CREZ Related Generation Interconnection Studies July 2008 Jeff Billo RPG meeting 07-18-2008.

Slides:



Advertisements
Similar presentations
Houston Region Import Capacity Project Planning for Reliable Power.
Advertisements

RPG: September 24, Approach for ERCOT Independent Review of the 2013 Houston Import Project Jeff Billo, Manager, Transmission Planning September.
Regional Planning Group Charter Revisions May 2008.
Regional Planning Group Project
Updated 1/28/2011. Technical Requirements & Regulatory Issues In Interconnection Agreements March 9, 2011 Jay Caspary ·
Queue Reform at the Midwest ISO NARUC February, 2008.
ISSUES WITH RETROFIT REQUIREMENTS FOR HVRT 1. CURRENT SITUATION WGRs HAVE HAD A CLEAR LIMIT OF 1.1 pu SPECIFIED FOR HVRT IN THE GUIDES WGRs ARE NOW BEING.
Economic Criteria for Transmission Planning in the ERCOT Region Public Utility Law Seminar DeAnn Walker August 3, 2012.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
System Strength Discussion
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
Generation Interconnection Overview
Valley Import Overview Jeff Billo Regional Planning Group Meeting July 22, 2014 Preliminary1.
Federal Energy Regulatory Commission Proposed Rule on Small Generator Interconnection RM July 23, 2003.
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
Wind Power and the CREZ Case: What’s Decided, What’s Not, What’s Next Patrick R. Cowlishaw Jackson Walker LLP SBOT Public Utility Law Section August 15,
December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.
Program Compliance Review Overview IFTA Annual Business Meeting Las Vegas, Nevada July 21-22, 2006 Presented by Dick Beckner Debora Meise Jay Starling.
NRG Comments/Concerns with HIP Assumptions January 21, 2014 RPG Meeting NRG Comments/Concerns with HIP Assumptions - January 21, 2014.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
2015 RTP – Study Scope of Short Circuit Analysis RPG Meeting May 19,
NPRR 365 Change in Resource Outage Approvals from 8 to 45 or 90 Days Woody Rickerson Director Grid Coordination
McCAMEY 345 kV TRANSMISSION PLAN Presentation to Technical Advisory Committee May 8, 2003 KENNETH A. DONOHOO, P.E. Manager, System Planning Transmission.
1 Interconnection Update Jay Zimmerman Manager, Transmission Policy Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
TPIT using Model On Demand Jay Teixeira Manager Model Administration Regional Planning Group 5/21/13.
March 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
Large Generator Interconnection Procedures Reform 2 nd Stakeholder Meeting May 5, 2009.
POWER SYSTEM PLANNING CHARTER AND PROCESSES UPDATES Presentation to TAC Sept 9, 2004 Transmission Services Ken Donohoo, Manager of System Planning
ERCOT Wind Survey Leo Villanueva. Abilene Mc Camey Big Spring.
MIG TF Voting Items Market Participant Notification Period (Transmission outage) – =1 Year Interconnection Date for Protocol Considerations – First Interconnection.
02/13/2009 RPG Wind Interconnection Survey Dan Woodfin Director, System Planning.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
CMWG Update Mark Soutter - Invenergy LLC WMS November 2015 Meeting.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
ERCOT Independent Review
October 29, 2012 RARF Workshop 2 Introduction to ERCOT Modeling Process Jay Teixeira Manager, Model Administration.
February 3, 2011 TAC ERCOT Planning Go-Live Update Jay Teixeira Manager, Model Administration.
Impacts of Environmental Regulations in the ERCOT Region Dana Lazarus Planning Analyst, ERCOT January 26, 2016.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
ERCOT ROS Planning Working Group (PLWG) Scope Approved at ROS Meeting.
ROS July 10, 2008 Meeting WOTF Update on ROS Action Plan Summary: EECP Step #2 (Feb.26 th, 2008) Mark Garrott WOTF Chair.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
May 15, 2009 Regional Planning Group CREZ Implementation Study Update Warren Lasher Manager, System Assessment.
3/28/2008 RPG CREZ Meeting CREZ Transmission Optimization (CTO) Study And The Oscar Goes To… Warren Lasher Manager, System Assessment.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
1 Customer Objections in Complete Status (CCO Clean-up Phase 3) Background Next Steps.
Panhandle Renewable Energy Zone (PREZ) Study
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
PLWG Report to ROS September 4, PGRR039 PGRR requires Interconnecting Entities (IEs) to provide information for ERCOT’s resource adequacy reports,
August 24, 2007 ERCOT Regional Planning Group Meeting CREZ Transmission Optimization Study Warren Lasher System Assessment.
1 Entergy Transmission Planning Summit New Orleans, LA July 10, 2003 Generation and Transmission Development in the Southeastern United States.
October 12, 2012 RPG Planning Guide 5.3.2(2) Developer obligation to keep RARF data updated Cathey Carter Resource Integration.
Transition Plan Network Operations Model Change Requests 5/26/2010.
Technical Advisory Committee Presentation to the ERCOT Board of Directors May 20, 2009.
1 Customer Objections in Complete Status (CCO Clean-up Phase 3) Background Next Steps.
June 11, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
PLWG Report to RPG January 21, 2014 Presented by John Moore, PLWG Chair.
Impact of not including proposed generators lacking RARF data in the planning models Planning Guide Section 6.9 Issues February 17, 2016.
1 ERCOT 2015 West Texas Study November 18, 2014 Jeff Billo.
Subsynchronous Resonance Update Jeff Billo, Senior Manager ERCOT Transmission Planning February 3, 2016 Wholesale Market Subcommittee 1ERCOT Public.
Abilene Mc Camey Big Spring. Far West Abilene Area All the values are based on returned ERCOT survey results Total number of Wind Powered Generation.
RPG - 10/12/2007 Competitive Renewable Energy Zones (CREZ) Update Bill Bojorquez Vice President, System Planning.
Houston Import Study Update
ISSUES WITH RETROFIT REQUIREMENTS FOR HVRT
ERCOT 2009 Five-Year Transmission Plan Update
Generation Interconnection Summary
Presentation transcript:

CREZ Related Generation Interconnection Studies July 2008 Jeff Billo RPG meeting

2 RPG Meeting Background Since Summer 2007 ERCOT has put a temporary moratorium on generation interconnection studies that meet the following criteria: (1) are in the area of the ERCOT System that will be significantly affected by system upgrades due to the CREZ process, that is, the West CM Zone; and (2) (a) have expected in-service dates beyond 2011 or, such that the CREZ upgrades will likely be in place by that in-service date; or (b) will likely require a non-exempt transmission CCN to accomplish the interconnection As of 07/15/2008 this moratorium has affected the following: –8 Screening Study Requests –13 Full Interconnection Study Requests (FIS) There are five FIS requests in process that would have been placed under this moratorium had we started it prior to 2007 ERCOT System Planning is currently processing 18 screening study requests that are not subject to the moratorium –ERCOT is required to complete screening study requests within 90 days of receipt per PUCT Substantive Rules

3 RPG Meeting Issues 1.When the PUCT selects a CREZ transmission plan in what order should ERCOT System Planning perform the screening studies? 2.At what point should FIS requests proceed? 3.How should in-process FIS studies be handled if a project’s interconnecting TSP changes? 4.How should in-process interconnection requests be handled if the developer decides to delay the project and change the POI to a new CREZ line? 5.What study assumptions should be used for screening and FIS studies?

4 RPG Meeting Issue #1 When the PUCT selects a CREZ transmission plan in what order should ERCOT System Planning perform the screening studies? Potential Resolution: –Place all requests that were on hold back into the screening study queue and process them in the order in which they were received –This means that CREZ related screening study requests received last summer would be worked on prior to non-CREZ related requests recently received –This may make it difficult to meet the 90-day deadline for processing recently received requests (average time out for the last 10 screening studies completed by ERCOT System Planning was 59 days from receipt)

5 RPG Meeting Issue #2 At what point should FIS requests proceed? Should FIS requests proceed once the PUCT selects CREZ transmission lines, once the transmission provider of a generation project’s interconnecting line is selected, once the CCN is filed, once the CCN is granted, or at some other time? Potential Resolution: –The FIS request for a project should proceed once the transmission provider of that project’s interconnecting transmission facility has been selected –This means that certain aspects of the FIS may not be able to be completed until the CCN has been granted (ie. the facilities study)

6 RPG Meeting Issue #3 How should in-process FIS studies be handled if a project’s interconnecting TSP changes? This is primarily related to Panhandle generation proposals Potential Resolution: –This should generally be worked out between the developer and the TSPs involved to determine the best course of action on a case by case basis –ERCOT recommends (but will not require) starting the process anew since a Panhandle with CREZ transmission lines will look a lot different than a Panhandle without any ERCOT transmission lines as was the case when these requests started

7 RPG Meeting Issue #4 How should in-process interconnection requests be handled if the developer decides to delay the project and change the POI to a new CREZ line? Potential Resolution: –If the POI changes the current request should be cancelled and a new request started –This applies for requests in either screening study phase or FIS

8 RPG Meeting Issue #5 What study assumptions should be used for screening and FIS studies? Should the study assume all CREZ transmission improvements are in place regardless of a generation project’s in-service date? What generation should be assumed in the study? –Should an assumption be made about the amount of wind generation in each of the CREZ zones? If so, how much and at what locations? Potential Resolution: –Studies should assume all CREZ transmission lines are in place in 2012 until more accurate information is known about the in-service dates for each of the transmission improvements –Only the plant under study, existing plants, and plants with SGIAs should be included in the study as is consistent with current practices (TSPs may include other likely generation as is consistent with their current practices)

9 RPG Meeting Comments Please direct comments to Jay Teixeira Jay: