ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela ELMB Networks CAN/CANopen Interoperability of the ELMB Usage of the ELMB in ATLAS ELMB Networks Full.

Slides:



Advertisements
Similar presentations
JCOP FW Update ALICE DCS Workshop 6 th and 7 th October, 2005 Fernando Varela Rodriguez, IT-CO Outline Organization Current status Future work.
Advertisements

Sezione di Bari September 16, 2002D. Elia - DCS workshop / ALICE week 1 SPD PS system and Controls Domenico Elia, INFN-Bari.
Peter Chochula CERN-ALICE ALICE DCS Workshop, CERN September 16, 2002 DCS – Frontend Monitoring and Control.
TPC-RO DCS set-up PVSS main(s) Iseg OPC server HV Iseg crates (3)LV Wiener crates (22) CAN bus Interface to FEE -temp.mon -I &V mon. Wiener OPC server.
HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and.
TPC DETECTOR SEGMENTATION OF THE READOUT PLANE LATERAL VIEW OF THE TPC
1 WP 10- High Voltage ’06 March 23 rd HV Trip studies  See previous meetings for the foreseen tests on LBC44  Started late by Clermont people when Clermont.
DCS aspects of TDAQ racks in USA15 and SDX1 Y. Ermoline et al. ATLAS Week, CERN, 15 February 2005.
Uli Schäfer DCS meeting Oct. 8th 1. Radiation tests 2002Jim Cook 2. CAN branch with Kvaser PCI/CAN cardFernando Varela 3. Readout chain ELMB-OPC-PVSSHelfried.
The Detector Control System for the ATLAS SemiConductor Tracker
Uli Schäfer Discussions with H.B. after last meeting… All ATLAS standard racks and crates will be monitored. Helfrieds group will equip them with ELMBs.
Clara Gaspar, May 2010 The LHCb Run Control System An Integrated and Homogeneous Control System.
8/11/2006 FPIX TB meeting L. Perera 1 Pixel Power Supply Response Measurement Lalith Perera - Univ. of Iowa Carlos Florez, Simon Kwan, Charles Newsom,
DCS LEB Workshop ‘98, Rome, Detector Control System, H.J.Burckhart,1 Detector Control System H.J Burckhart, CERN u Motivation and Scope u Detector and.
1 CALO DCS power supply status CALO meeting Anatoli Konoplyannikov [ITEP / LAPP] Outline  Introduction  Power supply description with hardware.
INTRODUCTION Chapter 1.
The Detector Safety System for LHC Experiments Stefan Lüders ― CERN EP/SFT & IT/CO CHEP03 ― UC San Diego ― March 27 th, 2003.
SCADA and Telemetry Presented By:.
S.Sergeev, JINR, Dubna. This is just an example of what could be done Could be extended to needs of any NA62 sub- detector requiring a lot of analog measurements.
5 March DCS Final Design Review: RPC detector The DCS system of the Atlas RPC detector V.Bocci, G.Chiodi, E. Petrolo, R.Vari, S.Veneziano INFN Roma.
DCS TCSG November 10th 1999, H.J.Burckhart1 Status of the general purpose I/O system LMB u DCS Architecture u LMB u Local Monitor Box (LMB) u Concept u.
Towards a Detector Control System for the ATLAS Pixeldetector Susanne Kersten, University of Wuppertal Pixel2002, Carmel September 2002 Overview of the.
Readout & Controls Update DAQ: Baseline Architecture DCS: Architecture (first round) August 23, 2001 Klaus Honscheid, OSU.
MDT PS DCS for ATLAS Eleni Mountricha
ATLAS ATLAS DCS H.J.Burckhart, Muon Electronics Meeting, December 11th Status of Embedded Local Monitor Board (ELMB) Overview Radiation tolerance.
ITER – Interlocks Luis Fernandez December 2014 Central Interlock System CIS v0.
9th September 2001R. BARILLERE - IT-CO1 Industrial and Custom Front-End solutions for Process Controls.
JCOP Workshop September 8th 1999 H.J.Burckhart 1 ATLAS DCS Organization of Detector and Controls Architecture Connection to DAQ Front-end System Practical.
Clara Gaspar, October 2011 The LHCb Experiment Control System: On the path to full automation.
S.Sergeev (JINR). Tracker consists of  4 chambers of 4 views each In total ~7200 drift tubes (~450 per view) To be controlled/monitored  HV system.
15/12/10FV 1 Common DCS hardware. General ideas Centralized system: o Common computers. Detector dedicated computers (with detector participation) only.
XXVI Workshop on Recent Developments in High Energy Physics and Cosmology Theodoros Argyropoulos NTUA DCS group Ancient Olympia 2008 ATLAS Cathode Strip.
1 Low Voltage Power Supply Specification DCS Workshop 8 Sept 03 L.Jirden.
DCS Plans and Pending Activities for 2013/14 Shutdown Muons in general Replacement/upgrade of DCS computers OS migration to Win-7, Win-2008 or SL6 PVSS.
André Augustinus 17 June 2002 Technology Overview What is out there to fulfil our requirements? (with thanks to Tarek)
11th March 2008AIDA FEE Report1 AIDA Front end electronics Report February 2008.
André Augustinus 6 October 2005 Cabling, Interlocks, Racks Some remarks.
1 Outline Firmware upgrade of the HV_LED_DAC boards. HV Status Bits board. Status of the board integration into the LHCb TFC system. CALO HV system and.
The Detector Control Power System of the Monitored Drift Tubes of the ATLAS Experiment Theodoros Alexopoulos NTU Athens TWEPP08 September 17, 2008 Naxos,
Clara Gaspar, March 2005 LHCb Online & the Conditions DB.
ATLAS ATLAS DCS B.Hallgren, CERN EP/ ATI PRR CERN 4 March the Embedded Local Monitor Board ELMB Design description of the Embedded Local Monitor.
Alice DCS workshop S.Popescu 1 1. News from TPC DCS cooling prototype Project overview: Aim of the prototype: investigating and developing standard.
André Augustinus 16 June 2003 DCS Workshop General Purpose Monitor.
Alice DCS workshop S.Popescu ISEG Crate controller + HV modules ISEG HV modules 12 Can bus PVSS OPC Client 1 Generic OPC Client Iseg OPC.
DCS Workshop, CERN MARCH ACORDE (Alice Cosmic ray detector) 60 scintillator modules (120 HV channels) Each module will have two scintillator counters.
NA62 straw tracker DCS Straw tracker overview Bulk power supply Power supply distribution and monitoring LV + monitoring HV Temperature monitoring Gas.
1 Calorimeters LED control LHCb CALO meeting Anatoli Konoplyannikov /ITEP/ Status of the calorimeters LV power supply and ECS control Status of.
Assumptions: Cockcroft-Walton photomultiplier bases are the same for all ECAL sections Digital to analog converters are installed on the distribution boards.
The Software for the CERN Detector Safety System G. Morpurgo, R. B. Flockhart and S. Lüders, CERN IT/CO.
60kW Thermosiphon control system
Status of the DCS Richard Brenner (Uppsala University) " Structure of the DCS " Cabling of DCS sensors " Interlock " Status and near future plans.
A.Henriques (JCOV meeting 31/5/2001) ATLAS Calorimeter cooling project Goal: u Definition of a common frame work for the cooling of the ATLAS calorimeter.
Distributed Low Voltage Power Supply System for Front End Electronics of the TRT Detector in ATLAS Experiment E.Banaś a, P.Farthouat b, Z.Hajduk a, B.Kisielewski.
ATLAS DCS ELMB PRR, March 4th 2002, H.J.Burckhart1 Embedded Local Monitor Board ELMB  Context  Aim  Requirements  Add-ons  Our aims of PRR.
S.Sergeev (JINR). Tracker consists of  4 stations of 4 views (planes) each In total ~7200 drift tubes (~450 per view) To be controlled/monitored 
22/03/11FV 1 NA62 DCS CAN bus lines. Short reminder General properties of CAN bus o Up to 64 nodes on one bus o Different devices need different buses.
DCS workshop,march 10th P.Saturnini, F. Jouve Slow control trigger of the muon arm Muon trigger of the muon arm Low voltage VME Crate External parameters.
D. EliaALICE week / DCS workshop - Sept 20, SPD Power Supply System DCS status Domenico Elia INFN Bari.
ATLAS DCS Workshop on PLCs and Fieldbusses, November 26th 1999, H.J.Burckhart1 CAN and LMB in ATLAS u Controls in ATLAS u CAN u Local Monitor Box u Concept.
1 COSTING DCS WS L.Jirdén. 2 LAN WAN Storage Configuration DB, Archives FSM servers Terminal servers, ACR consoles, etc Experimental equipment.
Monitoring hardware for SVD (VXD) L.Lanceri, L.Vitale /INFN Trieste VXD Workshop, 01/10/2014 Slow Controls discussion session 1 1.Radiation & beam abort.
ProtoDUNE - SP SLOW CONTROLS MEETING 11/11/2016 CERN – EP/DT
Programmable Logic Controllers: I/O
ATLAS MDT HV – LV Detector Control System (DCS)
Controlling a large CPU farm using industrial tools
Radiation- and Magnet field- Tolerant Power Supply System
The LHCb Run Control System
Detailed information FOR INTERNAL USE ONLY! CUBE20.
Presentation transcript:

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela ELMB Networks CAN/CANopen Interoperability of the ELMB Usage of the ELMB in ATLAS ELMB Networks Full Branch Test Conclusions Future work Outline

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela 120  Beckhoff Wago Compliance of the ELMB

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela Aims of the Test: TileCal Cooling and LV: 8 ELMBs Pixel Cooling: 7 ELMBs COMPASS 10 ELMBS Currently Pixel Cooling : 12 ELMBs MDT 10 ELMBs COMPASS 16 ELMBs Next Year 5000 ELMBs in ATLAS – 1200 MDT (test case, should cover all subdetectors) – 1000 RPC – 800 TGC ATLAS Powering Performance: tuning of parameters identifying bottlenecks 50 mm 66 mm Reliability Robustness Definition of recovery procedures Usage of the ELMB >> Give guidelines and recommendations to set up ELMB networks in ATLAS <<

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela The maximum number of ELMBs per bus is 64 for addressing reasons (6 bits), i.e Analog Inputs However, the number of ELMBs per branch must be a compromise: – Cost; a higher number of ELMB modules per bus => a lower number of buses and PCs – Affordable number of channels to be lost in case of a branch failure. – Performance and reliability of the readout system. – Powering of the CAN network (PS placed in USA15). 120  Branch_1 Branch_2 ELMB Networks

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela SCX1 USA15 Front-End System Back-End System Local Area Network Partition 3 Supervisory only Partition m UX15 Partition 2 Common Infrastructure Local Control Stations (LCS) Partition 1 Expert Workstations ServerOperation Subdetector 1Subdetector 2a Subdetector n Detector Sub-system Sensors Actuators Fieldbus 200m  ELMB Electronic Rack ELMB Rack PC Power Supply Cooling Interlock Box Test Rack PC ELMB Alarms CFS HV Barrel Architecture of DCS

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela ELMB Full Branch Test

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela ELMB ELMB Full Branch Test

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela ELMB ELMB Full Branch Test

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela Set Up Only one PS used. Digital and CAN parts of the ELMB and NI-CAN card powered via the bus. Analogue part powered from the digital (Power monitored by a scope). Normally powered from the FE equipment Bus and Interface card power lines were de-coupled (Allows for independent reset of both elements). 120  0x3F0x30 CANbus 200 m 16 V PS LCS 120  D9 Connectors Powering

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela 16 x 8 = 128 digital input lines (Sync + Async), 16 x 2 x 8 = 256 digital output lines (Async) Input and output lines interconnected 16 x 64 = 1024 Analogue channels (Sync) ELMBs reprogrammed to bypass filtering in OPC server and ensure maximum data volume transfer to PVSS-II (Worst possible case) ELMB I/O Functionality t SYNC_1 ELMB_30ELMB_31ELMB_3F  ELMB_30_0ELMB_31_0   ELMB_3F_0 SYNC_2 ELMB_30 SYNC Interval... ELMB_30_1 ELMB_31_1 ...  Digital Signals (Higher Priority) Analogue Channels (Lower Priority) ELMB_3F_1ELMB_3F_63 Bus Cycle... If adc = 32.5 Hz and Bus Speed = 125 kbit/s  ~ 0.8 ms => Time difference between messages on the bus;  ~ 30.8 ms => Time needed for ADC conversion

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela CAN Analyzer Diagnostic Tool SYNC Digital Signals Analogue Channels Bus load No. of CAN frames

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela Bus Load

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela Performance

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela Data get lost at higher data rates when SYNC Interval -> bus cycle Bottlenecks: NI CAN interface card (buffer overflow) => Need for a new interface (cost and characteristics). PVSS archiving (CPU consumption) => Better distribution of the tasks performed by SCADA. Performance (II)

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela Comparison at different Bus Speeds Results shown at 125 kbits/s were reproduced, i.e. 100 % transfer rate for a bus having 16 ELMBs and SYNC Interval equal to 4 s.

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela 200 m long ELMB Branch with up to 16 nodes successfully operated. I/O channels of the order of magnitude of some subdetectors in ATLAS: 1024 AI, 256 DO, 128 DI Preliminary studies of the powering has been carried out. The test tried to reproduce the “worst possible case” => All ELMBs transmitting at the same time. The system has shown excellent performance:Transfer rate of 100% for messages of different priorities on the bus and of different transmission types. Maximum readout rate 4s at 32.5 Hz. Results are reproducible at 250 kbits/s => Less bus load (but also smaller bus length). Several issues were identified at higher adc when SYNC  Bus Cycle Overflows in the read buffer of the NI-CAN interface Strange behavior of PVSS-II manager as a function of the OPC update rate. High CPU consumption by the PVSS archiving manager However, the CANalyzer showed the correct operation of all ELMBs on the bus. Conclusions

ATLAS DCS ELMB PRR, CERN, March 2002Fernando Varela Optimize powering of the bus => minimize voltage drop in the CANbus cable. Window-checking in the ELMB. Increase number of ELMBs up to 32 or 64. Several buses per PC. Test of network supervision and management -> Definition of error recovery procedures Long-term operability of the system in TCC2. Automatic power cycle of the bus needed due to SEEs (see below). Future Work