Presentation is loading. Please wait.

Presentation is loading. Please wait.

Status and Prospects for the AD and ELENA

Similar presentations


Presentation on theme: "Status and Prospects for the AD and ELENA"— Presentation transcript:

1 Status and Prospects for the AD and ELENA
Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling

2 Outline AD start-up and status 2015 AD consolidation program
ELENA overview and status I was reading a book on anti-gravity the other night - I couldn’t put it down!! WAG, London, August 7, 2015

3 AD start-up status 2015 AD Physics Run 2015 started July 6th.
One month into the run we have so far had good up-time and good, relatively high ejected numbers. What is new? Why might the AD work better/worse than last year?? Shutdown work 2014/15 - Some examples: Start of major target area renovation Continued stochastic cooling renovation Kicker pulse generator re-location Magnet renovation Cabling clean-up Cryogenic Current Comparator (CCC) WAG, London, August 7, 2015

4 Injection/ejection kicker pulse generators for AD and ELENA
Situation at end of run 2014 Situation in early July 2015 …have been removed to make place for ELENA WAG, London, August 7, 2015

5 Kicker platform replacement
Pulse generators re-located to B393 including renewal of electronics/interlocks/controls interface etc. Kicker platforms in the new building 393 WAG, London, August 7, 2015

6 Main dipole magnet refurbishment
BHZ23 & BHZ24 renovated, 21 more of these will be done over the next years….. WAG, London, August 7, 2015

7 Cryogenic current comparator
Cryogenic Current Comparator installed in section 15. first results encouraging but due to cryo problems it will have to come out again next shutdown WAG, London, August 7, 2015

8 CCC results and Schottky comparison
WAG, London, August 7, 2015

9 Other items changed since last year
Stochastic cooling consolidation: notch filter control, SW for pickup movement 3 new BCT:s in injection line, replaces obsolete units Target area: extensive consolidation program underway. New targets & design, New horns, refurbishment of buildings etc. etc. WAG, London, August 7, 2015

10 The year so far? Good deceleration efficiency, transverse emittances and bunch length, but still room for improvement WAG, London, August 7, 2015

11 An old machine gets a make over!
AD consolidation An old machine gets a make over!

12 AD consolidation Most of AD dates from ~1980 => Main components are years old…., Due to other important CERN programs (LHC), only urgent issues were addressed for the first ~10 years of AD operation For many years AD was always below the budget cut-off line since it’s not part of the LHC program A small consolidation program (~2.3 MCHF), separated from the LHC program, started in in view of running AD until 2016 or so After approval of the ELENA project, the scope of the consolidation increased and is aimed at continued operation of AD for at least years after ELENA physics has started which means Concerned items are: Target area, magnets, power converters, vacuum system, beam cooling, instrumentation, RF, control system, Infrastructure etc. AD is at the moment in the middle of a major consolidation program with a budget plan of 23.8 MCHF allocated for the period 2014 – 2020 WAG, London, August 7, 2015

13 Target Area Since the AD start-up only limited follow-up was done
During p 𝑝 program (1980 – 1996) a full team was looking after design, operation and maintenance Since the AD start-up only limited follow-up was done Most of control equipment was conceived as prototypes Few problems occurred during 15 years of AD operation Repetition rate is now ~ 100s, the target area was designed for 2,4 s Very reduced maintenance over the year – loss of expertise Major consolidation activity has started in 2011/12 & LS1 and will continue through LS2 => Activities related to major items need to be started ASAP to be ready for LS2 installation Significant impact on AD physics in case of failure between LS2 and LS3 Know weak points (target, horn, magnets…) Very long physics stops (≥ year) Increase contamination levels and associated radiological risks Horn assembly failure discovered in LS1 is an indication that urgent consolidation is needed for the whole area WAG, London, August 7, 2015

14 Mobile shielding PSAIF irradiation pit Dump BHZ6024/25 transformer
Magnets dog-leg WAG, London, August 7, 2015

15 Magnets, ring and transfer lines
Main bendings (24): Renovation and re-shimming: Regular coil movement measurements on remaining units will determine which one(s) next. 3 units will be renovated so far. 21 to go. WAG, London, August 7, 2015

16 Magnets, ring and transfer lines
H/V correctors near e-cooler replaced during LS1. Ejection line quadrupoles (2) replaced during LS1. Spare inventory almost complete. Target area magnets: Quadrupoles upstream of target (9050 & 9052). Area is very hot,1 spare exists but lack of knowledge about state, manipulation & connections. Alternative designs are being considered including permanent magnets. 2015 – 2017 Remaining Bendings and quads: renovation of spare units Ejection line magnets (except DEM-line) will be replaced by e-static units for ELENA ~2017 WAG, London, August 7, 2015

17 Power converters Most urgent items consolidation finished during LS1.
General consolidation program for 2015 – 2020 approved; renewal & standardization Replacement of orbit corrector units with standard Cancun supplies in 2015 2/4 kV pulsed injection line converters to be replaced by new Megadiscap in 2016 – units are already in operation with good results. Replacement of thyristor converters by commercial units during LS2. WAG, London, August 7, 2015

18 Stochastic cooling Controls, electronics, delay/attenuator platform installation, individual u-wave amplifier power supplies and p/u & kicker movement motors/electronics all renovated or replaced during LS1. Notch filters: Replacement of large cable-box with optical filter system. 2015 0.8 – 1.6 GHz power amplifiers (48): Obsolete semi-conductors, increased failure rate. Prototyping for new design if old amplifiers become unrepairable or too unreliable. 2015/16. Vacuum tanks: Life expectancy and mechanical integrity of pickup and kicker vacuum tanks & s-cooling equipment inside. Possible consolidation not yet addressed. WAG, London, August 7, 2015

19 Electron cooling consolidation
Renewal of electron cooler: Build a new state-of-the-art cooler 2015 – Aim for installation in LS2. Existing cooler: Is >35 years old We have no spare magnets; very long down time if failure, significant cost for new spares Performance issues e- bpm:s not operational Momentum pbar 300 MeV/c 100 MeV/c Electron energy 35 keV 2.8 keV Electron current 2.5 A 100 mA Cooling length 1.5 m Drift magnet field 590 Gauss Electron beam radius 25 mm Cooling time 16 s 15 s εx / εy 3 / 3 (π × mm × mrad) 0.8 / 0.5 (π × mm × mrad) dp/p 10-4 < 7 × 10-5 WAG, London, August 7, 2015 19

20 Instrumentation BIPM H and V systems merged into one vacuum tank.
Orbit system: solution with individual ADC:s in 2015, similar to ELENA system. Will permit measurements during ramps – 2017 BBQ-tune measurement: Using existing pickup, commissioned but not yet in regular operation. 2015 CCC (Cryogenic Current Comparator): Intensity measurements of low-intensity beams. To be used in ELENA as well – 2016 Schottky analysis (longitudinal): integrate ageing DSP equipment into new C02 LL beam control system + new system for visual monitoring WAG, London, August 7, 2015

21 RF C02 HV & tuning power supplies. Interlock system. Required to make space for ELENA. C02 Low-Level: Migration to PSB/ELENA-like DSP based system (including Schottky analysis) – 2018. C10 Low-Level & High-Level renewal: C10 final stage (obsolete TH116 valves): New power amplifier/control/interlock systems to be developed: 4MCHF WAG, London, August 7, 2015

22 Controls/software => No major consolidation needs !
Major LS1 renovation: Front-end upgrade (ACCOR): ~complete (80-90%) renewal in LS1 Central Timing: re-design for de-coupling AD from the LHC injector complex Cycle Generation: adaptation to comply with new timing system New Beam Request Server Similar CT, CG and BRS systems will be implemented in ELENA FESA, Java migration, InCA: majority has been completed (standardization) Some implications: All AP:s have been adapted (OP + Eq. groups) Major debugging effort during 2014 start-up ! => No major consolidation needs ! WAG, London, August 7, 2015

23 Infrastructure Cryo-distribution line for AD experiments, large dewar outside building + distribution lines to experimental zones. 2015/16 B193/B195 cooling/ventilation: Requested for LS2 major upgrade B193 cranes: Requested for LS2 WAG, London, August 7, 2015

24 ELENA Overview and status

25 ELENA Overview Momentum range, MeV/c 100 - 13.7 Energy range, MeV
Circumference, m 30.4 Intensity of injected beam 3 × 107 Intensity of ejected beam 1.8 × 107 Number of extracted bunches 1 to 4 Emittances (h/v) at 100 KeV, π·mm·mrad, [95%] 4 / 4 ∆p/p after cooling, [95%] 10−3 Bunch length at 100 keV, m / ns 1.3 / 300 Required (dynamic) vacuum, Torr 3 × 10−12 WAG, London, August 7, 2015

26 ELENA Overview and Layout
Deceleration of antiprotons from 5.3 MeV to 100 keV to improve efficiency of experiments Circumference 30.4 m (1/6 the size of the AD) Fits in available space in AD hall and allows installing all equipment without particular efforts Lowest average field (beam rigidity over average radius) Br/R = 94 G (smaller than for AD 115 G) Extraction towards existing experiments (with fast electrostatic deflector) Line from H- and proton source for commissioning Wideband RF cavity Injection with magnetic septum (≈300 mrad) and kicker (84 mrad) Scraper to measure emittances (destructive) Quadrupoles High sensitivity magnetic pick-up for Schottky diagnostic (intensity) and LLRF Electron Cooler and compensation solenoids Extraction towards new exp. zone WAG, London, August 7, 2015

27 ELENA Overview and Layout
New annex building with kicker equipment Towards existing experiments AD Shielding ELENA ring New area with GBAR and AEgIS WAG, London, August 7, 2015

28 ELENA Overview and Layout
Transfer line (magnetic)from AD External source for commissioning Electro-static line towards existing experimental area Extraction towards new experimental area WAG, London, August 7, 2015

29 Selected Features and Challenges
Energy Range Machine operated at an unusually low energy for a synchrotron (down to 100 keV!) Lattice and geometry Many Constraints (Long straight Section with small Dispersion for Electron Cooling, Geometry in AD hall, Beta Functions and resulting Beam Sizes, Working Point ...) Hexagonal shape and optics with periodicity two (two long Straights without Quadrupole Magnets) Electron cooling Applied at two plateaus to mitigate losses and generate dense bunches Very low energy electrons at bottom plateau Bunched Beam Cooling at 100 keV extraction Energy to generate dense Bunches for Experiments Effect (perturbation) of magnetic field of cooler on circulating antiprotons: delicate study started, continuation under discussion Expected main performance limitation: Intra Beam Scattering IBS Determines beam parameters with cooling (equilibrium between the two processes) Vacuum System: fully baked with NEGs where possible to reach Torr Interactions with rest gas (Blow-up, Losses) not the dominant limitation despite the low energy Beam Diagnostics with very low Intensities and at low Energy E.g.: Beam currents down to well below 1 mA far beyond reach standard slow BCTs Intensity of coasting beam measured with Schottky diagnostics WAG, London, August 7, 2015

30 The situation as of this Monday
WAG, London, August 7, 2015

31 Main components production status
16 quadrupoles 3 skew quadrupoles Oct. 2015 Apr. 2016 3 TL dipoles 8 dipoles Magnet Ready Sector 2 18/02/2016 Sector 3 Sector 4 16/03/2016 Sector 5 Sector 6 13/04/2016 Sector 1 Magnet Ready 3 magnets 1 available 2 in October 15 Courtesy: D. Schoerling WAG, London, August 7, 2015

32 Main components production status (2)
14 H/V correctors 5 sextupoles 3 solenoids Magnet Ready Pre-series 10/2015 Series 12/2015 Magnet Ready 2 magnets 01/2016 Courtesy: D. Schoerling WAG, London, August 7, 2015

33 Main components production status (3)
Electron cooler: Critical for ELENA! Operate at very low electron energies (down to 55 eV). Operate at very low magnetic field to minimize disturbance to circulating low energy antiprotons – we have chosen 100 Gauss in the cooler. Have extremely good vacuum. Adiabatic expansion to reduce transverse temperatures. Very good field quality – especially in the cooler solenoid (B˔/Bǁ < 5 × 10-4 ). Orbit correctors and solenoid compensators. Magnetic system in production at TESLA, vacuum system designed and to be produced at CERN, Delivery expected 15 March 2016 WAG, London, August 7, 2015

34 Main components production status (4)
Other components: All in production – on time (!) RF Finemet cavity Scraper BTV Tune measurements Longitudinal pick-ups Beam Position Monitors Septum Injection kicker magnet Electrostatic elements SEM grids Vacuum equipment Supports WAG, London, August 7, 2015

35 Replacing the magnetic lines from the AD by electrostatic lines from ELENA
LNE00 LNE01 LNE02 LNE06 LNE07 LNE05 LNE04 LNE03 Atrap 1 Atrap 2 Replacing the current magnetic ejection lines with the new electrostatic ejection lines will take about 9 months!! + commissioning ~ 6 weeks! WAG, London, August 7, 2015

36 Possible scenarios for 2017 and 2018 with LS2 starting around mid 2018
~10 weeks (week 41 to week 50) ~8 weeks (week 15 to week 22) preceded by ion run ~33 weeks (week 18 to week 50) WAG, London, August 7, 2015

37 Possible scenarios for 2017 and 2018 with LS2 starting around end 2018
Detailed planning not yet available (dates guessed) WAG, London, August 7, 2015

38 Thanks! Summary and Outlook AD off to a good start 2015
Major upgrade work underway at the AD ELENA design finished – production underway ELENA installation is progressing according to plan – so far!!! 100 keV pbars coming to an experiment near you! – but when? Thanks! WAG, London, August 7, 2015

39 WAG, London, August 7, 2015


Download ppt "Status and Prospects for the AD and ELENA"

Similar presentations


Ads by Google