Presentation is loading. Please wait.

Presentation is loading. Please wait.

ATom Science Meeting Armstrong Flight Research Center July 23, 2015

Similar presentations


Presentation on theme: "ATom Science Meeting Armstrong Flight Research Center July 23, 2015"— Presentation transcript:

1 ATom Science Meeting Armstrong Flight Research Center July 23, 2015
Dave Jordan ATom Project Manager Erin Czech ATom Deputy Project Manager

2 ATom Kick-Off Meeting Project Pronunciation Guide
ĀTom (do you say ātmospheric?) Ătom American Samóa (wrong syllable accented) American Sámoa Pago Pago (not pronounced phonetically) Pahngo Pahngo bĕst, FĕdEx, Pĕppers bēst, FēdEx, Pēppers (all e’s long in New Zealand)

3 ATom Kick-Off Meeting Project Pronunciation Guide
Wofsy????????

4 ATom Science Meeting ATom-1 Deployment Schedule

5 ATom Science Meeting ATom-1 Deployment Schedule

6 ATom Kick-Off Meeting ATom-1 Deployment Schedule
Palmdale Phased instrument team arrivals begin latter part of June All teams ship all equipment to Palmdale ESPO will ship all teams resupply equipment to Christchurch Additionally ESPO will ship WAS, AO2/Medusa and PFP canisters/flasks to Kona and Azores Test flights 7/15 & 8/2 Deployment begins 8/4

7 ATom Kick-Off Meeting Site Manager Concept
ANC SM1 KOA SM2 PPG SM3 CHC SM4 PUQ SM5 ASI TER SFJ PMD Notional Site Manager Assignments SM1 Erin Czech SM2 Dave Jordan SM3 Marilyn Vasques SM4 Quincy Allison SM5 Jhony Zavaleta

8 ATom Kick-Off Meeting Site Manager Concept
Site Manager on site 2-3 days prior to a/c arrival Coordinates with airport officials, FBO and consumables supplier Immigration and customs (as req’d) IMPERATIVE THAT ALL FOREIGN NATIONALS ARE IDENTIFIED LONG BEFORE EACH DEPLOYMENT STARTS Site Manager local POC for all instrument requirements Site Manager to provide local orientation document upon a/c arrival

9 ATom Kick-Off Meeting Deployment Days
Arrival Day Instrument postflights A/C postflights LN2 and dry ice replenishment Get rental cars and check into hotel Instrument Access Day A/C open and powered (schedule TBD) Instrument issues addressed Hard Down Day A/C open for short period for cryogen servicing Departure Day Flight planning A/C preflghts Instrument preflights

10 ATom Kick-Off Meeting Deployment Travel
Room Block will be set up for each deployment site Working with hotels to include flexibility with respect to arrival date Cooperative Agreement participants’ travel to be facilitated through Wyle (ARC Support Contractor) Airlines reservations (as needed) Hotel reservations Rental Vehicle reservations (2-3 persons/car) Reimbursements for M&IE

11 ATom Kick-Off Meeting Site Specific Information
Anchorage Primary hangar with back-up for January 2017 Only needed night prior to departure Potassium acetate and sodium formate used to de-ice runways LN2 and dry ice available M-F Kona WAS, AO2/Medusa and PFP flask/canister swap Courtyard Marriott ( ≈ 8 miles from airport) Pago Pago LN2 and dry ice not available Tradewinds Hotel ( ≈ 1.5 miles from airport)

12 ATom Kick-Off Meeting Site Specific Information
Christchurch LN2 and dry ice available (M-F) Arranging support from Pacific Architects and Engineers (PAE) (currently support NSF Deep Freeze and NASA SOFIA programs) Envisioning a shipping container with all instrument teams’ resupply material sent from Palmdale Sudima Hotel (within walking distance of PAE airport) Punta Arenas LN2 and dry ice available (though pricey) DC-8 has been there every year since 2009

13 ATom Kick-Off Meeting Site Specific Information
Ascension Island Jointly operated USAF/RAF base No LN2 or dry ice available Must have proper entry permit (business/research) prior to arrival Must have medical insurance that covers treatment and emergency evacuation by air (suggested £1M) prior to arrival The Azores (Lajes Field) Joint military/commercial airport operated by Portuguese Air Force USAF detachment LN2 and dry ice may be available through university Greenland Thule out for ATom-1 (runway work) Kangerlussuaq planned for ATom-1 only