TE-CRG Interfaces Fair S-FRS magnets - CERN cryogenics 11.06.15 Control interface CERN-GSI for B.180 cryogenics Control interface CERN-GSI for B.180 cryogenics.

Slides:



Advertisements
Similar presentations
SEE System Design Product Presentation The Computer-Aided Design Specialist dedicated to Electrical Engineering, Systems and Industrial Fluids.
Advertisements

Electrical distribution for ALICE experiment & Electronic Rack Control S. Philippin.
CO2 progress and issues on the control system Lukasz Zwalinski – PH/DT
André Augustinus 16 June 2003 DCS Workshop Safety.
LSC - 28 February M. Pezzetti – Cryogenics 1 28 February 2014 M. Pezzetti EDMS Id: v.1.
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
PLC DEVELOPMENTS FOR NEW VACUUM DEVICES IN THE LHC AND NA62
FUNDAÇÃO PARA A CIÊNCIA E TECNOLOGIA FCT Trainee Program Follow Up João Rodrigo Alvelos Ferreira | Started March 2013 October 2014 TE-VSC-ICM.
Setup Guide - Profibus communication AC141x with Step 7 V5.5 English
1. Commissioning of cryogenic crates using Mobile Test Bench 1. The Mobile Test Bench 2. Cryogenics crates and equipment – types of transducers and actuators.
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
DCS LEB Workshop ‘98, Rome, Detector Control System, H.J.Burckhart,1 Detector Control System H.J Burckhart, CERN u Motivation and Scope u Detector and.
(C.Betz Kick-Off Meeting Vacuum 5th March 2013) Agenda: First steps using WinCC OA First steps using UNICOS V5 Vacuum Test Rig Principles of.
IBL CO 2 cooling control system development status Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI Florian Corbaz – EN/CV/DC.
ISOLDE Vacuum Controls (CERN-GSI WS), S. Blanchard TE-VSC-ICM UNICOS Vacuum Objects Specifications Review Sebastien Blanchard TE/VSC Interlocks,
LTC Extended days, 03 March’08 J.M. Jimenez, AT Vacuum Group LHC Vacuum commissioning J.M. Jimenez On behalf of AT-VAC.
Diagnostic & Troubleshooting Date 06/09/00, Page 1 Diagnostic & Troubleshooting s.
2 Technical seminar - 5 th June 2014 Vincent Roger - TE-MSC-TF.
Progress report on the test facility project design and construction P. Schnizer and L. Serio on behalf of bldg. 180 test facility project team members.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
ITER – Interlocks Luis Fernandez December 2014 Central Interlock System CIS v0.
Organization of cabling information Creating a Medaustron Cable Database 1 That’s what we don’t want!! MACS 28/06/2011 Sebastien Pelletier Cabling Database.
Ethernet IP solution for ATLAS IBL and CMS Pixel detectors CO 2 cooling plants Lukasz Zwalinski PH/DT/DI.
Vacuum Controls Status MACS week December 2010 PP a-JWA-VacControlStatus.ppt Joachim Wallner 1.
André Augustinus 17 June 2002 Technology Overview What is out there to fulfil our requirements? (with thanks to Tarek)
FAIR Accelerator Controls Strategy
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
MERIT Hg System Final Design Review Hg Target System Controls V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma Science &
AdV- VAC CTRL SYS/Cryo Interface 06Feb2013. Cryotrap cryogenics (simplified sketch) = the ‘electronic’ equipment needed to read LN2 level, temperature,
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Chiller control system Lukasz Zwalinski – PH/DT.
Steve Lewis Gas Attenuator 11 December Instrumentation & Controls Steve Lewis 11 December 2006 LCLS Gas Attenuator Preliminary.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
60kW Thermosiphon control system
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
SAFETY DURING HARDWARE COMMISSIONING, 18 October 2007, D. Bozzini, AT/MEL-EM 1 Safety during Hardware Commissioning Davide Bozzini on behalf of the ELQA.
CEA DSM Irfu SIS LDISC 18/04/2012 Paul Lotrus 1 Control Command Overview GBAR Collaboration Meeting Paul Lotrus CEA/DSM/Irfu/SIS.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
Gas Coordination Meeting Cabling. General Philosophy Cables between racks within the Surface Gas Building or between racks within the Underground Gas.
ISOLDE Vacuum Controls (CERN-GSI WS), S. Blanchard TE-VSC-ICM UNICOS implementation in ISOLDE Sebastien Blanchard TE/VSC Interlocks, Controls.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
E.Sbrissa EP/TA3 - IC ATLAS EDR_MAG Magnet Project Fault analysis, QA & Failure rate.
TE-CRG Activities D. Delikaris, TE-CRG.
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 1 Claude DEHAVAY - CERN/AB/CO/HT Installation Readiness Report - Controls.
1 MQXF(S) Magnet Interface Document MQXF(S) magnet interface document will describe electrical connection between the magnet and the header assembly Scope.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
WA105, SC Collaboration Meeting, CERN, 07th March 2016 AIMARD B., LAPP BALIK G., LAPP BOURGEOIS N., CERN BRUNETTI L., LAPP CANTINI C., ETHz MURPHY S.,
ESS (vacuum) control system Daniel Piso Controls Division February 20, 2013.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
1 Cryogenics Instrumentation & Controls Commissioning for the LHC AB/CO viewpoint Enrique Blanco AB/CO IS.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
Neutrino Platform Proximity Cryogenics 68th EHN1 Cryogenics Integration TE-CRG
ProtoDUNE - SP SLOW CONTROLS MEETING 11/11/2016 CERN – EP/DT
IT-4189 Supply and installation of a cryogenic distribution system
BA6 – crab cavity activities in EYETS
LAPP BPM Read-out Electronics
PLC-based control systems at SOLEIL - ICALEPCS 2017
BINP, Sergey Pivovarov, Panda magnet meeting at GSl, June 07, 2016
MAUVE CO2 cooling review
XFEL Vacuum System Commissioning
Cryogenic C&C Scope of work
CERN with UNICOS M. Pezzetti AT_ECR_CE 27 June 2005.
Vertical Cryostat Kick-off metting
PSS verification and validation
Machine Protection PLC Based System Verification and Validation Plan
Vacuum Control System for Monolith Vacuum
Review Bloc 4 and SM18 facilities and upgrade
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

TE-CRG Interfaces Fair S-FRS magnets - CERN cryogenics Control interface CERN-GSI for B.180 cryogenics Control interface CERN-GSI for B.180 cryogenics V. Inglese, M. Pezzetti, B. D’Hulster

TE-CRG Interfaces Fair S-FRS magnets - CERN cryogenics Global cryogenic control architecture GSI equipment

TE-CRG Interfaces Fair S-FRS magnets - CERN cryogenics Control interface with GSI GSI racks for magnet instrumentation must use a Profibus DP interface with the CERN cryogenic control system o All signals shall be conditioned and calibrated, and exchanged with CERN in engineering units o These signals will be stored through CERN’s archiving facilities (TIMBER) by means of filters set according to CERN policies o Suitable naming complying with CERN standards shall be used for signal tags => OK, details of Profibus exchange to be defined (see dedicated slide). => Possibility of Ethernet exchange For each test station, the following items are reserved for GSI: o 2 CERN standard racks => OK o 5 kW / 400VAC (3.5 kW for current leads electrical heaters, 1.5 kW for remaining equipment) => To be validated by GSI o UPS & Ethernet => UPS only for QPS, so not in cryogenic racks => Ethernet required, how many plugs? in which racks? Slide presented on 12 th May 2015

TE-CRG Interfaces Fair S-FRS magnets - CERN cryogenics Instrumentation and cabling No electrical connections exchange from GSI magnet control system to cryogenic control system are foreseen for hardware safety chains and interlocks GSI Cable list to be revised (voltage taps to QPS) Who provides cables and connectors? If GSI => CERN safety approval required If CERN => Agreement between CERN specialists (EN/EL) and GSI needed + connectors and pinning to be defined by GSI Cable destination on magnet to be specified by GSI (for cable trays preparation and installation) Magnet current leads : Electrical heaters are auto-regulating, no enable signal foreseen in cryogenic PLC Flow control valves: who is controlling what? So far PV valve to cryogenic system, all the rest to magnet control system (to be clarified).

TE-CRG Interfaces Fair S-FRS magnets - CERN cryogenics Communication scenario definition Can we have the Magnet Control System (MCS) architecture foreseen by GSI? Profibus exchange to be defined between Cryo Control System (CCS) and MCS. Possibility of Ethernet exchange (SEND & RECEIVE SIEMENS function). Siemens CPU used for CCS. In any case a communication table has to be defined by GSI for the exchange (list of signals with name, unit, range,…).