50% LBNE Concept Design WCD Infrastructure. Mechanical.

Similar presentations


Presentation on theme: "50% LBNE Concept Design WCD Infrastructure. Mechanical."— Presentation transcript:

1 50% LBNE Concept Design WCD Infrastructure

2 Mechanical

3 3 WCD HVAC Large cavity and access drift cooled by 65 F drift air Once through system 100,000 cfm airflow Set by smoke extraction requirements 100,000 cfm results in ~10F temperature rise during normal operation VFD’s may be justified, however there are added costs No humidity control with once through system

4 4 WCD HVAC 2 x 100% exhaust fans for normal and emergency ventilation Exhaust fans located in 626 drift exhausting to east drift Davis cavern chilled water system left as is AORs air conditioned by local DX units Utility rooms including electrical cooled with drift air No spray chamber etc. Chiller by LBNE

5 5 WCD HVAC Cool Warm

6 Plumbing

7 7 WCD Plumbing & Fire Protection Services Potable water Purified water (50% size 8” per LBNE direction) Fire fighting water (redundant service from Yates and Ross shafts) 50% design assumes industrial water is currently provided to the 4850L (item for discussion) Drainage system Sewage Removal for the main AORs Valved and capped connection to a water mist system at the WCD. Compressed air, provided locally in LBNE’s equipment room.

8 8 WCD Plumbing Schematic

9 9 WCD Purified Water Schematic

10 Electrical

11 11 ITEMELECTRICAL CONNECTED LOAD NOTES LC Water (PMT-HV)3kWBased on May 13, 2011 RFP Table 1-200 LC-Deck100kWBased on May 13, 2011 RFP Table 1-200 LC-Balcony69kWBased on May 13, 2011 RFP Table 1-200 Crane6kW Total Estimated Detector Power 178kW With 20% Uncertainty factor 214kW20% based on LBNE requirements ITEM ELECTRICAL CONNECTED LOAD NOTES Detector Lighting – assuming 1w/sq.ft 32kW Drift Lighting – assuming.5w/sq.ft 45kW Chiller Plant – assuming 3 Tons 5kW This assumes the 140 Ton chiller electrical requirements by LBNE is already included in Table 1-200 of the May 13, 2011 RFP. Air handling Units30kW Water System431kW Based on May 13, 2011 RFP Table 1-200 Sump Pump @ 5060 Level for experiment 254kW Based on May 13, 2011 RFP Table 1-200 Sump Pump for 4850 level drainage system 156kW Utilities in Drift75kW Based on May 13, 2011 RFP Table 1-200 AORs – anticipate total load450kW Based on 100% PDR typical AOR information. Fire alarm2kW Communication12.5kW Security (future place holder)12.5kW Total Infrastructure Power1505kW 20% Spare factor1806kW Total Load – Detector + Infrastructure 2020kWIncludes 20% spare factor Total Load assuming.9 Power Factor 2244kVA WCD Experiment Electrical Loads WCD Infrastructure Electrical Loads WCD Electrical Connected Loads

12 12 ItemEmergency/Standby Connected Load Drift Lighting45kW WCD Chamber Egress lighting8kW AORs315kW Sump Pump109kW Fire Alarm1.5kW Security15kW IT System11kW Total Connected Electrical Load505kW WCD Emergency/Standby Electrical Load

13 13 WCD Infrastructure Other Levels and Ramps (OLRs)

14 14 Shaft Cables

15 15 WCD Lighting

16 16 WCD Drift Lighting

17 17 WCD Lighting

18 18 WCD 12kV Electrical Distribution

19 Communications

20 20 Scope of Work at WCD Structured Cabling System - ICT Enclosures and Pathways - Backbone Distribution - Horizontal Distribution Communications System - Extend existing analog phone system - Extend existing radio system Extend existing Data Network

21 21 REDUNDANT BACKBONE STRAIN RELIEF LOOP EXISTING COMMUNICATIONS ROOMS AT THE SURFACE CEs IN WEST DRIFT CEs NEAR WCD WCD Option

22 22 2-Way Radio Coverage

23 23 Pathway Supports and Enclosures Communications Enclosure Dimensions vary from: 24” x 24” x 36” to 24” x 24” x 60” Communications Distribution Enclosure Dimensions: 24” x 24” x 72”

24 Fire Protection

25 25 Life Safety Codes Standards - IBC 2009 - Referenced NFPA Codes and Standards - NFPA 520 – Standard on Subterranean Spaces - Variances ADA - As per DUSEL ADA Policy July 2010 - “…recognizing that DUSEL is a unique facility with special hazards and construction challenges, portions of DUSEL will not be accessible…” Variances will be necessary

26 26 WCD Fire Safety 91 Occupants Exit via Ross and Yates Shaft or to AORs Barriers to separate out adjacent mine areas - 4 hour barrier to AOR and experiment cavity - 2 hour any other openings to drift - 2 hour for cross drift AORs to limit travel distance to 2000 feet - 96 hour duration - Shaft AORs sized for 91, others 10

27 27 WCD Fire Safety Suppression - Sprinklers in West drift and occupied spaces - Standpipe throughout west drift and occupied spaces - Redundant water supply 100,000 cfm for smoke control discharged to east drift Emergency lighting throughout occupied areas

28 28 Fire Alarm System shall consist of: Manual Pull stations Combination speaker/strobe lights Water flow/tamper switches Aspirated Air Sampling w ith gas monitor modules WCD Fire Alarm

29 29 Life Safety

30 30 91 person AOR 4 hour separation 4 hour separation to WCD cavern 2 hour separation to other unoccupied areas 2 hour shaft separation 4 hour AOR separation Life Safety

31 31 Airlocks

32 32 Airlocks