CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL Systems Engineer Chris Pasma, SSL Mechanical.

Slides:



Advertisements
Similar presentations
Fischer Manufacturing is an electrical fabrication company based in New Brighton, MN. We specialize in building to engineering specified requirements.
Advertisements

Protocol & Test Review Spaceport America Student Launch University/Institution Team Members Date.
Proposal Analysis Review NMSGC Student Launch University/Institution Team Members Date.
Data Test Review Spaceport America Student Launch University/Institution Team Members Date.
Flight Readiness Review New Mexico Space Grant Consortium University/Institution Team Members Date.
University of Kansas EPS of KUTEsat Pathfinder Leon S. Searl April 5, 2006 AE256 Satellite Electrical Power Systems.
Redesign of a Submersible Autonomous Data Collection and Transmission System (S.A.D.C.A.T.S.) Group Members: Matthew Rhoads BS ME (Lead) - Ballast, Hull.
14 October 2004AME 470 – Team Unum PDR #10 – 11 November 2004 Subsystem Integration Tim Culbertson Team UNUM.
STEREO IMPACT Preliminary Design Review 2001-September 11,12 David Curtis1 IMPACT Project Overview.
CINEMA PDR- MEC 1 CINEMA Mechanical Subsystem PDR August 22, 2008 David Glaser/Paul Turin.
SMART About NASA’s Magnetospheric Multiscale Mission (MMS) MAGNETIC RECONNECTION is a little-understood physical process at the heart of space weather.
THEMIS INSTRUMENT PER 1 UCB, May, 2005 EMC / Mag Instrument Test Plan & Results Michael Ludlam University of California - Berkeley.
TRIO-CINEMA 1 UCB, 2/08/2010 MAGIC Patrick Brown Imperial College London.
SPP FIELDS V5 Antenna Mechanical Peer Review David Glaser, Paul Turin, Jeremy McCauley, John Bonnell, Dennis Seitz SSL UCB 7/17/13.
Continuing Embry- Riddle’s CubeSat Satellite Development Program Presented by Clayton G. Jacobs Embry-Riddle Aeronautical University, Prescott EagleSat.
TRIO-CINEMA 1 UCB, 2/08/2010 STEIN Intro Davin Larson Space Sciences Laboratory University of California, Berkeley.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
Tielong Zhang On behalf of the CGS Team in the Institute of Geology and Geophysics, Chinese Academy of Science Spacecraft System and Payload China Geomagnetism.
CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL Systems Engineer Jerry Kim, SSL Mechanical.
CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL Systems Engineer Jerry Kim, SSL Mechanical.
CINEMA Mission Readiness Review
August 11, 2009 Small Satellites Conference A New Particle Detection Instrument for Space Weather Research with CubeSats David Glaser Space Physics.
DINO PDR 23 October 2015 DINO Systems Team Jeff Parker Anthony Lowrey.
TRIO-CINEMA 1 UCB, 2/08/2010 Instrument Interface Board Dorothy Gordon CINEMA - EE Team Space Sciences Laboratory University of California, Berkeley.
CINEMA (CubeSat for Ions, Neutrals, Electrons & MAgnetic fields) Jerry Kim * David Glaser † Thomas Immel ‡ * Systems Engineer, †
Week 7 Status Updates. Statement of Work: To design and prototype an attitude control system (ACS) for a Cube-Sat. This ACS will align the Cube-Sat with.
Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental Nuclear Physics Division 12 GeV Trigger System Status Update.
Taeyeon Kim. Page  2 1.Vibration test plan for KHU 2.Harnessing 3.STEIN Housing 4.Future work.
CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL Systems Engineer Jerry Kim, SSL Mechanical.
TRIO-CINEMA 1 KHU, 08/10/2010 TRIO-CINEMA Activity in Korea Jongho Seon 10 Aug 2010.
NASA Operational Simulator for Small Satellites (NOS 3 ) NASA IV&V Independent Test Capability (ITC) Team Mr. Scott Zemerick
BUZZSAT CONTROL SYSTEM Control System Architecture.
Instrument Status GLM Science Team Meeting 9 September 2016 Marc Rafal/GSFC GLM Instrument Manager.
STEREO IMPACT Critical Design Review 2002 November 20,21,22 Acuña1 MAGNETOMETER (MAG) M. H. Acuña NASA/GSFC Laboratory for Extraterrestrial Physics.
SPP FIELDS DFB Quarterly June 16, 2015 Solar Probe Plus FIELDS Instrument Quarterly Q Digital Fields Board (DFB) 1.
Solar Probe Plus Fluxgate Magnetometer QSR – Oct SPF MAG Quarterly Report – Oct 2014 The MAG EM1 (EQM) (board and frame at right) was successfully.
LiteBIRD US Team Meeting 10/13/2015 Team Meeting at UCB SSL1 Intro to SSL.
CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL System Engineer David Curtis, SSL STEIN.
CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL System Engineer David Curtis, SSL STEIN.
TRIO-CINEMA 1 UCB, 8/10/2010 CINEMA Project Update Thomas Immel UCB/SSL Space Sciences Laboratory University of California, Berkeley.
Component Selection and PCB Fabrication Supervisor: Dr. Peter Driessen Presenter: Justin Curran.
TRIO-CINEMA 1 UCB, 2/08/2010 CINEMA Mechanical Systems David Glaser Mechanical Engineering Space Sciences Laboratory University of California, Berkeley.
Mar 18, 2003PFIS CDR1 Control System Summary of Changes Since PDR All the motors, drivers, sensors, switches, etc. have been chosen Built up a mechanism.
FM1 Instrument Suite Pre-Ship Review (PSR)INT- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) INTEGRATION AND TEST PLANS Jeremy.
TRIO-CINEMA 1 UCB, 2/08/2010 CINEMA Solar Array Design Review Yashraj Khaitan David Glaser Kevin Jenkins Chris Pasma Space Sciences Laboratory University.
June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota
Introduction: The on-board measurements available for control are a dual-slit sensor to find the elevation of the sun and a magnetometer to measure the.
TRIO-CINEMA 1 UCB, 2/08/2010 Integration and Test Program Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley.
TRIO-CINEMA 1 UCB, 10/8/2010 Chassis & Avionics Stack Design Jerry Kim Mechanical Engineering Space Sciences Laboratory University of California, Berkeley.
BSMIan Pain, UK ATC SPIRE Instrument Intermediate Design Review April 23, RAL 1 Beam Steering Mirror Sub-System IIDR Overview Ian Pain UK ATC Colin.
TRIO-CINEMA 1 UCB, 2/08/2010 Mission Design Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley.
TRIO-CINEMA 1 UCB, 2/08/2010 ACS Dave Auslander, Dave Pankow, Han Chen, Yao-Ting Mao, UC Berkeley Space Sciences Laboratory University of California, Berkeley.
Status of EPS Battery configuration finalized Solar panel layout –finalized Solar panel Substrate is ready for bonding EM – fabricated and Completed the.
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review Integration & Test David Curtis, PF Package Manager.
TRIO-CINEMA 1 UCB, 2/08/2010 System Design Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley.
P10203 LV1 MOTOR CONTROLLER FINAL REVIEW MAY 14, 2010 Electrical: Kory Williams, Adam Gillon, Oladipo Tokunboh Mechanical: Louis Shogry, Andrew Krall.
TRIO-CINEMA 1 UCB, 2/08/2010 FSW & Operations Winter Summary Seyoung Yoon KHU EE Team.
USNA Standard CubeSat Bus USNA-P1 CubeSat (USNA-14)
Planetary Lander PDR Team Name
Preliminary Platform Design for KuaFu-A
Overview 3 2 Introduction Design Analysis Fabrication Testing
CINEMA System Engineering
Agenda. Solar Probe Plus FIELDS Main Electronics Package iPER Agenda Feb 2, 2017.
Solar Probe Plus – FIELDS Main Electronics Package
ACS UC Berkeley Space Sciences Laboratory
Spacecraft Structures
HA1L High Altitude 1U Laboratory
Control System Summary of Changes Since PDR
Structures March 13, 2004.
CONTOUR NGIMS Electronics Test History
Presentation transcript:

CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL Systems Engineer Chris Pasma, SSL Mechanical Engineer David Glaser, SSL STEIN Scientist Davin Larson, UCB MAGIC Scientist Tim Horbury, ICL Imperial College London CINEMA

GENERAL NOTES 11 UCB currently students on CINEMA team. In collaboration with students at KHU, visiting students from Puerto Rico. Magnetometer from ICL Started a Seminar class devoted to CINEMA Current Mass Budget: Around 2.7 kg, harnessing and redesigns Thermal Model: Analytical at SSL, FEA from KHU, check with Solidworks Launch Provider: Still backup on NPP launch, alternatives

SUBSYSTEMS Electrical Power Progress Building Flight Panels Vibration and Thermal Cycling of panels Testing of Battery/ EPS Issues Clean Room facilities Interference with torque coils Cracked Cell during Thermal Cycle Next Steps Finish Flight Panels Build High Voltage Power Supply C & DH Progress Reviewing Commands FSW Issues Narrow down the amount Next Steps

SUBSYSTEMS Radio Communication Progress ETUs of both S-band and UHF antennas NTIA Application Issues NTIA process moving slowly Problems connecting Coaxial Cable to Whip Antenna Next Steps Finish NTIA Frequency Assignment Purchase Radios/ Antennas Redesign Whip Antenna ACS Progress Torque Coils tested, new wire Sun Sensors tested, refab of flight parts Finishing simulation Issues Varying settling times in simulation Next Steps Integration of ACS and Flight Software Speed up settling time Assemble Flight Parts

SUBSYSTEMS Spacecraft Structure Progress ETU built, being used for harnessing, stack integration Holes drilled into it as needed Issues Hard to machine Next Steps Slight redesign to make fabrication more precise. STEIN (SupraThermal Electrons, Ions and Neutrals) Progress New detector/ ASIC Issues Changes caused by the new hardware Next Steps Addressing these

SUBSYSTEMS MAGIC (MAGnetometer from Imperial College) Progress Single axis ETU complete Triple axis ETU in testing Issues Behind Schedule Next Steps Integrate with flight software Other Components Instrument Interface Board is being assembled. FPGA code fully simulated, waiting to run on the board. Harnessing done in Solidworks, working with the mockup chassis