1 Antiproton Decelerator (AD) Consolidation ADUC 13/1/2015T. Eriksson CERN BE/OP1

2 AD consolidation Most of AD dates from ~1985 => Main components are 30 years old…. Due to other important CERN programs, only urgent issues were addressed for the first ~10 years of AD operation For many years AD was always below the budget cut-off line since it’s not part of the LHC program A small consolidation program (~2.3 MCHF), separated from the LHC program, started in 2009 in view of running AD until 2016 or so After approval of the ELENA project, the scope of the consolidation increased and is aimed at continued operation of AD for at least 10-15 years after ELENA physics has started which means 2030 - 2035 Concerned items are: Target area, magnets, power converters, vacuum system, beam cooling, instrumentation, RF, control system, Infrastructure etc. AD is at the moment in the middle of a major consolidation program with a budget plan of 23.8 MCHF allocated for the period 2014 – 2020 ADUC 13/1/2015T. Eriksson CERN BE/OP2

3 Target Area ADUC 13/1/2015T. Eriksson CERN BE/OP3

4 4 20thM. Calviani - Dump Magnets dog-leg PSAIF irradiation pit Mobile shielding BHZ6024/25 transformer

5 Target Area consolidation Target/horn control system (movements, interlocks etc.) – Replace old hardware built as prototype and running since initial AD operation: – New radiation hard-cameras in the target area for surveillance. New machine interlocks acquisition system. New software for AD operators supervision and expert interface for equipment operation. Additional safety added: Status of horn supply, zone access, strip line temperature, mobile shielding status etc. Separation of machine and access interlocks. Service vehicle (elephant): complete overhaul of electrics/hydraulics after breakdown in 2012 Tunnel areas: – Water infiltration at entrance repaired with resin injection – New airtight door at target zone entrance – New resin floor throughout tunnel – Improve infiltration situation in TT6 Surface buildings: – B232: Removal of legacy radioactive waste, Re-creation of a buffer zone adapted for large radioactive object from target area, Water tightness – B195: Retention vessel for the AD-target cooling station, Sealing penetration to target area ADUC 13/1/2015T. Eriksson CERN BE/OP5

6 Target Area consolidation Consolidation of beam instrumentation: Additional BCT + BPM. 2015 & 2017 Production of antiproton target designs & spares: Only 1 spare target available. From 2015 Magnetic horn spares and new stripline/junction box. From 2015  Critical for operation – only very radioactive spare horn available. Consolidation of target and horn chariots: Very old equipment, monitoring being lost year by year. From 2015 Review of target area magnets: Upstream quads critical for operation! From 2015 Consolidation of transport methods: Moving heavy and radioactive equipment. 2017 Consolidation of radiation protection detectors: Air monitoring + PMI/IG5. 2018 Ventilation and cooling system replacement – RP issues: Access and ventilation system not integrated, no monitoring of air flushing of zone, manual setting of beam/access conditions. To be completed in LS2. Target area decontamination 2019 Refurbishment of surface buildings and tunnel 2015 - 2019 Consolidation of electrical infrastructure 2018/19 ADUC 13/1/2015T. Eriksson CERN BE/OP6

7 Magnets, ring and transfer lines Main bendings (24): – Renovation and re-shimming: DR.BHN06 dismantled and renovated due to excessive coil movement. Regular coil movement measurements on remaining units will determine which one(s) next. – 1 or 2 units will be renovated this shutdown. BHN23/BHN24 ADUC 13/1/2015T. Eriksson CERN BE/OP7

8 Magnets, ring and transfer lines Ring Quadrupoles: no specific plan, re-shimming done a few years ago H/V correctors near e-cooler replaced during LS1. Ejection line quadrupoles (2) replaced during LS1. Spare inventory almost complete. Target area magnets: Quadrupoles upstream of target (9050 & 9052). Area is very hot,1 spare exists but lack of knowledge about state, manipulation & connections. Alternative designs are being considered including permanent magnets. 2015 – 2017 Remaining Bendings and quads: renovation of spare units Ejection line magnets (except DEM-line) will be replaced by e-static units for ELENA ~2016 ADUC 13/1/2015T. Eriksson CERN BE/OP8

9 Power converters Most urgent items consolidation finished during LS1. General consolidation program for 2015 – 2020 approved; renewal & standardisation Replacement of orbit corrector units with standard Cancun supplies in 2015 2/4 kV pulsed injection line converters to be replaced by new Megadiscap in 2016 – 2018. 4 units are already in operation with good results. Replacement of thyristor converters by commercial units during LS2. ADUC 13/1/2015T. Eriksson CERN BE/OP9

10 Vacuum system General consolidation of complete vacuum system. 2013 – 2018 – Completed: Control system renewal, Cryo system, Sublimation pump filament renewal, 6000-line primary pumps, Turbo-pump groups, Previdage valves, Penning/Pirani gauges. – Ongoing: Bakeout equipment renewal, Ion pump feedthrough heaters, Ion pumps (1 sector/year). – To be started in 2015: Spare vacuum chambers, Standardisation of straight sections, Ion gauges renewal, Fast valve electronics renewal, Spare Cryo compressors, Gas injection system. – >2015: RGA PVSS integration, ELENA integration In total ~ 25% of complete program is done. ADUC 13/1/2015T. Eriksson CERN BE/OP10

11 Stochastic cooling Controls, electronics, delay/attenuator platform installation, individual u-wave amplifier power supplies and p/u&kicker movement motors/electronics all renovated or replaced during LS1. Notch filters: Replacement of large cable-box with optical filter system. Increased stability and simplicity & less space requirements. Planned for 2015 0.8 – 1.6 GHz power amplifiers (48): Obsolete semi-conductors, increased failure rate. Prototyping for new design if old amplifiers become unrepairable or too unreliable. 2015/16. Vacuum tanks: Life expectancy and mechanical integrity of pickup and kicker vacuum tanks & s-cooling equipment inside. Possible consolidation not yet adressed. ADUC 13/1/2015T. Eriksson CERN BE/OP11

12 Electron cooling consolidation ADUC 13/1/2015T. Eriksson CERN BE/OP12 Ongoing/LS1: –HV power supply renewal (TE/EPC) Renewal of electron cooler: –Build a new state-of-the-art cooler –2015 – 2018. Aim for installation in LS2. –Existing cooler: Is >30 years old We have no spare magnets; very long down time if failure, significant cost for new spares Performance issues e- bpm:s not operational Momentum pbar300 MeV/c100 MeV/c Electron energy35 keV2.8 keV Electron current2.5 A100 mA Cooling length1.5 m Drift magnet field590 Gauss Electron beam radius25 mm Cooling time16 s15 s ε x / ε y 3 / 3 (π × mm × mrad) 0.8 / 0.5 (π × mm × mrad) dp/p10 -4 < 7 × 10 -5

13 Beam transfer Kicker tanks 55/56 structural improvement. Kicker pulse generator dump/main switch consolidation. 2014/15 Kicker electronic/controls renewal. (Re-location of Pulse generators to B393) 2014/15. Septa electronics/controls renewal. 2014/15. Magnetic Horn HV power supply. Replace with modern unit. 2014/5. Horn ignitron mercury switch phase-out. 2015 – 2016. Horn test bench. Re-located from B174 to B195. 2016/17. ADUC 13/1/2015T. Eriksson CERN BE/OP13

14 Instrumentation BIPM H and V systems merged into one vacuum tank. Orbit system: solution with individual ADC:s in 2015, similar to ELENA system. Will permit measurements during ramps. 2015 – 2017 BCT (TFA6006 and 5302) renewal: mechanical redesign/standardisation. 2015 BBQ-tune measurement: Using existing pickup, commissioned but not yet in regular operation. 2015 CCC (Cryogenic Current Comparator): Intensity measurements of low-intensity beams. To be used in ELENA as well. 2015 – 2016 Schottky analysis (longitudinal): integrate ageing DSP equipment into new C02 LL beam control system + new system for visual monitoring. 2016 - 2018 BCT/BPM in Target area: Improved efficiency monitoring. 2014&2017 ADUC 13/1/2015T. Eriksson CERN BE/OP14

15 RF C02 HV & tuning power supplies. Interlock system. Required to make space for ELENA. C02 Low-Level: Migration to PSB/ELENA-like DSP based system (including Schottky analysis). 2016 – 2018. C10 Low-Level & High-Level renewal: – C10 final stage (obsolete TH116 valves): New power amplifier/control/interlock systems to be developed: 4MCHF 2016-2018 ADUC 13/1/2015T. Eriksson CERN BE/OP15

16 Controls/software Major LS1 renovation: – Front-end upgrade (ACCOR): ~complete (80-90%) renewal in LS1 – Central Timing: re-design for de-coupling AD from the LHC injector complex – Cycle Generation: adaptation to comply with new timing system – New Beam Request Server – Similar CT, CG and BRS systems will be implemented in ELENA – FESA, Java migration, InCA: majority has been completed (standardization) – Some implications: All AP:s have been adapted (OP + Eq. groups) Major debugging effort during 2014 start-up ! => No major consolidation needs ! ADUC 13/1/2015T. Eriksson CERN BE/OP16

17 Access/Safety New PAD/MAD access doors for AD ring & Target Area Complete renewal of interlock system, cabling, sectors, logic etc. Target Area: new sectorization (to facilitate access in TT6, manipulation through shaft etc.) Separation of access and machine interlock systems Standardization ADUC 15/1/2014T.Eriksson BE/OP17 Target area access point: AD ring access point:

18 Infrastructure Cryo-distribution line for AD experiments, large dewar outside building + distribution lines to experimental zones. 2015/16 B193/B195 cooling/ventilation: – Requested for LS2 major upgrade B193 cranes: – Requested for LS2 ADUC 13/1/2015T. Eriksson CERN BE/OP18

19 Schedule 2015 https://espace.cern.ch/be- dep/BEDepartmentalDocuments/BE/Injector_Sched ule_2015.pdf https://espace.cern.ch/be- dep/BEDepartmentalDocuments/BE/Injector_Sched ule_2015.pdf ADUC 13/1/2015T. Eriksson CERN BE/OP19

20 Next 10 years, preliminary 20 Run 2 Run 3 LIU (Injectors)