertion to holders Room temperature test
PMT Final Delivery Insertion to holders Room temperature test 2018/11/18

21 PMT Final Delivery and Test Status
Vacuum break Chlorine Newly delivered PMTs (~250) in 2006 LP 4th PMT test 100 new PMTs tested, finished on 17/Mar/2006 Pisa test facility Test of 102PMTs finished on 12/May/2006 50 more PMTs (delivered in June) will be tested. Delivered PMTs (We need 846 PMTs in total) 870 PMTs ordered and delivered 107 PMTs returned and ~120 PMTs will be returned (t>0.3mm) to Hamamatsu 264 PMTs delivered for replacement Al Silica Metal Tube HCl Hamamatsu investigated further 5 PMTs w/ large tilt but w/o any remaining chlorine High temp/humidity test  OK t 2018/11/18

22 PMT Installation 5 6 1 7 2 8 3 4 9 2018/11/18

23 PMT Installation cont’d
Window slope measurement Done for all PMTs Installation status Side : 40 (out of 48) holders ready. PMTs with large D(≥0.3mm) have been replaced. Once installed, but later Hamamatsu provided replacements. Outer : 18 (out of 22) holders ready Inner : 18 (out of 24) holders ready Top/bottom: not started yet Inner holders are located in a vacuum chamber (LP cryostat) to remove humidity as much as possible before installation to the detector Inner, Outer, Top/Bottom Side 2018/11/18

24 PMT test before installing into the detector
Signal check before installing into the detector NIM HV module Oscilloscope Measurements All cable connections are checked simultaneously Current (mA) at 800V Pedestal distribution 2018/11/18

25 Assembly hut Air Filter 2018/11/18

26 Liquid H2 Target and NaI Detector
2018/11/18

27 p0 Calibration Anti Counter p-pp0n p0(28MeV/c)  g g 54.9 MeV < E(g) < 82.9 MeV Need Anti-Counter (NaI) at the opposite side Movable to scan the acceptance Timing counter (Pb+Scinti) in front of the NaI detector for timing calibration Another interesting possibility Abandon NaI detector in coincidence Detect one g with the xenon detector Convert another  in a 0.1X0 converter close to the H2 target Detect conversion and measure conversion point with a “special counter” Measure e+ branch of the pair in the chambers H2 target and NaI detector with a movable stage are essential. g up p0 g down target q Eg 170o 175o q Eg Eg p0 Requiring q>170o FWHM = 1.3 MeV Requiring q > 175o FWHM = 0.3 MeV 2018/11/18

28 Liquid Hydrogen Target
Liquid Helium Cooling Installed to the position through the insertion tube Thin entrance window (100 micron Mylar) 2018/11/18

29 Liquefaction Test Several tests
Super-insulation Material of LHe inlet In the last test we liquefied some hydrogen Terminated because of exhausting available helium 2018/11/18

30 NaI Mover Construction
3x3 NaI crystals For covering the xenon detector acceptance +/-30cm in z +/-60o in f and +/-30o in q All motions are motor-driven and remotely controllable 2018/11/18

31 Detector Preparation Status
3x3 NaI crystals Readout electronics APD Hamamatsu S 2 on 1 crystal BD voltage ~400V, 5mmx5mm Pre-AMP GND GN-0261 (Shaper) Temperature monitor and control PT100 Peltier Plastic scintillator (+Pb converter) with fine-mesh PMTs for timing calibration Simulation Just started 2018/11/18

32 Cryogenic/gas system 2018/11/18

33 Cryogenic/Gas system 2018/11/18

34 Slow Control 2018/11/18

35 Slow Control Xenon Detector System Storage Gas purifier 1000L dewar
pressure, valves Gas purifier valves, flow meter, pressure, pressure reducer control 1000L dewar valves, pressure, temperature, refrigerator control, LN2 flow, heater Detector Valves, pressure, temperature, surface level, strain gauge, refrigerator control, LN2 flow, heater Liquid purifier Valves, surface level, level control, LN2 flow NaI mover Motor control, position sensor 2018/11/18

36 Status History Display
Scheme SCS Module 2 Gas Purifier SCS Module 1 Storage SCS Module 0 NaI Mover SCS Module 4 Detector liquid Purifier MSCB Ethernet Adapter SCS Module 3 1000L Dewer Network Xenon SC Backend PC Backend backup Main Slow Control Logging & Alarm Xenon LabView Interface Status History Display The backend PC handles signals between SCS modules 2018/11/18

37 Measurements of UV light reflection on Al and PEEK
We asked spectroscopic LENS laboratory in Firenze to perform some measurements and to provide us experimental data about the properties of PEEK (used in the inner holders) Aluminium (used in the others) (we are very grateful to them for their kindness and helpfulness). Reference frame for the measurements: qinc = 300  qref =+300 qinc = 450  qref = 00 qinc = 600  qref =-300 qinc qref Laser beam Results indicates >10% reflection on Al negligible on PEEK Checking with LP data linc = 160 nm (UV light). Movable optical prism 2018/11/18

38 Schedule 2018/11/18

39 Cryostat delivery at the end of August
Schedule Cryostat delivery at the end of August PMT assembly installation and cabling takes 35 days. Detector setup (evacuation, liquefaction, purification…) takes 45 days Detector can be ready in November DAQ can be started when liquefaction finishes p0 calibration at the end of 2006 run 2018/11/18

40 Now on Google Calendar (public)
Up-to-date Schedule Now on Google Calendar (public) 2018/11/18


Download ppt "Liquid Xenon Detector Xenon Detector Group 2018/11/18."

Similar presentations


Ads by Google