Presentation is loading. Please wait.

Presentation is loading. Please wait.

LESSON 3 Lot Sizing and Buffering

Similar presentations


Presentation on theme: "LESSON 3 Lot Sizing and Buffering"— Presentation transcript:

1 LESSON 3 Lot Sizing and Buffering
29 August 2014

2 Lesson Objectives Upon completion of this lesson, you should be able to: Analyze various lot sizing techniques Explain how buffering mitigates four categories of uncertainty Differentiate the role of safety stock and safety lead time Interpret the relationship between set-up time and cyclic inventory levels Given a scenario, propose techniques to reduce changeover time

3 Lesson Topics This lesson will cover the following topics:
Lot-Sizing Techniques Buffering Safety Stock Cyclic Inventory and Set-up Time Reducing Changeover Time

4 What’s In It For Me? Gain insight into models used by contractors to handle: Inventory orders from suppliers Optimize different inventory use across a common machine

5 Lesson Introduction How do companies determine the quantity of materials to requisition across multiple orders and product lines?

6 Lot-Sizing Techniques
Lesson Topics: Lot-Sizing Techniques Buffering Safety Stock Cyclic Inventory and Set-up Time Reducing Changeover Time

7 Lot-Sizing Techniques
Inventory Lot Sizing: Used to minimize cost Cost of holding Cost of procurement setup and/or ordering Techniques start out with idealized models, such as having stable and known demand. From there – we tweak. Limited value for unstable Master Planning Schedule (MPS) Tend to be sub-optimal as they only consider one item at a time

8 Types of Lot-Sizing Techniques
Common Lot-Sizing Techniques Lot-for-Lot (LFL) Economic Order Quantity (EOQ) Periodic Order Quantity (POQ)

9 Data Required for Lot Sizing
Demand Net Requirements Data Cost Data Order / Setup Cost (Cs) Inventory Carrying (Holding) Cost (Ch)

10 Example: Data for Lot Sizing
Table 1: Each unit of Z uses one A and two Bs Table 3: Cost Data Item On Hand (units) Lead Time (weeks) Scheduled Receipts Z 50 N/A None A 1 20 in week 1 B 100 2 50 in week 2 Item Cs Ch Z $3 A $300 $1 B $200 Item Z has no lead time because Z is manufactured and not ordered Cs = setup or order cost (each time an order is placed) Ch = periodic carrying (holding) cost rate ($/unit/period) Week 1 2 3 4 5 6 Quantity 40 20 100 50 Table 2: Demand Data – MPS for Z

11 Lot-for-Lot (LFL) Lot size matches the net requirements in each period: No excess inventory is carried May lead to: Too many orders based on financial concerns Irregular-sized orders Uneconomical orders – ex: Less than truckload amounts, or less than a supplier’s desired minimum purchase amount Week 1 2 3 4 5 6 Quantity 40 20 100 50 Demand Data – MPS for Z

12 Economic Order Quantity (EOQ)
EOQ lot size is calculated as follows: EOQ = 2𝐶s𝐷 𝐶ℎ Item D Cs Ch EOQ Z $3 A 350 $300 $1 458 B 700 $200 529 Optimal order quantity may increase lot size Increases average inventory on hand May reduce frequency of orders Assumes demand is constant, reoccurring, and known Cs = setup or order cost (each time an order is placed) Ch = periodic carrying cost rate ($/unit/period) D = Annual demand

13 What if demand changes over time?
Conundrum What if demand changes over time?

14 Periodic Order Quantity (POQ)
POQ is calculated as follows: POQ = 𝐸𝑂𝑄 𝑑 = 2𝐶s𝐷 𝐶ℎ 𝑑 Cs = setup or order cost (each time an order is placed) Ch = periodic carrying cost rate ($/unit/period) d = average periodic demand(days, weeks, etc.) Week 1 2 3 4 5 6 Quantity 40 20 100 50 Demand Data – MPS for Z Optimize cost data to figure out a periodic order frequency Periodic order quantity varies with each order because it sums the net requirements over a set number of periods (number of periods based on the periodic order frequency)

15 Question and Answer This type of Lot Sizing technique matches the net requirements in each period so that the orders produced are the exact amount needed Lot-for-Lot (LFL) Economic Order Quantity (EOQ) Periodic Order Quantity (POQ) Lean Manufacturing

16 Question and Answer Which lot-sizing technique is used to compute minimum costs for an optimal order quantity when demand is assumed to be constant, reoccurring, and known? Just in Time (JIT) system Lean Manufacturing Economic Order Quantity (EOQ) Periodic Order Quantity (POQ)

17 Question and Answer Which lot sizing technique is used to calculate an optimal time between orders based on cost concerns? Economic Order Quantity (EOQ) Lean Manufacturing Lot-for-Lot (LFL) Periodic Order Quantity (POQ)

18 Buffering Lesson Topics: Lot-Sizing Techniques Buffering Safety Stock
Cyclic Inventory and Set-up Time Reducing Changeover Time

19 Materials Requirements Planning (MRP) Uncertainties
Sources of Uncertainty Timing Quantity Demand Requirements shift from one period to another Requirements for more or less than planned Supply Raw material orders not received when due Raw material orders received for more or less than planned -or- Losses in raw material quantities due to quality problems

20 Buffering Mitigates performance risks from uncertainties
Role increases as: Fluctuation in demand increases Level of uncertainty increases Limited value for unstable MPS

21 Buffering Techniques Safety Stocks Safety Lead Time
Hold in inventory more than required Release P.O.’s (order releases) early, ahead of contracted lead time requirements Quantity buffer (demand or supply uncertainty ) Timing buffer Preferred when uncertainty is quantity related Preferred when uncertainty is timing related

22 Other Buffering Mechanisms
Techniques to reduce or buffer uncertainty: Freeze the MPS close to production time Increase forecast accuracy Use priority systems Improve quality Work with vendors

23 What are two buffering techniques?
Question and Answer What are two buffering techniques? Total Quality Management (TQM) & Drum-Buffer-Rope (DBR) Economic Order Quantity (EOQ) & Periodic Order Quantity (POQ) Customer Relationship Management & Modeling Safety Stock & Safety Lead Time

24 Question and Answer Which of the following is a buffering technique?
Priority system for moving parts through a shop Expenditure system for determining the cost of inventory Periodic inventory system for accounting of raw materials

25 Safety Stock Lesson Topics: Lot-Sizing Techniques Buffering
Cyclic Inventory and Set-up Time Reducing Changeover Time

26 Safety Stock Inventory without safety stock Quantity Reorder Point
High Inventory Low Inventory Time Quantity Reorder Point

27 Safety Stock Provides protection for uncertainty
Defines a minimum level of inventory Safety Stock (SS) protects factory from uncertainty in supplier lead times and customer demand SS Level High Inventory Low Inventory Reorder Point

28 Safety Stock (cont.) Safety stock should be set to accommodate:
Unplanned orders Deviations from the master schedule Delays in receiving material from suppliers have some quantity available for production Mismatch between physical inventory and computer records

29 Safety Lead Time Because of unforeseen events, it may take more time than the planned lead time to manufacture or procure an item

30 Question and Answer If this event occurs, the MRP system should generate orders sufficient enough to maintain the specified level of safety stock and desired inventory. Inventory is depleting sporadically Inventory reaches maximum capacity Inventory will consume part or all of the safety stock before next receipt Inventory reaches equilibrium

31 Question and Answer Which of the following is not a reason for adding safety lead time to a schedule? To give vendors as much time as they want to deliver their goods To provide a buffer for unforeseen events A vendor has a record of being late

32 Cyclic Inventory and Setup Time
Lesson Topics: Lot-Sizing Techniques Buffering Safety Stock Cyclic Inventory and Set-up Time Reducing Changeover Time

33 Cyclic Inventory and Setup Time
The relationship between cyclic inventory and setup time is an area where firms can identify and reduce waste

34 Shared Resources Manufacturing firms share resources within their organizations Ex: The stamping press is a shared resource in a company

35 Shared Resources (cont.)
Each day, the dies of the stamping press are changed over to manufacture different parts Removable dies are changed over daily

36 Example: Cougar Armored Fighting Vehicle
Stamping Press Cyclic Inventory Stamping Press Production Cycle Mon Left door Tues Right door Wed Rear door Thu V-shaped hull Fri 30 minutes to set up machine

37 Example: Cougar Armored Fighting Vehicle (cont.)
All products are needed simultaneously All products are consumed continuously as the vehicles are being assembled Stamping Press Production Cycle Mon Left door Tues Right door Wed Rear door Thu V-shaped hull Fri

38 Minor Changeover Within a Family Major Changeover Between Families
Product Wheel Used when multiple products are made on a single line or on a single piece of equipment (minimizes setup time) Product Family A Product Family C Product Family D A C B Product Family B IDLE Minor Changeover Within a Family B-1 B-2 B-3 B-4 Major Changeover Between Families

39 What causes cyclic inventory to occur?
Question and Answer What causes cyclic inventory to occur? Excessive inventory Safety stock Safety lead time Multiple items requiring the same resource

40 Question and Answer What tool is used to sequence product cycles with manufacturing resources? Product wheel Production schedule Ishikawa diagram Comparative matrix

41 Reducing Changeover Time
Lesson Topics: Lot-Sizing Techniques Buffering Safety Stock Cyclic Inventory and Set-up Time Reducing Changeover Time

42 Reducing Changeover Time
Changeover time is: Wasteful Non-value added activity Requires a firm’s asset to be unproductive Wasteful Activity in Lean Production: “An activity that consumes resources but adds no value”

43 Pit Crew Changeover Manufacturers goal is similar to a race car pit crew Optimize (minimize) setup time Pit crews practice reducing changeover by tenths of a second

44 Single Minute Exchange of Dies
Single Minute Exchange of Dies’ (SMED) goal is to reduce machine set-up time Developed by Dr. Shigeo Shingo of Toyota Reduced Toyota’s changeover time: Many of the practices that Dr. Shingo used have revolutionized today’s manufacturing 4 hours ½ hours minutes

45 Change dies (or parts) out in less than 10 minutes
SMED Concept Reduce to a single digit! Results in smaller production batch sizes Produce only what is demanded by the customer Change dies (or parts) out in less than 10 minutes

46 SMED Steps for Reducing Changeover Time
Step 1: Document the changeover steps Describe all tasks being performed in sequence Classify the task as either internal or external Internal activities: Activities performed while the asset is idle External activities: Activities performed before or after changeover while the asset is operating

47 Example: Document the Changeover Steps
Description Time Cumulative Time Internal or External 1 Look for and put on gloves 0:02:21 E 2 Disconnect minor hoses 0:01:00 0:03:21 3 Disconnect major hoses (includes looking for a wrench) 0:02:30 0:05:51 4 Retrieve set-up cart 0:00:25 0:06:16 5 Raise bottom ram 0:00:23 0:06:39 I 6 Disconnect top mold, removing bolts from front 0:00:54 0:07:33 7 Reattach bolts – front and back 0:00:57 0:08:30 8 Lower tooling 0:00:27 0:08:57 9 Take magnet off 0:00:19 0:09:16

48 SMED Steps for Reducing Changeover Time (cont.)
Step 2: Determine which internal changeover activities can be made into external changeover activities Ask: “Can this task be done prior to idling the machine/work center?”

49 SMED Steps for Reducing Changeover Time (cont.)
Step 3: Transform as many internal activities to external activities as possible Examples of internal activities transformed to external activities: Getting tools Moving the next die to the press Moving the next material to be processed to the press Warming up molds

50 Example: Transformed External Activities
Step Description Time Cumulative Time 1 Disconnect minor hoses and fasteners between base and shell 0:01:00 2 Connect shell to hoist and load onto jitney 0:02:00 3 Put shell away and return with jitney 0:04:00 4 Connect base to hoist and load onto jitney 0:05:00 5 Put base away 0:07:00 6 Load new base onto jitney 0:08:00 7 Upload base in front of press 0:09:00 8 Retrieve shell with jitney and load onto base 0:11:00 9 Attach shell to base 0:12:00 10 Connect hoses 0:13:00

51 SMED Steps for Reducing Changeover Time (cont.)
Step 4: Reduce internal changeover time Streamline all internal activities Eliminate redundancies Brainstorm ideas

52 Example: Reduced Internal Changeover Time
Step Description Time Cumulative Time 1 Disconnect hoses 0:00:20 2 Raise bottom ram 0:00:23 0:00:43 3 Disconnect top mold, remove pins 0:01:03 4 Lower tooling 0:00:27 0:01:30 14 Ram in 0:00:10 0:07:48 15 Connect hoses 0:07:58 16 Turn steam on 0:00:15 0:08:13 17 Raise ram to accelerate heating 0:08:33 18 Hook up thermal couple lead 0:08:43 Internal steps reduced further

53 SMED Steps for Reducing Changeover Time (cont.)
Step 5. Reduce external changeover time Reduce the number of workers that can feasibly and safely perform the external task Only do what is required for the setup

54 Spaghetti Diagram Before SMED reduction After SMED reduction
Operator travelled 3,215 feet 98 minutes from last piece to first piece Operator travelled 375 feet 14.9 minutes from last piece to first piece

55 Shadow Boards Manufacturer’s SMED reduction also included a shadow board

56 Other Quick Changeover Ideas
Rolling tool carts Color-coded items Scribe markings Push-button bolts Half-turn screws

57 Question and Answer This changeover technique uses five steps to reduce waste and redundancy in machine setup: Strategic method of external reduction Stamping press Single minute exchange of dies Spaghetti diagram

58 Question and Answer This time-saving organizational method can assist employees in performing quick changeover of parts on a machine: Product Wheel Shadow Board Large Parts Kanban cards

59 Summary Having completed this lesson, you should now be able to:
Analyze various lot-sizing techniques Explain how buffering mitigates four categories of uncertainty Differentiate the role of safety stock and safety lead time Interpret the relationship between set-up time and cyclic inventory levels Given a scenario, propose techniques to reduce changeover time

60 Summary (cont.) Your can now:
Look for peculiarities in how a Prime procures parts from suppliers for a contract, Understand basic inventory lot sizing methods, and Watch a shared resource perform over time and understand various ways its setup could be optimized.


Download ppt "LESSON 3 Lot Sizing and Buffering"

Similar presentations


Ads by Google