Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review 22-24 November 2013.

Slides:



Advertisements
Similar presentations
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Advertisements

Leak Testing QC of Cold Vacuum Systems the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank.
QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank TE/VSC - QRL Leak Tests.
Vacuum, Surfaces & Coatings Group Technology Department Cleanness of the 3-4 cold beam lines Outline:  History: Status of 2009 cleaning  Foreseen and.
1 Integration of collimators in the dispersion suppressors Status of 11 T cryo- assembly integration Dec 17, 2013
New HV test specification for the LHC N. Catalan for the EI section.
Bilan du contrat Renco Piping contract F467 TS workshop Archamps Mai 25 th 2005 R. Principe TSCV.
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
Overview of SMACC-QA 1.Recall of SMACC-QA organization 2.Tuning the procedures 3.Main results from the QC teams 4.Auditors findings Ranko Ostojic 23 July.
Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
Status of handling studies for PSB-LIU Caterina Bertone EN-HE LIU-PSB 17/09/2015 Courtesy: A. Newborough EDMS
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LHC Hardware Commissioning Review May 2005, CERN, 1211 Geneva 23 1 LHC Hardware Commissioning Review Contribution ID: 20 – Quality assurance and.
M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve.
Technology Department 1 Visit to Hall 180: Presentation of the consolidation process Third LHC Splice Review, November 12, 2012.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
TE/MPE/EE Short ‘Halfway’ Update ELQA – LS1 Activities MPE/The Electrical Engineering section Knud, on behalf of TE/MPE/EE – 20 September LSC Reminder:
Fourth LHC Splices Review Quality Assurance Review Review of actions from 3 last reviews NB : 8 non-closed ones from 1 st review 5 non-closed ones from.
1 Quality control of the LHC main interconnection splices before and after consolidation C. Scheuerlein and S. Heck 2 nd LHC splice review,
LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, slides  Status of LHC: electrical connections  Description of shunt.
MP3 recommendations from June 2013-Feb 2014 Arjan Verweij on behalf of the MP A. Verweij, LSC meeting 7/2/2014 One of the tasks of the MP3 is.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project … Courtesy ….
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
ABTEF Meeting, V. Namora Quality Assurance in the Superconducting Magnets and Circuits Consolidation (SMACC) project.
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
A. Perin, TE/CRG, DFBA LSC Page 2 LHC Long Shutdown 1 Committee June 14 th, 2013 A. Perin (TE-CRG) On behalf of the DFBA splices consolidation.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
MSC Technical Meeting 29 August 2013 Overheated QBBI.A21L6 F. Savary with contributions from N. Dalexandro, H. Prin, C. Scheuerlein, P. Voisin.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.
LHC Risk Review Installation Progress Francesco Bertinelli – TE/MSC 5 March, 2009 (20 minutes) On behalf of - and with several contributions from – the.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
S. Barbanotti - DESY Requirements Conformance for SRF Cryomodules Workshop 16/10/2014 – ESS, Lund XFEL cryostat main components: Quality Assurance and.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Third LHC Splices Review SMACC Organisation Scope of work (What’s new since Nov 2011) Organization chart update Human resources Budget Unforeseen? Unexpected?
Magnet activities in SPS during EYETS
SMACC Eighteenth report [20 min] 07/02/2014
Ti/SS transitions A.Basti INFN-PISA*
SMACC Tenth report [15 min] 13/09/2013
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Cutting and welding First internal LHC Dipole Diode Insulation Consolidation Review 10 Oct 2017 G. Favre / A. Amorim Carvalho G. Favre EN-MME.
Update of cryogenic activities
Cutting and welding First internal LHC Dipole Diode Insulation Consolidation Review 10 Oct 2017 G. Favre / A. Amorim Carvalho G. Favre EN-MME.
LS1 Committee January 24th, 2014
Long Shutdown for the LHC: Vacuum Beam Pipes
Consequences of warming-up a sector above 80 K
MPE main activities planned for LS2
SMACC local splice quality control
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
Consolidation of the dipole diode insulation Technical aspects
TE-MSC activities in SPS during YETS
Update on development of consolidated insulation system and procedures C. Scheuerlein, 4th DISMAC meeting,
The 11T cryo-assembly: summary of design and integration aspects
K. Foraz on behalf of OSS members
Q1-Q2, Q2-Q3 Interconnect Zone Disconnection Q1 Magnet Extraction
WP3 Meeting – December the 10th 2015 H. Prin
Shortening the long RQF/RQD busbar segments in points 1 and 5
Presentation transcript:

Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013

Outline I. Work organisation II. Sector 5-6: lessons and improvements III. Status of special activities IV. Status of magnets replacement V. QC VI. Traceability VII. Still to do and conclusion

Work Organisation Interventions prior to the train: PIM consolidations Special opening (ELQA, leaks, RQ busbars segment shortening, early opening for splice analysis, Q7-DFBA M sleeves opening…) Magnets exchange Interventions in parallel of the train: Fixed urgent NCR raised during train consolidations

Team (16 persons) 3 month of training in surface before LS1 on mock-ups in building 180.

Sector interventions planned before start of LS1 (PIM consolidations, 3 leaks, ELQA)…. More than 40 interventions done! Flange replacements (10) Corrective action: partial cutting Cut of flanges for busbars machining (18) Corrective action: tooling re-design Cutting mark on flange weld Corrective action: modify tooling PIM damaged (5) Corrective action: add protections Q7-DFBA M sleeves opening (train machine doesn’t fit) SIT intervene in 23% of the IC of the sector.

Sector 5-6: lessons and improvements PIM damaged Q9 M-N pipes cutting Mark during cutting M flange cutting Only 7 interventions in sector 6-7 up to now! Corrective actions applied in sector 5-6 improve the quality.

Status of special interventions PIM Only 2 PIM found broken during ball test (1-2 and 8-1) instead of 14 expected. 5 PIM damaged during SMACC (5-6). Leaks 3 old leaks repaired in 5-6 (2 M flange and 1 M2N flexible) 1 old leak repaired in 7-8 (M2N flexible) Sector Total Magnets0/0 8/80/024/248/120/160/840/68 NCR + preventive 10/102/26/125/72/20/40/26/631/45

Status of special interventions Early opening of M line sleeves and removal of insulation Sector Total ELQA tests 3/3 24/24 Splice analysis 0/0 5/54/48/822/220/115/544/55 Electrical NC 0/0 4/4 1/10/0 9/9 77/88 M sleeves opened prior to the train Opening for ELQA instrumentation

Status of special interventions RQ busbars segment shortening at point 1 and 5 4 IC’s opened, desoldering and cutting of busbars done. QEQI.11R5: soldering of the short- circuit. M1 ok but NCR on M2 (cable initially too long and external copper wedge too soft). (D.Etiembre / G.Bachmann) Before repairing After repairing Courtesy of S. Le Naour

Status of magnet exchange 14/18 magnets removed (last transport foreseen 09/08) 12 installed (last transport foreseen 15/08) Reconnection of all magnets foreseen before end of the year

Some pictures of cryomagnets transport Thanks to EN-HE colleagues

QC: Welding Welders qualification (automatic and manual welding) Internal QC Visual inspection Endoscopy Parameters recording for automatic welding External QC Visual inspection 100% (WQC) Radio on butt weld 100% (WQC) Leak tests (VSC) Systematic change of M line flanges 1 NCR detected by radio: crack due to copper particles (leak test ok). Corrective action: modification of the shielding tooling from copper to stainless steel (see EDMS report of A.Gerardin). Courtesy of A.Gerardin

QC: Desoldering and stabilisation Internal QC Same procedure than train Visual inspection Gauges Process data recording Traceability of data in MTF External QC Visual inspection (ELQC) SIT never do soldering of 13KA busbars.

QC: US welding US welding of spools US welding of line N

QC: US welding Qualification of welding machines before LS1 and after each transport. Production of standard samples for cold Rc measurements (cryolab) and tensile test (EN-MME). Same welding program than 2009 production. Same criteria than during the installation.

QC: US welding Example of reports for machine qualification

QC: US welding Internal QC production of samples just before soldering to warm-up the machine Visual inspection, gauges External QC Visual inspection by ELQC team N line EDMS # M line EDMS # Electrical tests by ELQA team after completion of a sector > 0.5 mm non-conform 1 mm ± 0.5 Alignment Excess length Gauge

Traceability New step created in MTF to register process data. All activities done by SIT are registered in excel files

Still to do and conclusion Still to do: Magnets replacement will finish before end of weeks of delay on the planning. Connection cryostat: 6/16 inspected ok. Still 2 to repair. Line Y repair Triplets copper braid SAM level gauges Follow train NCR SIT is able to follow the needs and we expect to free resources for major NCR last quarter of 2013.

Thank you for your attention.