Latest on the Schedule K. Foraz LMC October 7th, 2009 Wednesday, Oct. 7th 2009K. Foraz - LMC.

Slides:



Advertisements
Similar presentations
1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Acknowledgments: O.Aberle – F.Bertinelli – J.C.Billy - O.Capatina - J.Casas - L.Ceccone - S.Claudet J.Coupard - K.Dahlerup - R.Denz - K.Foraz - J.J.Gras.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006.
LHC Cryogenics: “From cool-down & HWC to operation with beam” S. Claudet, for LHC cryogenics Extended LTC, 3 Mar’08.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
17 july 2008 Inner Triplets upgrade – 2013 Very first Schedule.
Plan. 12/05/ Who are we? PM (Project Management and Resource Planning) – APT – IMPACT – PPTEU2 – Plan LS1 – 2012 –…–… Plan V2 – From LS1 to LS2.
7/23/ J.Coupard. 1) Cryogenic risks 2) Cryogenic phases from RT/floating to nominal and additional safety rules A. Sectors warmed-up to RT or considered.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
Dry runs and cold checkout Markus Albert, Reyes Alemany, Rossano Giachino, Delphine Jacquet, Verena Kain, Belen Salvachua Ferrando, Matteo Solfaroli Camillocci.
10/7/2003Thomas Schneider1 Status report of CERN/PNPI Tooling support for PNPI M2R2 Prototype Plans towards the PRR.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
X LCLS SCU NbTi Prototype Schedule Version: February 12, 2015 Update 23JUN2015 X X System complete and ready for test X System complete & tested w/Hall.
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
MPE Workshop for LS1 Summary of Global Activities Thanks to Speakers Arjan Verweij Hugues Thiesen Zinur Charifoulline Kajetan Fuchsberger.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 1 Coating of the SPS Main Dipoles Vacuum Chambers: Resources Needed for Project.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 30/08/2013LSC - S. Baird, M. Bernardini1.
An invitation to an open discussion We are team reviewing its performance globally We want to help each other to reach the objectives We know the other.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
LHC Cryogenics From cool-down to 1st beams Serge Claudet (LHC Cryo OP), On behalf of cryo teams involved.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
Overall planning, consolidation, stops, time line K. Foraz MAC – April 27th 2010 April 27th 20101K. Foraz - Machine Advisory Committee.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
ASTA Latest Update E. Harms April Photoelectrons first produced at ASTA on 20 June 2013 –Molybdenum (uncoated) cathode ‘Routine’ Electron operation.
01/09/ KTAG 5/8 sectors equipped DCS system in pogress DAQ commissioning in progress Test pressure scan this week (t.b.c) 01/09/20142.
EHN1 Extension planning
BA6 – crab cavity activities in EYETS
Status of LHC installation & New Installation Schedule
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
K. Foraz on behalf of OSS members
Update of cryogenic activities
Long Shutdown for the LHC: Vacuum Beam Pipes
LHC-TS3 Coordination meeting #3
MPE main activities planned for LS2
Status of the cryogenic system for B180
K. Foraz on behalf of OSS members
BLM planning 03/03/2014.
Children’s Hospital Update
Wednesday 03/11 – The Plan Finish electron-cloud program:
Two-beam Test-stand Design and Construction Status
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

Latest on the Schedule K. Foraz LMC October 7th, 2009 Wednesday, Oct. 7th 2009K. Foraz - LMC

Progress since September 9th Sector 12: QPS IST finishing. The first sector took longer than expected, and its experiment shows that 3 steps are needed for the full commissioning of the nQPS system. But the results are there. Powering tests phase 2 in progress Sector 23 ELQA at cold finished nPST racks installed, the tests for 2kA will follow the 6kA tests in sector 78  Powering phase 2 of the mains will start in wk. 43 (2 wks. of delay w.r.t September 9 th ) Sector 34 DSLC filling this week-end, boil-off will be done next week, 2 wks. of delay w.r.t September 9 th (Logistic) Sector 45 ELQA at cold finishing, some delays due to DFBA consolidation (valves and filter) Powering test, pahse 1 just starting 1.5 wks. of delay w.r.t September 9 th Wednesday, Oct. 7th 2009K. Foraz - LMC

Progress since September 9th Sector 56: ELQA at cold finished Powering tests phase 2 will start this week. 2 wks. of delay w.r.t September 9 th Is this coming from the DFBA consolidation ??? Sector 67 Boil-off in progress- 2 wks. of delay w.r.t September 9 th (Logistic) Sector 78 ELQA at cold finished nQPS tests at 2kA in progress Powering tests phase 2 in progress 2 wks. of delay w.r.t September 9 th Is this coming from the DFBA consolidation ??? Sector 81 ELQA at cold in progress, some delays due to DFBA consolidation 1 wk. of delay w.r.t September 9 th Wednesday, Oct. 7th 2009K. Foraz - LMC

Schedule outcomes Powering phase 2 – durations (number of shifts): the experiment of sector 12 shows that the number of shifts was overestimated, – but the experiment of sector 12 shows that about two weeks are needed to commission the system at 2kA & 6kA (part of the powering tests). Wednesday, Oct. 7th 2009K. Foraz - LMC

Powering  2 Updated Schedule Wednesday, Oct. 7th 2009K. Foraz - LMC Cool-down ELQA nQPS installation & IST nQPS &6kA Powering  1 Beam Commissioning 1.5 wks of delay w.r.t September 9 th

Remaining activities Doors: PM18 and SPS Floor painting Smoothing and beam vacuum chamber alignment in sector 34 Test of UPS batteries All the machine areas have been cleaned again, all the “alone” materials have been removed. So please keep the areas clean. Wednesday, Oct. 7th 2009K. Foraz - LMC

Conclusion Machine cold in wk.41 Powering tests phase 2 – Experiment of the first sector was very good – Durations (in term of shifts) were overestimated – New tests to be included for the nQPS – End of powering tests phase 2 = wk.47 (+1.5wks) Wednesday, Oct. 7th 2009K. Foraz - LMC