S.R. 30A / U.S. 98 / Panama City Beach Parkway
Project Development & Environment (PD&E) Study From Mandy Lane to Thomas Drive Intersection Bay County, Florida Financial Project ID No: , ETDM No: 14208 TPO/CAC/TAC PRESENTATION | December 7, 2016 The Florida Department of Transportation, or FDOT, District Three, is conducting this public meeting concerning planned future transportation improvements along S.R. 30A / U.S. 98 / Panama City Beach Parkway
2
Purpose of Briefing Status Update for upcoming Alternatives Workshop Receive input
3
Project Location S.R. 30A / U.S. 98 / Panama City Beach Parkway
From Mandy Lane to Thomas Drive Intersection Approximately 7.9 miles in length Bay County Panama City Beach Design Year 2045
4
Purpose and Need Add two lanes of capacity to the four lane section of U.S. 98 in order to address existing and projected future failing level-of-service Certain roadway segments are currently over capacity Project is needed to relieve congestion Enhance safety and mobility Improve emergency evacuation Include sidewalks and bicycle lanes
5
Existing Characteristics
4 Lanes Divided: Mandy Lane to west of Richard Jackson Boulevard & East of Richard Jackson Boulevard to Cauley Avenue (45 mph/55mph) 6 Lanes Divided: West of Richard Jackson Boulevard to East of Richard Jackson Boulevard 4 Lanes Undivided w/ 2-Way Left Turn lane: Cauley Avenue to Thomas Drive Posted Speed: 45 mph/55 mph Discontinuous sidewalks and bicycle lanes Existing 200-ft Right-of-Way (R/W)
6
Proposed 6-Lane Suburban Typical Section
100’ 100’ 7’ 11’ 11’ 11’ 11’ 11’ 11’ 11’ 11’ 7’ 11-ft Lanes 22-ft Median 10-ft Shoulder (7-ft paved) 5-ft Sidewalks 200-ft R/W Design Speed 45 mph
7
Public Involvement Public Involvement Plan Meetings with Agencies Local Government Coordination Meetings with the Public Project Website
8
Public Kick-Off Meeting Held
Date: April 21, 2016 Location: Panama City Beach Lyndell Senior Center Lyndell Lane Panama City Beach, FL 42 people in attendance including project staff Key issues of concern were: Intersection improvements Noise impacts Drainage Traffic congestion Multimodal accommodations
9
Alternatives Public Workshop
Study Schedule and Funding Begin Study: December 18, 2015 Receive Location Design Concept Approval (LDCA): January 2018 2015 2016 2017 2018 Project Initiation Kick-off Meeting Environmental & Engineering Analysis Alternatives Public Workshop Draft Environmental & Engineering Documents Final Environmental & Engineering Documents Location Design and Concept Approval Environmental & Engineering Data Collection Public Hearing Winter Spring Summer Winter Winter Summer Fall Winter Future phases include: - Design - Right-of-Way - Construction We Are Here Today
10
Alternatives Public Workshop
Date: February 16, 2017 Location: Panama City Beach Lyndell Senior Center Lyndell Lane Panama City Beach, FL Time: 5:30 pm to 6:30 pm
11
Contact Information FDOT Project Manager Sherry Alaghemand, P.E. FDOT, District 3 (888) , extension 1510 FDOT Public Information Director Ian Satter FDOT, District 3 (888) , extension 1205 ,P.E.