ATC/ABOC 2007T. Eriksson CERN AB/OP AD Machine and Experimental Areas – Operation and major problems in 2006, outlook for 2007.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

1 MICE Beamline: Plans for initial commissioning. Kevin Tilley, 16 th November. - 75days until commissioning Target, detectors, particle production Upstream.
Re-commissioning the Recycler Storage Ring at Fermilab Martin Murphy, Fermilab Presented August 10, 2012 at SLAC National Laboratory for the Workshop on.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
P. Spiller, SIS18upgrade, Peter Spiller GSI, Darmstadt Kick off Meeting - EU Construction DIRAC Phase SIS18 upgrade.
LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
AD status in 2012, foreseen consolidations at AD ADUC 20/11/2012T. Eriksson CERN BE/OP.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
IEFC 22 March 2011T. Eriksson CERN BE/OP How to ensure a bright future of the AD.
RHIC Status: Startup Run 12 V. Schoefer RHIC Spin Collaboration Meeting 1/13/12.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
RHIC Run14 Time Meeting. Run14 Status – Apr. 15 Operations running well, 12 stores over the past 7 days with 1 lost to another “super quench”. Testing.
Status of the AD ADUC 13/6/2012T. Eriksson CERN BE/OP.
Results of the argon beam test at Linac3 D. Küchler BE/ABP/HSL Including feedback from R. Scrivens and M. Bodendorfer.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Status and Prospects for the AD and ELENA
Accelerator Issues Fermilab Antiproton Experiment Keith Gollwitzer Antiproton Source Department Accelerator Division Fermilab.
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
F All Experimenters' Mtg - 2 Jun 03 Weeks in Review: 05/19/03 –06/02/03 Keith Gollwitzer – FNAL Stores and Operations Summary Standard Plots.
AD start-up 2014 A rough and brief summary MSWG 16/01/2015T.Eriksson BE/OP1.
Recent Work Towards Increasing the AP2 & Debuncher Aperture – Keith Gollwitzer – May 9, Recent Work Towards Increasing the AP2 & Debuncher Aperture.
The SPS as a Damping Ring Test Facility for CLIC March 6 th, 2013 Yannis PAPAPHILIPPOU CERN CLIC Collaboration Working meeting.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
SPS proton beam for AWAKE E. Shaposhnikova 13 th AWAKE PEB Meeting With contributions from T. Argyropoulos, T. Bohl, H. Bartosik, S. Cettour.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
ELENA EXTRACTION LINES W. Bartmann, D. Barna, M. Fraser, J. Jentzsch, R. Ostojic ELENA Commissioning discussion, 23th November, 2015.
ATC-ABOPC Days 2008: Session 1 Summary ATC-ABOC days Summary Session; February Session coordinated by B. Mikulec AB-OP and O. Br ü ning AB-ABP Operation.
MERIT review, Dec. 2005CERN AB-ATB1 CERN installation I. Efthymiopoulos, A. Fabich, J. Lettry CERN AB-ATB MERIT review, Dec.
Antiproton Decelerator (AD) Consolidation ADUC 13/1/2015T. Eriksson CERN BE/OP1.
ELENA: Commissioning & operation ELENA beam commissioning Operation 12/11/2015T.Eriksson CERN BE/OP/AD1.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
19 January 2006 PS&SPS DAYS AD equipment tests and startup with beam Slide 1 AD and AD experimental areas: equipment tests and startup with beam Tommy.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Villars, 26 September Extra Low Energy Antiproton Ring (ELENA) for antiproton deceleration after the AD Pavel Belochitskii for the AD team On behalf.
A. Herlert, CERN PH-IS ISOLDE scientific coordinator’s report INTC meeting, May 19, 2008 ISOLDE scientific coordinator’s report INTC meeting, May 19, 2008.
13 January 2005 PS&SPS DAYS How can we restart AD in 2006? Slide 1 How can we restart AD in 2006 ? Tommy Eriksson AB/OP/AD.
LIU-Ions overall status and outlook: LEIR H. Bartosik for the LIU-IONS LEIR team* with lots of material from “Beam dynamics studies on LEIR”, H. Bartosik,
T.Eriksson P.Belochitskii G.Tranquille CERN, BE department, 1211 Geneva 9 September 2011T. Eriksson CERN BE/OP.
Low Energy Antiproton Facility at CERN Christian Carli on behalf of the AD and ELENA team …. with special thanks to P.Beloshitskii, T.Eriksson and S. Maury.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
18/March/2008OP-days S.Mataguez / O.Hans1 Hardware Problems in the PS complex LINAC 2 BOOSTER PS AD Thanks to all that helped and provided information,
DTU A VISION OF SUPPORTING NEUTRON CHOPPER ESS PT 1 - BUNKER SYSTEMS Discussion Document.
Slide 1 Overview Introduction Stochastic Cooling History of the Antiproton machines at CERN The AD and ELENA Conclusion.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
ELENA installation progress F. Butin / ELENA collaboration.
RHIC Status Haixin Huang Time Meeting 01/25/2011.
Parameters of ejected beam
Status of HESR 18th March Gießen Dieter Prasuhn.
Lead performance throughout the injector chain with focus on LEIR
Overview of Extra Low ENergy Antiproton ring (ELENA) and TE-EPC contribution to the project TE-EPC Group Meeting Michal Dudek 25th June 2015.
ELENA installation and commissioning status
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Installations up to Start of Commissioning
AD consolidation activities in LS2
LEIR IMPEDANCE AND INSTABILITY MEASUREMENTS
ELENA Overview and Layout Start of ELENA Commissioning Next Steps
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
High Radiation to Materials 16th Project Team Meeting – May 20, 2010
How to run ions in the future?
Alexander Herlert, CERN (PH-SME-IS)
How can we restart AD in 2006 ? Tommy Eriksson AB/OP/AD
2003 test beam with 25 ns bunched muons
ELENA Extra Low ENergy Antiproton Ring
I-LHC NOMINAL ions beam in 2007
(Beam) Commissioning Plan
Achieving Nominal Ion Beam PS Ion Progress
ELENA beam commissioning
Electron Cooling in ELENA - observations and plans
LEIR e-cooler operational experience and needs
Plans for future electron cooling needs PS BD/AC
Presentation transcript:

ATC/ABOC 2007T. Eriksson CERN AB/OP AD Machine and Experimental Areas – Operation and major problems in 2006, outlook for 2007

ATC/ABOC 2007T. Eriksson CERN AB/OP Contents AD restart and related problems The 2006 physics run What’s in store for 2007? Consolidation

ATC/ABOC 2007T. Eriksson CERN AB/OP AD startup after 18 months…. Extremely difficult startup: PS-complex schedule delayed 6 weeks due to PS rotor ( ) 3 weeks planned for AD startup – needed 8 weeks !!  –Problems in setting up electron cooler (19 days)  –PS injection septum failure (6 days)  –CERN general power distribution failure (4 days)  –Difficulties in finding correct trajectory for ALPHA line (8 days)  Physics finally started 22/8 instead of 18/7(all beamlines ok) …… …but with lower rep. rate and somewhat lower intensity 

ATC/ABOC 2007T. Eriksson CERN AB/OP Startup: Electron cooling difficulties Many,many problems during the PS repair (power converters, ctrls etc.) First beam on target 28/6 – 1 week to decelerate to low energies and discover e-cooling problems 50% of the 19 “cooling days” spent on cooler itself. 50% on other issues (ctrls, network, OASIS, supplies etc.) – inefficient ! Problems w. unstable residual collector voltage (cooling circuit?) Cathode stability verified after improvements in voltage divider When stable, momentum cooling rate much reduced in spite of much work on alignment, coupling compensation etc. Limited cooler diagnostics Problem “fixed” by drastically increasing cooling duration 300 MeV/c, 100 MeV/c)

ATC/ABOC 2007T. Eriksson CERN AB/OP H and V beam profiles at 100 MeV/c

ATC/ABOC 2007T. Eriksson CERN AB/OP “2006 cycle”: –Now 100s (86s in 2004) –Final emittances ok for reasonable deceleration and xfer efficiency –Rep.rate suffers also from longer PS- supercycles

ATC/ABOC 2007T. Eriksson CERN AB/OP Startup: ALPHA beamline Beam passes through strayfields of both ATRAP solenoids

ATC/ABOC 2007T. Eriksson CERN AB/OP Startup: ALPHA beamline New DE0.DHZ87 successfully commissioned with ATRAP2 3T. Shortly after, transmission = 0……??!! (solenoid off) Found (much later…) that despite normal beam on 5 downstream MWPC:s, a trajectory change through the septum caused the losses New MWPC will be installed in the sensitive region during this shutdown

ATC/ABOC 2007T. Eriksson CERN AB/OP The 2006 run Run time (h) Total Physics md uptime86%89%90% 71%65% All beamlines operational as of 22/8 (5weeks late): Run extended until 20/11 to compensate

ATC/ABOC 2007T. Eriksson CERN AB/OP The 2006 run Typical performance

ATC/ABOC 2007T. Eriksson CERN AB/OP The 2006 run Increased losses PS – AD target Increased deceleration losses Slower beam cooling at low energies Higher long. emittance Parameter (at extraction) DesignAchieved 2004Achieved MeV/c 300 MeV/c 100MeV/c, multiej. 100 MeV/c 500 MeV/c 100MeV/c multiej. Total energy spread [4s] [10 -3 ] 1 – – >12 Bunch length [ns] Number of antiprotons [107] /4.23.3/4.01.0*30.4* *6 Cycle time [s]

ATC/ABOC 2007T. Eriksson CERN AB/OP The 2006 run: ASACUSA Several subgroups including RFQD and multiejection (ej. at 2.4s interval on h=6)

ATC/ABOC 2007T. Eriksson CERN AB/OP The 2006 run: ATRAP Commissioning of new zone (ATRAP2); new e+ source  New trap with large-bore 3T superconducting solenoid (several quenches) Some handling problems with the new source New dipole corrects well for strayfield disturbance, but complications can arise when coupled with AD orbit trajectory drift

ATC/ABOC 2007T. Eriksson CERN AB/OP The 2006 run: ALPHA Commissioning of new trap ultimately aimed at trapping Hbars

ATC/ABOC 2007T. Eriksson CERN AB/OP The 2006 run: ACE Cell irradiation with 500MeV/c beam: Plans for AD cycle w. e- cooling at 300MeV/c and then acceleration for ejection at 500MeV/c abandoned……. Extended s-cooling at 2GeV/c Eh,Ev = 8pi, lbunch=500ns Some modifications to ej. line supplies 1 week exclusive run (including final setting-up)

ATC/ABOC 2007T. Eriksson CERN AB/OP shutdown work E-cooler: –Renovation of collector cooling system: improve water quality (conductivity); attempt to solve stability problems –Verification of all collector HW –2005 NEG improvement was successful, BUT we are running with one less Ion pump (feedthrough broken) “New” MWPC in DE0-line: –To simplify ALPHA line setup –Mech. design done w. upstream move of 2 quadrupoles –Optics consequences checked: hope for improvements…

ATC/ABOC 2007T. Eriksson CERN AB/OP shutdown work Shielding of DE1.STP26/DE1.MWPC42: under study New experimental area access system ACE: Alignment of DEM-line ASACUSA: –1 New Ion pump + refurbish 1 existing –Turbo pumps: last spare used, no longer supported (CERN-wide problem). To be discussed –RF buncher removal (end March?) ALPHA: Re-arrangement of zone. (+ general alignment/vacuum, not yet defined) ATRAP: (General services only, not yet defined)

ATC/ABOC 2007T. Eriksson CERN AB/OP shutdown work Safety issues: –Modification of platform near D305 (after crane accident) –New ATRAP e+ source: much overhead work –Condition of catwalks –Barracks/workshops…

ATC/ABOC 2007T. Eriksson CERN AB/OP 2007 (and beyond) requests ACE: awaiting request ASACUSA: awaiting subgroup schedule (for support planning) PAX: Initial feasibility study for proposed experiment underway.Internal target tests soon?

ATC/ABOC 2007T. Eriksson CERN AB/OP 2007 startup Extra HW-test time requested by AB/PO: 4 weeks in total Start with production beam 7/5 4 weeks for startup/md –Thorough study of e- vs. Pbar alignment for e-cooling –Set-up of new optics in DE0, DE3/4, DE2 No plans for tst protons, but it might be needed And: –Study of PS to AD line optics desirable –5-bunch production beam – is it far away?????

ATC/ABOC 2007T. Eriksson CERN AB/OP 2007 startup Physics run: 4/6 – 22/10 Plan to continue running during weekends AD operation: –2 shifts/day during startup, then: –1 specialist on-call/week –1 backup/week –ccc looks after AD during nights/weekends The same team also runs LEIR

ATC/ABOC 2007T. Eriksson CERN AB/OP ccc Running AD from ccc reinforces the need for: Improved machine stability = Electron cooler stability/performance Need improved correction of ecool trajectories Better tools for ejection beamline tuning = Need new monitors for fast, non-destructive measurements and corrections

ATC/ABOC 2007T. Eriksson CERN AB/OP AD Consolidation AD is now included in the general consolidation program…. ….at the bottom of the list…. Let’s look at only RS…and see what can be done ItemRSMaterial budget kCHF Staff requirements MY C10/C02 Cavity upgrade Stochastic cooling Pickup/kicker movement Horn pulser ignitron phaseout Stochastic cooling controls/instrumentation Horn pulser electronics Ej.line trajectory instrumentation (RF low level migration to DSP)

ATC/ABOC 2007T. Eriksson CERN AB/OP Conclusion General remarks AD downtime is increasing e-cooler is getting more and more difficult to set-up correctly Some equipment (eg. target area) has been operational for a very long time without intervention: know-how is disappearing Keen interest from users