MPE activities within MP3 Arjan Verweij A. Verweij, MPE review, 2 June 2015 The questions: 1. Define the scope of work for your activity 2. Structure of.

Slides:



Advertisements
Similar presentations
1 PER-005 Update Impact on Operators System Operator Conference April and May 1-3, 2012 Columbia, SC Margaret Stambach Manager, Training Services.
Advertisements

1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
Chapter 2 The Analyst As Project Manager In Managing Information Systems 2.3.
Creating the Project Plan
Implementation. We we came from… Planning Analysis Design Implementation Identify Problem/Value. Feasibility Analysis. Project Management. Understand.
Stoimen Stoimenov QA Engineer QA Engineer SitefinityLeads,SitefinityTeam6 Telerik QA Academy Telerik QA Academy.
Development and Quality Plans
System Implementation
TE/MPE/MI OP section meeting 29 th September 2009 HCC 2009 Frequently Asked Questions 0v1 M. Zerlauth.
From Olivier to commissioning team plans for the start-up of regular operations of LHCb 30/06 to 4/07 : Global commissioning week, all detectors, full.
S/W Project Management
Managing the development and purchase of information systems (Part 1)
INTEGRATED MANAGEMENT SYSTEMS (IMS) OCT 2011 R. Nahon.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
MP3 report : W49 (6 slides, 6’) J.Ph Tock for the MP3 team Since oral report last week (24 th of November) 1JPhT – LMC 1st of December 2010.
CS 360 Lecture 3.  The software process is a structured set of activities required to develop a software system.  Fundamental Assumption:  Good software.
1.  Describe an overall framework for project integration management ◦ RelatIion to the other project management knowledge areas and the project life.
Project Post-Mortem University of California Berkeley Extension Copyright © 2008 Patrick McDermott From an AutoContent Wizard 10/27/2007.
Moving into Implementation SYSTEMS ANALYSIS AND DESIGN, 6 TH EDITION DENNIS, WIXOM, AND ROTH © 2015 JOHN WILEY & SONS. ALL RIGHTS RESERVED.Roberta M. Roth.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
EU BON Meeting, Joensuu, March 2015 WP2 Task 2.3: Data sharing tools – Action Point MS232 : Technical workshop, review of documents, test versions of data.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Powering of the Superconducting Circuits: Procedures and Strategies for Circuit Validation Antonio Vergara on behalf of the Hardware Commissioning Coordination.
LHC Hardware Commissioning Review May 2005, CERN, 1211 Geneva 23 1 LHC Hardware Commissioning Review Contribution ID: 20 – Quality assurance and.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
AT-MEL Group Meeting, CERN, 1211 Geneva 23 1 Agenda MPP subpanel meeting Analysis Team 16/11/2007 Agenda  How to best fulfill the Analysis team's mandate,
Company LOGO Final Project Status Preview: LIMKOKWING STUDENT DB SYSTEM Date : 9 th October 2007 Presented By:
© The McGraw-Hill Companies, Software Project Management 4th Edition Step Wise: An approach to planning software projects Chapter 2.
Muon Shift Organization Outline Class 1 Atlas Control Room Shifts Booking Present Status + Experience+ Feedback Class 2 reminder A. Polini & Z. Yan May.
Copyright 2002 Prentice-Hall, Inc. Chapter 3 Managing the Information Systems Project 3.1 Modern Systems Analysis and Design.
MPE Review – June 2, 2015 A. Erokhin, TE-MPE-EE Upgrade, IST and Powering tests of the Upgrade, IST and Powering tests of the 600A Energy Extraction Systems.
MP3 recommendations from June 2013-Feb 2014 Arjan Verweij on behalf of the MP A. Verweij, LSC meeting 7/2/2014 One of the tasks of the MP3 is.
By Zinour Charifoulline, Scott Rowan Automation of Hardware Commissioning - Offline Analysis of 60A circuits.
M. POJER, ON BEHALF OF THE USUAL BUNCH OF SUSPECTS… S UPERCONDUCTING CIRCUITS RE - COMMISSIONING AFTER THE 2011 C HRISTMAS BREAK.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Unit 17: SDLC. Systems Development Life Cycle Five Major Phases Plus Documentation throughout Plus Evaluation…
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
TE-CRG-CE OMP Meeting 06 / 11 / 2014TE-CRG-CE OMP Meeting.
MP3 List of main Issues during March 2010 MP3 - Team.
1 15 April 2010: Post Mortem Analysis by M.Zerlauth Automated analysis of Powering Events – Progress update.
Software Development Process CS 360 Lecture 3. Software Process The software process is a structured set of activities required to develop a software.
T Project Review RoadMappers I2 Iteration
Data processing Offline review Feb 2, Productions, tools and results Three basic types of processing RAW MC Trains/AODs I will go through these.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
HWC with nQPS Splice Monitoring Zinur Charifoulline & Bob Flora Real Time (~10 sec) BUS Voltage Energy Extraction Trip 300 µV threshold on Un-bypassed.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Christophe Martin TE-MPE-EP 02/06/ The BIS and SMP activities during LS1 MPE Group Review, 2 June 2015 Christophe Martin, Stephane Gabourin & Nicolas.
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
TE-MPE, MPE Workshop 2010, G.D’Angelo, 14-Dec TE-MPE on-call service for the LHC Giorgio D’Angelo on behalf of TE-MPE On call team, with inputs.
MPE Workshop for LS1 Summary of Global Activities Thanks to Speakers Arjan Verweij Hugues Thiesen Zinur Charifoulline Kajetan Fuchsberger.
MPP Workshop Status of Powering Interlocks I. Romera on behalf of MPE-MS MPP Workshop, 12 June 2015, I. Romera (TE-MPE)1.
 Automation Strategies for LHC System Tests and Re-Commissioning after LS1 Kajetan Fuchsberger TE-MPE LS1 Workshop On behalf of the TE-MPE-MS Software.
Component D: Activity D.3: Surveys Department EU Twinning Project.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
Update on the automation of quench heater analysis Zinour Charifoulline 18/06/2015TE/MPE-PE, ZCh1 Automation team: Odd Oyvind Andreassen, Jean-Christophe.
Maria Alandes Pradillo, CERN Training on GLUE 2 information validation EGI Technical Forum September 2013.
Quench behavior of the main dipole magnets in the LHC By Gerard Willering, TE-MSC On behalf of the MP3-CCC team Acknowledgements TE-MSC, MP3, BE-OP, TE-MPE,
M. Modena and D. Wollmann 2 “MP3 Review Day”, 28 April 2015: Session 2: “Preparation for the Powering Tests”, M. Modena, D. Wollmann.
(Access system for HWC)
Minimum Hardware Commissioning – Disclaimer
MP3 Review Software tools
Systems Analysis and Design
Dipole diode lead resistance measurement
Powering from short circuit tests up to nominal
Overview & baseline of LS2 and roadmap for CRG
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
DepEd e-FORMS Automated Form Templates in Excel for Elementary and High School Alfonso C. Corpuz, Physics Teacher September 10, :00 pm.
Review of hardware commissioning
Presentation transcript:

MPE activities within MP3 Arjan Verweij A. Verweij, MPE review, 2 June 2015 The questions: 1. Define the scope of work for your activity 2. Structure of the scope of work (flow charts are very helpful) 3. Was it properly planned, how much in advance? 4. Initial schedule and actual schedule (the realised one) 5. How many resources were used? How many resources would have been needed? 6. Give three examples of aspects which worked well 7. Give three examples of aspects which went wrong and gave difficulties 8. What needs to be improved? 9. What needs to be changed? 10. What will be done in the same way next time? Answers on the above questions are mainly based on the MP3 review that took place on 28 April 2015 (see Indico for the presentations and EDMS for the executive summary).

1. Define the scope of work of the MP3  Identify, track and document all important issues and non-conformities related to the SC magnets system. Set-up of a database for the management of exceptions related to the magnet circuits.  Solve or mitigate all pending issues related to the magnet circuits.  If needed, open and close non-conformities.  If needed, give recommendations for future operation, or for additional testing (in the machine and/or in SM18).  Report to TE-TM and LS1 Coordination Committee on electrical performance and all critical magnet circuit issues, in particular involving inter-group responsibilities.  Define and revise the procedures for the powering of all main ring magnet circuits.  Set-up and run the CCC support team during the “hardware commissioning” campaign. 2 A. Verweij, MPE review, 2 June 2015

2. “Structure” of the scope of work  The MP3 was re-started beginning of Since then, we had almost weekly meetings.  To assure our mandate, the MP3 is set up of almost 20 people (from MPE, MSC, EPC, and CRG). Most of the MP3 members had experience with previous HWC campaigns.  Each task of the MP3 is usually done by a (small) subgroup, presented in a meeting, and then approved.  We planned a CCC support team of 12 people for the powering tests during the HWC. These people were also doing the procedures, analysis manual, automation, 7 TeV campaign in Feb A. Verweij, MPE review, 2 June 2015

3. Planning  Identify, track and document all important issues and non-conformities related to the SC magnets system. Set-up of a database for the management of exceptions related to the magnet circuits. The “database” containing issues, NC’s, and exceptions on the SC circuits was started in Aug 2013, and was then modified whenever needed (see ) Tracking of MP3 issues during operation was started immediately after LS1 (using an excel file). Since May 2015 we include the issues in Jira (which was used during Run-1 by COMS).  If needed, give recommendations for future operation, or for additional testing (in the machine and/or in SM18). 16 recommendations have been issued between June 2013 and Aug 2014, see A. Verweij, MPE review, 2 June 2015

3. Planning  Define and revise the procedures for the powering of all main ring magnet circuits. We started the revision of the procedures in Dec After approval in EDMS all procedures were released in Aug-Nov 2014 (except “Powering Group of Circuits”, because it was only needed in 2015).  Set-up and run the CCC support team during the “hardware commissioning” campaign. We started preparation for the HWC in the beginning of A. Verweij, MPE review, 2 June 2015 Conclusion: Our planning for HWC was OK. The (old) NC’s/circuit issues were listed and the procedures were ready, and we had a rather large team (with sufficient contingency) to analyse the powering tests. We did not cause delays during LS1 and the HWC.

4. Initial schedule and actual schedule  We always “followed” the official schedule. We were flexible enough to adjust to the frequently revised planning, because:  we were 12 people, working part-time for the MP3,  the planning usually got longer and never shorter.  Initially we planned a CCC support team of 12 people for the powering tests from Aug 2014 to Jan The time span was changed several times, finally from end Sept 2014 to mid March  The MP3 was never the reason for schedule revisions.  The slow start of the HWC was very helpful to train all 12 MP3 members. 6 A. Verweij, MPE review, 2 June 2015

5. Resources How many resources were planned/used?  9 weeks with 5 shifts of 8 hrs of 2 persons  3 weeks with 5 shifts of 8 hrs of 2 persons and 2 shifts of 1 person (weekend)  9 weeks with 10 shifts of 8 hrs of 2 persons and 4 shifts of 1 person (weekend) Total: 314 person-days (pd) We planned “large” in order to learn (in the beginning), to complete the analysis manual, and to have the possibility to easily disappear from the CCC for a few hours (for other work, meetings, etc). We could have planned for more (about 500 pd) if needed. Many shifts were (partially) cancelled due to lack of analysis work. On average, the MP3 work took about 30% of the time for the 12 involved persons. How many resources would have been needed? In the last 12 weeks we could have maybe reduced to 1 person per shift during the week, so reducing by 12x5x2=120 pd. So about 200 pd in total would have been OK. 7 A. Verweij, MPE review, 2 June 2015

6. Three examples of aspects which worked well 1.The powering procedures were much completer and clearer than before:  Uniform structure among the 10 procedures.  Better description of the circuit, the protection and the signals.  Tests were also visually explained.  The sequencer and procedure were carefully checked against each other.  Less important info was moved to the Annex. 2.We created an analysis manual, so that we all analysed the tests in the same way. This will also be the starting point for further automatic analysis of future HWC campaigns and powering events during operation. We also created a database covering all magnet/circuit quenches during reception tests, HWC tests, and operation. 3.We reduced the number of signatures, by having automatic analysis of all 60 A and A circuits, and by taking over most of the analysis for the QPS and EE. 8 A. Verweij, MPE review, 2 June 2015

7. Three examples of aspects which gave difficulties 1.The data of the QPS post-mortem files still contain many timing errors, saturated points, spikes, which also make a dependable analysis and automation very difficult, if not impossible. Non-logical signal and crate naming, signal swaps, polarity issues, and incorrect documentation further complicated the analysis. 2.We expected to discuss issues related to the circuits such as long training, heater problems, internal shorts, insufficient bus cooling, DFB regulation etc. In stead, we got much more issues with the QPS, which continued to come back during the testing of the 8 sectors. The tracking and follow-up of these issues was insufficient and not efficient. 3.We did not receive a proper analysis manual from QPS and EE for analysis of the different tests before the start of the powering tests. This also resulted in some last-minute changes of the signature in AccTesting. 9 A. Verweij, MPE review, 2 June 2015

8/9. What needs to be improved / changed? 1.Proper tracking of issues during the powering tests in AccTesting with clear rules when a test can be repeated. 2.Before starting the powering tests, the Individual System Test (IST) of the QPS should be completely finished. An additional IST at very low current can be added, so that the QPS people can check proper signals, polarities, compensation factors, PM file contents. 3.There should be a QPS expert in the CCC at least as long as many QPS problems slip through the QPS-IST. 4.All circuits should have an updated circuit diagram, including signal names, polarities, measurement frequency, filtering, threshold(s), evaluation time, etc. 5.Control systems should be fully debugged and available several months before the start of the HWC. 10 A. Verweij, MPE review, 2 June 2015

8/9. What needs to be improved / changed? 6.The analysis manual for the PGC tests. 7.The analysis manual with clear acceptance and warning criteria for the QPS and EE part. 8.Review of the test requirements for the ‘End of the Year Technical Stop’. 9.Automatic analysis of more tests (also with more uniform approach). 10.Automatic analysis of powering events (with heater firing) during operation. 11.Continuous monitoring of protection-related signals. 12.Storage of analysis results in user friendly (easily accessible) database. 11 A. Verweij, MPE review, 2 June 2015

10. What will be done in the same way next time? 1.Preparation for the HWC about 6-12 months before the start of the powering tests. 2.Planning of the MP3 support during the powering tests. 3.Use of Twiki as communication means between MP3 members (and to the outside). 4.Carry on to automate and speed-up the analysis of the powering tests, while keeping the same level (or improving) the quality. and of course much much more…. 12 A. Verweij, MPE review, 2 June 2015