1 UK PM Report Costs & Schedule Alan Grant, STFC.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
SS and AFC Control Systems Brian Martlew 21 st Sept 2011.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MICE Collaboration meeting May 31 st – June 3 rd 2009 RAL Tim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 APRP Meeting MICE UK work packages Costs and schedules Organisation and monitoring Schedule summaries Cost summaries Andy Nichols, STFC, 15/8/11.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
MICE magnetic measurements Sequence of events and MICE hall movements Alain Blondel – 10-April 2012 revision from 13 December 2012.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
MICE - UK Project Progress Roy Preece 30 th April 2013.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
MICE Integration Engineering Jason Tarrant - STFC l Contents »Device Interfaces – General »AFC »Spectrometer Solenoids »RFCC »EMR / KL »South Mezzanine.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be Jun at IIT and the 19th at Fermilab right before the.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Hydrogen Delivery System Schedule MICE Schedule Review 23 rd -25 th May 2011 M Hills STFC.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – Cost to Completion Risks – Top level to completion – R9 working space – Summary 2 RLSR 24/11/2014.
MICE CM35 Status and Goals Alain Blondel 1 WELCOME TO MICE CM35! – Status and Goals - Many thanks to Chris Rogers, Debbie Loader and Rose Hayes for taking.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MPB 31 October 2012 and FAC 15 November monitor how well we are doing in assembling step IV ! -- should deliver a ‘realsitic schedule scenario’
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 MICE Schedule Review no 1 Aims of review and description of review charge Motivation and external drivers Aims of the review A few of the problems Description.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Finance Roy Preece STFC RAL Oversight Committee Meeting 27 th November 2015.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – FY 2014/15 – Cost to Completion Risks – Top level to completion – R9 working space – Summary.
PSAG mtg 20/03/2015 Finance Alan Grant. 2 PSAG mtg 20/03/2015 Finance Update FY14/15 – February Figures Additional capital funding in January of £63K.
PSAG mtg 3/2/2014 PSAG mtg Alan Grant. 2 PSAG mtg 3/2/ MICE Finances FY 2013/14.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
Muon Ionisation Cooling Experiment Overview
Status of the MICE Construction Project
UK Financial Plan & Risks
MICE CM31 Schedule summary
Presentation transcript:

1 UK PM Report Costs & Schedule Alan Grant, STFC

MICE Allocation 2 Finance sheet updated to show new approved allocations. Propose to start new sheet for this next phase of new allocations. No Common Fund income included at present. STFC allocations shown as mostly capital – need to agree split between capital & resource yr on yr. ~ £3.05M for next 4 yrs except this yr £2.88M as we brought forward £170k. STFC agreed allocation this yr excluding Universities £2.186M wp 8 resource wp 1-7 capital

Forecast Cost FY 2012/13 3  Forecast costs to deliver step IV only.  Labour intensive this year.  Assumed similar income lines from previous yr for Common Fund & EU Card.  Still some work to do to trim negative margin.  Plan to monitor each month.  Final payment for AFC not included in these figures.

Step IV 4 Spectrometer Solenoid & Tracker Focus Coil EMR

Step IV Installation 5 Step IV base plate installation complete. AFC rail installation complete. SS rail system installation complete. Hydrogen system tests ongoing. Preparing for Tracker single station tests - beginning 15 th May. EMR delivery delayed until beginning of November. EMR commissioning after step IV installation.

Hydrogen System 6 Helium tests well underway, currently liquefying the helium, aim to complete by 18 th May. Hydrogen tests begin after helium tests, currently working through Procedural Safety Requirements. Aim is to complete before we accept the Focus Coil & Solenoid into the MICE Hall.

Focus Coils 7 Focus coil delivery slipped to 1 st week in June. Delays due to supplier mechanical issues. Control system complete and ready to be shipped to Tesla – waiting for Tesla. Potential resource clash with controls group who maybe needed to test the Spectrometer Solenoid in US. Final payment was in last yrs budget - NOT accounted for in this yrs budget.

Spectrometer Solenoids 8 Pumping down taking little longer than expected vacuum levels now Cool down now planned for 22 nd May. Control system in place and commissioned. Delivery of 1 st Solenoid expected first week in August.

Magnet Mapping & Movement Sequence 9 Field mapping to be carried out with beam path clear – no obstructions!!! Focus Coil & 1 st Spectrometer Solenoid mapping clash currently.  Will manage this clash when we have the magnets.  May delay the final completion date by 2-3 weeks.