1 Fermilab Cavity Refurbishment Status J. Reid M. Slabaugh November 19, 2014 J. Reid 1

2 Fermilab Cavity 1008 Cavity # 1008 – Removed from Station 5 – Cavity downstream end cut open - Class 3 cavity October 21 - Mechanical refurbishment complete October 22 – Installed in test cave at MI-60. November 12 – Repairs completed - LCW leak on center casting cooling tube. November 24 – Finish testing and ready to ship to Booster December 1 – Ship to Booster December 2 – Ready for installation in Booster Station 9 November 19, 2014J. Reid 2

3 Fermilab Cavity 1008 November 19, 2014J. Reid 3

4 Fermilab Cavity 1008 Repairs November 19, 2014J. Reid 4

5 Fermilab Cavity 1008 November 19, 2014J. Reid 5

6 Fermilab Cavity 1008 November 19, 2014J. Reid 6 LCW Leak on braze joint

7 Fermilab November 19, 2014 J. Reid 7 Cavity 1002 November 20 - Cavity fully machined and will be mounted on a girder with bottom tuner November 24 – Mount back tuner November 26 - Mount front tuner December 1-4 – Complete plumbing and vacuum leak test December 8 – Install in test cave at MI-60 December 22 – Testing complete January 6, 2015 - Ready to install in Booster

8 Fermilab Cavity 1001 Rem oved from Station 9 Needs center casting cooling tube replaced Presently on Bridgeport mill – refurbishment not started yet November 19, 2014J. Reid 8


Download ppt "Fermilab Cavity Refurbishment Status J. Reid M. Slabaugh November 19, 2014 J. Reid 1."