MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.

Slides:



Advertisements
Similar presentations
K. Long, 18 April, 2015 Beam-line status — red sky at night?
Advertisements

MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
June 26, 2009TLH, NFMCC Friday Meeting1 MICE Updates MICE News Overview ISIS and MICE Schedules DAQ Review Spectrometer Update Aspirational Schedule Terry.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
MOM report 23/9 – 28/9 G.CECCHET. MOM report Hall PPS commissioning Target tests last night MOM laptop.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICE Video Conference April 22, 2010.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 21 September, 2009.
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
MICO 1 st February 2010 Terry Hart (MOM). MICO 1 st February June 2015 Decay Solenoid DS will not be ready for Machine Physics. Matt Hills spent.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO March 23, 2009.
Online Reconstruction Update Linda R. Coney UCR Mar 25, 2010.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
MICO 22 nd February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Computing Panel Discussion Continued Marco Apollonio, Linda Coney, Mike Courthold, Malcolm Ellis, Jean-Sebastien Graulich, Pierrick Hanlet, Henry Nebrensky.
Online Reconstruction Update Linda R. Coney UCR Dec 17, 2009.
MICO Meeting, 1 st March 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - March User Runs Plans - Suggestions.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 14 September, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Detector Systems Update MICO March 3, MICE Detector Systems  CKOV u CKOV humidity (HIH4000) and temperature (LM35) sensors in hand for installation.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 26, 2010.
Alain Blondel MICE VC 9 september 2010 Spokesmouse report o VC 22nd April o 12th-13th May posters for IPAC (Vittorio Palladino) o VC 20th May o IPAC May.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting June 7, 2010.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO April 6, 2009.
MICO 8 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - Problems and Issues.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 19, 2010.
MICO 15 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
Detector Systems Update MICO Feb 25, MICE Detector Systems  CKOV u CKOV installation planned during March shutdown u Cable issues resolved. Geneva.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO March 30, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting May 24, 2010.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 7 September, 2009.
CM26 March 2010Jean-Sebastien GraulichSlide 1 Online Summary o The heplnw17 case o DAQ o CAM o Online Reconstruction o Data Base o Data Storage Jean-Sebastien.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE VC Aug '10J.S. GraulichSlide 1 MOM report o Achievements Since CM27 o Daily Operations o Run Plans o Summary Jean-Sebastien Graulich, Geneva.
MOM report – part I Roumen Tsenov as MOM ( )
1 Operations Overview L. Coney UC Riverside MICE CM32 – Glasgow – June 2012.
1 MICE Running L. Coney – UCR MPB – 31 Oct Coney - MPB - 31 Oct 2012Outline Current Running Current Running Shift personnel training Shift personnel.
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
MICE Operations Manager Report Linda Coney University of California, Riverside UKNF Meeting June 8, 2010.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
MOM Report Victoria Blackmore VC /06/11 1/7.
Click to add Text L. CONEY1 MICE Shifter Training June 2015.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
Linda R. Coney – 24th September 2009 MOM Update Linda R. Coney 24 September, 2009.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
Alain Blondel MICE VC 12 March 2009 Brief MICE news 1. Decay solenoid: operations will restart in early July. Criteria for acceptance have been specified.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
MICE VC MOM Report, 25 th February 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - Machine Physics and User Runs - Suggestions.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
Running plan Step I.1 Basic radiation levels. I.1.1 ISIS running with beam elements on, target off, beam stop shut. Establish permanent MICE monitoring.
VC117 February 2009Jean-Sébastien GraulichSlide 1 MOM Report o Yagmur Torun ( June 15 - July 14) o J.S. Graulich ( July 13 - August 7) Jean-Sebastien Graulich,
MICE MICO Alain Blondel 23 December MICE Commissioning needs 22 December 08.
Tracker Cosmic Ray Test 2011 Linda R. Coney UC Riverside CM 29 - February 16, 2011.
Beamline Update Adam Dobbs, MICE CM38 Feb Contents Recent and Upcoming Activities Target Conventional magnets Decay Solenoid Proton Absorber Summary.
MICE, Uni-Geneva and the transnational access to MICE (MICE-TNA)
Coney - CM36 - June Online Overview L. Coney – UCR MICE CM36 – June 2013.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
Linda Coney MICO June 6, 2011 MICE Online Report.
L. Coney UC Riverside MICE CM32 – Glasgow – June 2012
MICE Operations Scenario Run 1
Controls & Monitoring in MICE
Presentation transcript:

MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010

MOM Report-Coney2 Decay Solenoid & Target Decay Solenoid —See Mike’s talk —Good news: Cooldown started last Friday and is progressing well. —Snag today – level gauge not working – measures liquid level —Work for June shutdown: service scroll pumps Target —Working on aligning mechanical axis w/magnetic axis —Remake bearings to bore mechanical axis to match magnetic o End May —T3/T4 ready by February

May 20, 2010MOM Report-Coney3 Detectors —Luminosity Monitor o Data runs taken April 20 —Tracker o Paper in process of submission to archive. o In the last week: –Read out both Tracker1 and Tracker2 together o Need to repair 1553, get spare(s) o Need to set up trigger cable for hall o Cooldown date & extent to be determined o Then trackers made safe and stored —CKOV,TOF0, TOF1, TOF2, KL: all powered up and ready to go o Data taken for calibration of TOF and KL o Need feedback as to how successful & how much more data needed —Beam Profile Monitors o Overheated during running last weekend – not understood

May 20, 2010MOM Report-Coney4 Beam Beam Magnets —New flowmeters installed in power supplies (replaced repeatedly faulty originals) —Slew rate control of magnet ramp implemented o Much easier for Operations & safer for electrical infrastructure o Unwanted new feature: –auto reset and reramp upon magnet trip –prevents understanding of source of trip –Under investigation —Sometimes D2 control says “OFF” when actually “ON” —Flow rate improved for most magnets to match manufacturer spec —Magnet polarity labeling scheme from Henry adopted (MICE note) Proton absorber —Probably need extra ~100mm plastic for 240 Mev/c protons o Will it fit? Investigate during June shutdown —Some stick during operation —Need webcam to verify configuration from MLCR

May 20, 2010MOM Report-Coney5 MICE Hall & MLCR Hall work: —PPS electrical system installation should be finished in 2 weeks —Jobs for short shutdown planned: ???? MLCR —Notify MOM if equipment not working – some network ports shut down by RAL w/o notification —Remote readout of neutron monitor not always auto-update —New ssh bastion making progress o Connected up, Malcolm working with PPD computing to debug o Next step setting up user accounts…work in progress

May 20, 2010MOM Report-Coney6 Other MOM daily walkthrough form was updated Controlled access shutdown procedure written To Do: —Does the FNAL BPM need startup/shutdown manual? —Possible BLM signal from ISIS o Already have BLM8 – need implement in Target DAQ o New possibility for more information – MOM investigate —All manuals on MICO page need date and version number o Cannot tell if subtle changes or if match hardcopies in MLCR o Update hardcopies to latest version —Write Troubleshooting document —Analysis machine

May 20, 2010MOM Report-Coney7 April/May Run Summary April 23-25: —300 MeV/c pi+ beam for TOF calibration – 10k pulses, Runs —300 MeV/c e+ beam TOF calibration – 1000 pulses, Good Runs April 30-May1: —Proton absorber study May 8: —10k pulses with e+,  + beam for KL Calibration May 14/15/16: —May 14 – 300 MeV/c e+ beam KL Calibration - ?pulses, ?Runs —May 15 – proton absorber study 140 MeV/c, etc… —May 16 – no running, ISIS down

May 20, 2010MOM Report-Coney8 May Run Plan May 21-23: —300 MeV/c pi+ beam for TOF calibration —300 MeV/c e+ beam TOF calibration May 26/27/28: —Decay Solenoid cold by Tuesday (May 25) —Lock, search & secure Hall Wed evening in preparation for running Thursday & Friday —Run full day Th/F —After feedback from TOF/KL, run data for emittance,momentum matrix May 29/30: —Possible Machine Physics – interested parties speak up —NEED SHIFTER SAT/SUN

May 20, 2010MOM Report-Coney9 June/July/August Run Developing Global Run Plan: first pass today —Machine Physics JUNE 7-20 —User Run JUNE 22-AUGUST 12 —Machine Physics Aug —SHUTDOWN August 16 – January 30, 2011 —Change in Trigger June 7 —Change in TOF1 PMTs – early June —Machine Physics studies o Activation Study o Beam Loss vs Rate o Proton Absorber Study o Beam Bump Study —User Run o TOF Calibration o Emittance/Momentum matrix with muon beams —Machine Physics

May 20, 2010MOM Report-Coney10 June/July/August Run Developing Global Run Plan: NEED SHIFTERS

May 20, 2010MOM Report-Coney11 June/July/August Run Developing Global Run Plan

May 20, 2010MOM Report-Coney12 June/July/August Run Developing Global Run Plan

May 20, 2010MOM Report-Coney13 June/July/August Run Developing Global Run Plan: BLOC personnel

May 20, 2010MOM Report-Coney14 The End