CMS Upgrade Workshop, FNAL, Oct 28-30, 2009 1 O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,

Slides:



Advertisements
Similar presentations
Agenda Aug.2,2001 Chaired by Nelson Chester Welcome & Introduction Weiguo Li 10:00-10:10 CSC Management &Tooling Chunhua Jiang 10:10-10:40 Coffee Break.
Advertisements

Update on the bakelite gluing Feb 2002: first warning from BaBar  13 gaps (over 48) accepted (27%) (i.e. max 2 non contiguous unglued spacers)…the remaining.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
US CMS Collaboration Meeting, UC Riverside, May 19, Endcap Muons John Layter US CMS Collaboration Meeting May 19, 2001.
1 Peter Monaghan“Hall C January 2011 Users Meeting”15 th January 2011 SHMS Wire Chamber Update RECAP from August Review: Vendor price quote 5x larger than.
1 ME 234/2 HV noise investigation N.Bondar CMU. 12/18/02.
Davide Piccolo - INFN NapoliSIENA maggio 2004 Production and Quality control of RPCs for the CMS muon barrel system Davide Piccolo – INFN Napoli.
MM mechanical prototype Work progress at CERN MicroMegas General Meeting, CERN, 5-6 November
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
Production Readiness Review of Frascati MWPC Production Site December 4 th, 2003 – P. Campana.
RF Cavity / Coupling Coil Module
June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R.
LHCb MUON MPWC STATUS OF TOOLING, SITES, PRODUCTION AND MATERIAL PROCUREMENT.
TD/MSD TORUS CMM PRODUCTION: OVERVIEW G. Velev Clas12 Torus CCM Production Readiness Review –Dec 4, 2013.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Endcap Integration Workshop: June 11-14, CSC Commissioning Andrey Korytov.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
A Lanaro UW Madison CMS Upgrade Week April 26-30, CSC Phase 1 Upgrade Installation – Logistics - Planning Armando Lanaro UW Madison CMS Upgrade.
ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06 Frank Taylor MIT V1.3.
Production of Forward RPC Gaps CMS Forward RPC EDR (10/10/2002 – 11/10/2002) Seong Jong Hong KODEL, Korea University.
Status of production at LNF E. Dane, C. Forti, D. Pinci, A. Sarti – LHCb Muon CERN 25-may-04 Monday 24-may: closed chamber 30. Will close 2 more this week.
Tracker Summary Alan Bross MICE CM October 10, 2007.
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
 YE+4 disks = 2 Nos. (12 Sectors each)  Support Structures = 2Nos.  AISI 1045 steel bar = 1 No. for checking dimension of 680 mm (0/-0.5)  Fasteners.
11/05/2000Wire Chamber Working Group Visit to Fermilab Participants: –Giulio Auriemma, Thomas Schneider, Burkhard Schmidt General Remarks: –Visit was organized.
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
Baby MIND coil modules assembly the aluminium folded strip solution 1 Alexey, Philippe, Gabriella, Helder, Herman Baby Mind Magnet CERN June.
ATLAS Endcap Signal Feedthrough Project Status Report Pin carrier Procurement Summary Feedthrough Production QA/QC Shipment to CERN Reception Tests at.
CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida.
CMS Experiment at the LHC, CERN Date Recorded: :21 CET Run/Event: / Candidate Collision Event Report from Belgium Michael Tytgat.
14-Dec-15S.Movchan Straw manufacturing and QC1 Straw manufacturing procedure and QC tape and straw parameters specification conditions of straw production:
Introduction Straw Working group meeting CERN group 1 NA62 Collaboration meeting, Brussels 7-10/9/2010.
Total Cross Section, Elastic Scattering and Diffraction Dissociation at the LHC January 17, 2003TOTEM plenary meeting -Marco Bozzo1 CSC detectors for T1.
CERN adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of Production of support panels - Things to be settled.
4-Jan-16S.Movchan Straw manufacturing and QC1 Straw tracker manufacturing procedure Dubna: assembly halls procedure conclusion Presented by S.Movchan.
Production Readiness Review at PNPI Chamber assembling: Main production and quality control steps 30 January 2004 – G.Alkhazov 1.Input components control.
Muon Meeting April 2004JsG Status of Chambers Production at CERN Jean-Sebastien Graulich o Open Questions from the PRR O-ring Aging, Aging tests, Storage.
DOE/NSF Review of U.S. ATLAS May 21-23, 2003 CSC Mechanics and Electronics Paul O’Connor Tom Muller BNL May 22, 2003.
CMS Upgrade Workshop, FNAL, Nov 19-21, O.Prokofiev CMS Upgrade Workshop Updated ME4/2 chamber construction costs and prototype Status and plans.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
10/7/2003Thomas Schneider1 Status report of CERN/PNPI Tooling support for PNPI M2R2 Prototype Plans towards the PRR.
Dick Loveless Upgrade report 12 Oct EMU Upgrade Report Dick Loveless University of Wisconsin 12 October 2012.
G. PassalevaFirenze - September 8, 2004 Production Readiness Review Firenze MWPC Production Site G. Passaleva.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Zaragoza, 5 Julyl Construction of and experience with a 2.4 x 1 m² micromegas chambers Givi Sekhniaidze On behalf of the Micromegas community.
26-Feb-16S.Movchan Straw manufacturing and QC1 Dubna NA62 straw tracker assembly area (milestone) halls plans conclusion Presented by S.Movchan.
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
11/02/2005M. Alfonsi - LNF1 DETECTOR CONSTRUCTION M. Alfonsi - LNF.
CMS-GEM gas system GEMs for CMS High Eta Muons - Workshop III, CERN April R.Guida PH-DT-DI.
Trigger efficicency on double tracks Trigger efficiency on isolated tracks Final results of the Trigger Test on the 25ns beam Bx NUMBER Fraction of Triggers.
Organising 904 RPC lab Ian 23 April Already done, ISR I3-I4 tunnel is empty. Move out and chamber/gap sorting done in the ISR. Manpower available.
HGC Cassettes Jim Freeman September 17, Director's Review -- Calorimetry – HGC Cassettes Jim Freeman, 2015 Sept 17.
Activity report from LNF Panels Soldering tests Production site and tooling status WPC miscellanea (+7 cm layout, cathode costs, aging tests)
6-Mar-2016 Dan Wenman | FC Installation 1 APA installation and integration at CERN Shipment of APAs APA handling Acceptance testing Tools needed.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
US CMS Phase 2 R&D Discussion 30-July-2013 “Phase 2 muon R&D” J. Hauser, UCLA  Expected wire accumulated charge at 3000 fb-1 for various chamber types.
PSL APA Update May 3, 2016 UW Physical Sciences Lab.
ELENA installation progress F. Butin / ELENA collaboration.
Rui De Oliveira Vienna March 2014 Industrialisation of Micromegas detector for ATLAS Muon spectrometer upgrade 1.
University of Wisconsin
DC56 R&D Goals, Schedule and Status
T1 status (a selection from EDR presentations)
HL-LHC upgrade at IPHC news
PNPI – M3R4 – Panels 70% - HV bars 100% - FR4 frames 100%
CSC Electronics Installation and Commissioning Oct ‘06
Presentation transcript:

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling, preparation for shipping Updated factory plan in 904 Production scenario

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev ME4/2 Upgrade Project (Phase 1) Goal is to construct 75 ME4/2 chambers of the largest (1.5m x 3.4m) CSC chambers. Major chamber milestones in 2009: - Construction and testing of new ME4/2 chamber prototype with using a production factory tooling and new material (FR4 skins). - Installation of 5 spare ME4/2 chambers (one of them is a new chamber) on the YE+3 disk. Chambers are fully operational and integrated into the EMU system. It is very good progress for EMU upgrade project

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev R&D Plan for FY10 Goal is to make new ME4/2 prototype at CERN (Bldg.904) in 2010 List to do:  Chamber parts - procure new FR-4 skins, anode and gap bars, cooling plates - make 10 panels from new skins  Shipping of factory tooling from FNAL to CERN - tooling preparing, crate making, packing  Preparing 904 for prototype production - cleaning, painting - prepare engineering communication (power, vacuum, gas and pressure lines )  Prototype construction - factory tooling installation and commissioning - personnel learning and training - prototype production with using standard procedures and travelers

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Chamber Parts Procurement: - placed order for production of anode wire fixation bars, gap bars and cooling plates - placed order for making 20 FR-4 skins with option to make 1100 (production quantity) Target is to have parts for making of 3 chambers 5ft x 12ft copper clad FR-4 skin production: It is the most critical chamber part because old vendor GE who made FR4 skins earlier has been disconnected this line of production. What we did: - focused efforts to find new vendors capable to make this size FR-4 skins - found 4 vendors (US Laminates, AAR composite, Plascore and Aurora Technologies) - obtained reasonable quotes for making FR-4 skins for small quantities - got quotes for production quantities that are higher than we have had few years ago We expect to place a final order to make 20 skins this week

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Both AXIOM and Gerber machines (panel cutting, drilling and strip milling) are fully operational. Panel Production Tooling at FNAL Axxiom machine Gerber machine Vacuum Lifting system Gerber control unit

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev List of major factory tooling:  Vacuum lifting system  Epoxy strip gluing machine  Clamping tables for anode and gap bars  Winding machine  Automatic soldering machine  Wire spacing and tension machine  Automatic strip connectivity tester  Automatic wire and strip capacitance setup  Ionized air knife cleaning machine  Ionized air gun  Panel and chamber carts  Assembly table  RTV sealing equipment  Scope, capacitance meter Chamber Production Tooling Tooling stored at FNAL in few buildings. Preliminary, we will need ft containers (depends how many tables we can get) We have started preparation for crate making and packing.

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Overseas Shipping to CERN Shipping: 40 ft overseas container: 5 crates/stack or 15 crates / container Shipping container: panels + chamber parts Panels (38 crates)  3 containers Factory tooling  1-2 contaners Chamber parts  1-2 containers Total: ~ 6 40ft containers Shipment by air: chemicals, small parts,….

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Updated CSC Factory Plan at 904 Storage, inspection kit preparation RPC Factory Profuction CSC chamber storage CSC panel storage Electronics Racks CSC FAST Site Chamber/Panel storage area 10 m 20 m Additional storage area of 200m 2 with crane is required (Bld 888, SX5,…?)

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Storage Area for ME4/2 Chamber Production Panels: Production: vendor  FNAL  CERN (shipping: 14 panels / crate) Panels: 75 chambers x 7 panels = 525 panels  38 crates Crate: 2.0m x 3.7m x 0.4m, maximum 5 crates per stack Storage area for panels (904) : 2.5m x 4.5 m = 11 m 2 /stack x 8 = ~ 90 m 2 Chamber parts: - Big parts: Al frames, Z-brackets (open shelf storage) - FR4 parts: anode wire fixation bars, gap bars, spacers, … - small parts: wires, electronics components, bolts, nuts, Chambers: - Chamber Crate: 2m x 3.7m x 0.4m, maximum 5 crates per stack - Reuse the panel crates remained from panels - Need 75 crates for ME4/2 chambers (shortage ~ 20 crates) Chamber storage: 5 chambers per stack  15 stacks x 11 m 2 = ~ 165 m 2 Total storage area required for ME4/2 CSC production is about 250 m 2 Inspection/storage room

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Engineering Services for CSC Factory Gas mixture pipelines (copper tube, 12 mm OD), test area Pure nitrogen line (SS tube, 25 mm OD, P = 20 atm, flow ~0.5 m3/min), clean rooms Pressure line for pneumatic tooling (10 atm) Vacuum line Power 220V & 110V (will be discussed with CERN engineers) Clean rooms : Class 1000 Vendor: Clean Rooms International, Inc Storage area and kit preparation Gas storage Clean Room 1 Clean Room 2 Panel lifting area HV tests area Laser area Packing Incoming Parts Loading

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev ME4/2 Prototype Production at CERN  FNAL: Factory tooling shipment to CERN  FNAL: Panel production, strip milling (Lab.8)  FNAL: Chamber parts procurements, control, shipment to CERN  FNAL: Supervising production, training and learning technicians  CERN: CSC factory preparation (Bldg 904)  CERN: Prototype production and testing

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Preparation at Bldg.904 CSC factory setup (3-4 months):  Clean, paint production area  Engineering services (gas, vacuum, power lines)  Clean room construction ???  Tooling installation and testing  Personnel training, learning, start prototype production Manpower: - 2 technicians, one of them will be a flow manager in the future - 1 technician from FNAL for 1-2 months for training of CERN personnel Engineering support: - 1 engineer from CERN - 1 engineer from FNAL/Purdue for 1- 2 months to help with tooling startup Prototype production (2-3 months): - 2 technicians - 1 physicist - 1 engineer Preparing 904 area and engineering communications

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Production Scenario and Time Schedule Tooling and chamber parts shipping: Mar-Apr 2010 Readiness CERN site (Bldg 904): May, 2010 Factory tooling setup, personnel training: Jun – Aug, 2010 Prototype production and testing: Sept – Nov, 2010 If a prototype production will go smoothly we will continue a production for additional 2 chambers (parts will be available) to keep technicians busy. Also, electronics component preparation (resistor and capacitance bending, ground foils cutting, cables preparations) could be considered as filing time before ME4/2 chamber production. Making new chamber prototype with factory tooling at CERN will allow to save 6-9 months for ME4/2 production since a project will be approved. It is a good reason to make prototype in framework of R&D program. With a proposed plan and project approval in 2010 the first 36 chamber production could be completed in the end of 2011.

CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Summary Construction of ME4/2 chamber prototype of production quality is important milestone for EMU Upgrade project. New ME4/2 prototype that will be produced at CERN with using of factory tooling will allow to save time significantly for factory setup and personal training Preparation of 904 building and engineering communications for prototype construction is a crucial point of factory setup at CERN.