Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review H.-C. Hseuh Vacuum Systems January 4, 2007 Project Overview.

Slides:



Advertisements
Similar presentations
February 17-18, 2010 R&D ERL David Pate R&D ERL Photocathode Deposition and Transport System David Pate February 17-18, 2010 Photocathode Deposition and.
Advertisements

Mar 13, Low-energy RHIC electron Cooler (LEReC) CRYOGENICS Mar 13, 2014.
Upgrade Plan of KEKB Vacuum system Pre-kickoff KEK1 Y. Suetsugu KEKB Vacuum Group Contents Challenges for vacuum system Designs for.
Progress and Plan for Superconducting RF Cavity RF Group.
Beamline 12 Project BL12 In-vacuum Undulator Source August 11, 2004 Andy Ringwall BL12 In-vacuum Undulator Source August 11, 2004 Andy Ringwall.
1 Low-energy RHIC electron Cooler (LEReC) Update November 17, 2014.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
Vacuum Pressures at IR Contents Y.Suetsugu KEKB Vac. Group 1.Outline of Vacuum System at IR 2.Behavior of Pressures 3.Remedies for Heating of Vacuum Components.
30/05-03/06/2007 LCWS2007 and ILC2007, DESY Hamburg Germany Vacuum System Specifications What needs to be specified in Vacuum Specification for ICL Damping.
1 BROOKHAVEN SCIENCE ASSOCIATES Production of Vacuum Components H.C. Hseuh NSLS-II ASAC Review October 14-15, 2010.
1 BROOKHAVEN SCIENCE ASSOCIATES Vacuum Systems H.C. Hseuh, Vacuum Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
DR Vacuum Component Overview April 25, 2012 Joe Conway.
Brookhaven Science Associates U.S. Department of Energy H.C. Hseuh, Status and Upgrade of RHIC Beam Vacuum Systems ICFA13, Dec , Status and.
SR Vacuum Systems and Front Ends
1 Low-energy RHIC electron Cooler (LEReC) cost estimate December 2, 2014.
1 LEReC Funded! From: Fedotov, Alexei Sent: Thursday, May 14, :04 PM Subject: LEReC project approved Dear All, FYI. The LEReC project is now formally.
NSLS-II ASAC Review, 10/9-11/06 H-C. Hseuh,…, SR Vacuum Systems Storage Ring Vacuum Systems H-C. Hseuh, C. Foerster, J. Hu, G. Mahler, S. Pjerov, S. Sharma,
BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
Low Energy RHIC e - Cooling LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity 704 MHz SRF gun converted to booster cavity 5-cell 704 MHz.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
January 4, 2007 RHIC II Project Internal Cost Review Gary McIntyre RHIC Ring Modifications January 4, 2007 Project Overview.
Matthew Cox VSSLS Workshop Barcelona Sept SLIDE 1 1 Diamond Light Source Vacuum Systems Matthew Cox
J. Alessi Implementation Plan EBIS Project Technical Review 1/28/05 Implementation Plan WBS exists Working on a “bottoms up” cost estimate The following.
Cornell ERL Vacuum System as a Model for ILC Damping Vacuum System Conceptual Design Yulin Li & Joe Conway C ornell L aboratory for A ccelerator-based.
G5 Beam Line Vacuum System. G5 Beamline Vacuum System Design  Bakeable and Particulate free to Class 100 Clean Room quality Require Clean room QA and.
Beam Line Layout – Cooling Section There seems to be two options for energy measurement: at the 180 dipole and/or in a diagnostic branch at the end of.
New injection region 1L1 Engineering Change Request PSB-L-EC-0001 EDMS Wim Weterings PLI Meeting Wednesday 14 th January 2015.
Low Energy RHIC e - Cooling Meeting Minutes – 11/19/14 1. Cooling Section Magnets and Power Supplies –Most of power supplies will be from ERL (R. Lambiase).
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
Abstract Storage Ring Vacuum and Interface to Magnets Hsiao-chaun Hseuh, NSLS-II Project This presentation provided a quick overview of the storage ring.
Booster and Collider SC magnets. Design & prototyping of UHV and cryostat systems for Booster and Collider A.Smirnov JINR, Dubna, Russia NICA Machine Advisory.
Low Energy RHIC e - Cooling Meeting Minutes – 11/5/14 1.J. Tuozzolo will schedule a visit to NSLS next week to evaluate available magnets, power supplies,
ECOOL Meeting 03/26/10 1 Low-E cooler baseline decisions: 1.FNAL’s cooling section “as is” – with weak solenoids, correctors, etc. (to prevent over focusing.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
Experience Fabricating the Storage Ring Vacuum Chambers for NSLSII
Extraction Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
NCSX NCSX CDR May 21-23, 2002 H.W. Kugel Slide 1 Conceptual Design for NCSX Auxiliary Systems Heating, Fueling,Wall Conditioning and Vacuum Systems.
Low Energy RHIC e - Cooling Meeting Minutes – 11/5/14 1.Funding is available to purchase magnets. 2.Comment during presentation of attached slides: 180.
January 4, 2007 RHIC II Project Internal Cost Review Existing RHIC power supply Modifications Don Bruno & George Ganetis January 4, 2007 Power Supply Modifications.
Low Energy RHIC e - Cooling 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
BROOKHAVEN SCIENCE ASSOCIATES SR Vacuum Systems ASAC Review, 7/17-18/ of 21 Storage Ring Vacuum Systems H. Hseuh, Vacuum Group ASAC Review of NSLS-II.
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
Low Energy RHIC e - Cooling Meeting Minutes – 12/23/ Cooling Section: –LF Solenoids:  At PPM, G. Woods has assigned buyer, SOW will be revised,
2007/09/17-21 SLAC IRENG07 1 A Basic Design of IR Vacuum system Y. Suetsugu, KEK Possibility of a pumping system without in-situ baking at z < L*
LEReC. COOLING in Blue RHIC ring COOLING in Yellow RHIC ring 63.9 m to IP2 Beam Dump 20° Bending Magnets DC e - Gun 704 SRF Booster Cavity 2.1 GHz Cu.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity Booster Cavity and Gun move (next slide)
Beam Line Layout – Cooling Section (to be installed by 1 Dec ember 2015) J. Kewisch wants to move the 20 dipole, yellow (to the right) toward the triplet.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
LEReC. COOLING in Blue RHIC ring COOLING in Yellow RHIC ring 63.9 m to IP2 Beam Dump 20° Bending Magnets DC e - Gun 704 SRF Booster Cavity 2.1 GHz Cu.
LEReC System 1. Project Schedule 2015 shutdown COMPETE! Move beam line equipment from IP 01:00 Install cooling section beam line 2016 shutdown Install.
Low Energy RHIC e - Cooling Meeting Minutes – 12/17/ For the matching energy of electron and ion beams methods for electron energy measurement were.
Minutes meeting Mapes, Miller, Kayran, Fedotov, Gassner, Hamdi, Bruno, Mahler, Weiss, Hammons, Arno, Nayak, Fite, Bellavia The layout shown in.
LEReC System 1. LEReC Injection section 2016 CeC Beam Dump 45°dipole (CeC) Profile Monitor (ERL HE) No SRF Cavity DC e - Gun ERL Solenoid ERL Halo Monitors.
High energy beam transport.
CBETA Vacuum System and Beam Stop (Conceptual Design) Yulin Li, CLASSE.
Cornell ERL Prototype Injector DC Photocathode Gun Design Review Vacuum Systems Yulin Li, January 5th– 6th, /5-6/2011 Cornell Gun Review.
CBETA Vacuum System and Beam Stop Yulin Li, CLASSE.
RTML Vacuum System RDR Summary FermiLab October 24, 2007
XFEL Collimation and Beam Switchyard Vacuum Issues
XFEL Bunch Compressor BC1 and BC2 Vacuum Issues
(WBS ) Alan Wootton, LLNL April 24, 2002
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Extraction Michael Bevins May 17, 2007
Presentation transcript:

Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review H.-C. Hseuh Vacuum Systems January 4, 2007 Project Overview

Vacuum, H-C. Hseuh January 4, Four Vacuum Areas and Three Sub-systems (1) ERL, (2) Electron Transport, (3) Cooling, (4) RHIC Modification (A) Chambers, (B) Pumps & Valves, (C) Monitoring & Control Scope - RHIC-II Vacuum Systems

Vacuum, H-C. Hseuh January 4, < Torr UHV, Clean and dust free Cost estimate based on existing ERL No. Chambers Triplets9 Doublets15 Drift pipes12 Dipole-607 Dipole-60-Y (60)1 Dipole-60-Y (30)2 Dipole-301 Dipole-30-Y (30)1 Inj. chicane-151 Inj. chicane-302 Inj. chicane-15-Y1 Inj. drift pipes4 Dump drift pipes1 Dump -30-Y1 Dump pipe2 Pipe for solenoids4 Adaptors for RF6 Vacuum components: Vacuum Chambers: ~ 70 GV: DN100 (8), DN63 (3), RAV (19) IP: 20 l/s (40), 200 l/s (6), IPC (26) VG: CCG (21), TCG (12), GC (12) TMP: Beam (2), Insulating (3) Total 70 chambers Scope - ERL Design, fabrication, assembly, evaluation, installation and commissioning ~ 50 m UHV systems Including all the vacuum chambers, pumps, valves, monitoring and control 70

Vacuum, H-C. Hseuh January 4, ERL dipole chamber ERL triplet chamber BPM mounting block RHIC II ERL ring vacuum will be similar to existing ERL vacuum loops Aluminum dipole chambers, Inconel doublet and triplet chambers with BPM blocks, bellows and pumping ports on quadrupole chambers ERL Vacuum ChambersScope - ERL ERL triplet chamber

Vacuum, H-C. Hseuh January 4, Scope – Electron Transport Vacuum Chamber TypeNo. Drift pipe10 Drift pipe-L12 Dipole-301 Dipole-458 Bending-204 Bending-20-Y4 Triplet-L18 Triplet4 Vacuum components: Vacuum chambers: ~ 61 GV: DN63 (13); RAV: (12) IP: 20 l/s (42), IPC (24) VG: CCG (12), TCG (16), GC (6) ~ 110m < 1x10 -7 Torr vacuum < 1x10 -9 Torr at HI beam cross-over Design, fabrication, assembly, evaluation, installation and commissioning ~ 110 m vacuum systems Including all the vacuum chambers, pumps, valves, monitoring and control 61 #1 & #2

Vacuum, H-C. Hseuh January 4, Scope – Undulators/Cooling Sections PipeGVRAVIPNEGCCGTCGGCBellows YI YO BI BO ~ 210 m; < 1x Torr with beams In-situ bakeable to 250 o C < 60mm Ф pipes at IP, larger away from IP 5m long NEG coated ( ~ 1 μm) beam pipes Bellows and pump between beam pipes Clearance at flange location!! Can’t make 13m long pipes!! 10mm (coil, wall, …..) 10mr D = 70mm R = 30mm F=116mmФ R(mm) = x σ D(mm) F(mm) L(m) 13? 4 Is this possible? At flange locationAt IP2 1 σ(98%) = 3.3mm < 14 σ or 17 σ? Larger V kick?

Vacuum, H-C. Hseuh January 4, Remove IR2, DX, DX-D0 Relocate & modify 4 triplets Relocate diagnostics to #9 & #10 Modify Q4-Q9 arcs Restore insulating vacuum YI2, YO1, BI1, BO2 No. Q6 C-B4 D5O (D5I) C-B4 D5O (D5I) W-C4 Gate Valve4 Bellows + IP4 Vert Corr Pipe4 Bellows4 E - A cross pipe4 W-B pipes (3)4 Bellows4 Vert Corr Pipe4 Bellows + IP4 Gate Valve4 Q3 W-C4 Q3-Q24 Q2-Q14 Q1 W-C4 Q1 W-B4 Gate Valve4 Bellows + IP4 Vac Comp.TotalOldNew GV (DN125)844 GV (DN100)440 RAV1266 IP l/s16 0 IP - 20 l/s844 NEG Cartridges404 NEG Pipes1266 TMP stations422 CCG28244 TCG16142 GC14122 Scope - RHIC Modification (W-B + C-B + Insulating vacuum) Torr vacuum In-situ bakeable to 250 o C Detail design to eliminate interference Installation between physics runs

Vacuum, H-C. Hseuh January 4, Costs by WBS

Vacuum, H-C. Hseuh January 4, Major Procurements (direct $) Vacuum chambers –ERL dipole chambers - $96K; triplet chambers - $137K ( ) –Electron transport dipole chambers - $136K; triplet chambers - $130K ( ) –Cooling section NEG coating - $360K; heating jackets - $144K ( ) Vacuum pumps and valves (WBS ) –All-metal gate valves - $640K –Ion pumps - $200K –NEG cartridges - $166K –Heating jackets - $234K –Turbopump stations - $160K Vacuum instruments and control (WBS ) –Gauges and controllers - $68K –Ion pump controllers - $316K

Vacuum, H-C. Hseuh January 4, Contingency & Risk Technical - medium –Adequate spacing between two cooling sections to provide sufficient aperture for the beam and undulator coils Bigger vertical separation, smaller aperture at IP by AP? –< Torr with beam loss and multi-pacting in the cooling sections Sufficient pumping with NEG coating and ion pumps Schedule - high –Manpower for vacuum chamber design Freeze physics design, start engineering design early –Adequate periods and manpower between physics runs for RHIC modifications and relocation of the diagnostics to sectors #9 and #10 Diagnostics relocation and RHIC modification at different shutdown Cost - medium –Labor for RHIC Modification may not be sufficient due to lack of detail design and layout, and for diagnostic relocation Start detailed layout early to better understand the installation effort

Vacuum, H-C. Hseuh January 4, Milestones Design of cooling section vacuum complete Procurement and NEG coating of chambers complete Installation of ERL vacuum complete Installation of RHIC modification and cooling sections complete Vacuum system commissioning complete

Vacuum, H-C. Hseuh January 4, Assumptions Sufficient clearance between cooling section beam pipes at IP2; adequate spacing between undulator sections for bellows, flanges and pumps Successful development of NEG coating for the cooling section beam pipes Sufficient shutdown time and manpower between physics runs for RHIC modification and installation of cooling sections Cost of vacuum pumps, valves, monitoring is based on catalog price and historical cost Cost of vacuum chambers is based on recent ERL cost and from engineering judgment