LHC Machine Checkout & Dry Runs Strategy Acknowledgements: R.Alemany, R.Giachino M. Albert LHC Beam Operation Workshop June 2014.

Slides:



Advertisements
Similar presentations
Stéphane Gabourin TE/MPE-EP 21 st March 2014 BIS & SMP changes for Run 2 SPS – Extractions – Injections – LHC.
Advertisements

Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Post Mortem Workshop - discussion1 17/1/2007 HWC Requirements GMPMA  Concentrate on pre-beam requirements Post-quench analysis ([semi-] automatic) Integrity.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Injection test? Mike Lamont For initial discussion.
Failure mode impact studies and LV system commissioning tests
Tomasz Ladzinski GS/ASE. LASS Annual Maintenance & Tests General Principles Each winter shutdown preventive maintenance of EIS takes place. It is followed.
How to improve operational efficiency ? [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] Beam Commissioning Workshop, Evian Jan 2010.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Sat 18/6 – Sun 19/6 07:48 Beam dump due to spurious interlock from BIS 08:30 access BIC repair. RF intervention in parallel. 13:00 Intervention on BIC.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
Proposal for Decisions 2007 Work Baseline M.Jonker for the Cocost* * Collimation Controls Steering Team.
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
B. Todd et al. 25 th August 2009 Observations Since v1.
SPS RESTARTING AFTER LS1 05/03/2015 Stéphane Cettour Cavé.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
R.Giachino / M.Albert Be/op 12 th March 2012 LHC Machine check out 1v1.
Status Report – Injection Working Group Working group to find strategy for more efficient start-up of injectors and associated facilities after long stops.
1 Beam Plans for Accelerator Systems: The Machine Protection System Jan Uythoven On behalf of the MPWG and the MPS Commissioning WG Special thanks to R.Schmidt,
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
FGC Upgrades in the SPS V. Kain, S. Cettour Cave, S. Page, J.C. Bau, OP/SPS April
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
1 Operational availability Optimizing LHC L. Ponce With the (un)intentiona lcontribution of all OP crew.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
RBAC Content: LHC Operational Mode Piquet Roles RBAC Strict LHC Operational mode and CMW Acknowledgements: Pierre C., Wojtek S., Stephen P., Lars J., Verena.
Schedule IT General Schedule 9 th, September 09 Today.
Dry runs and cold checkout Markus Albert, Reyes Alemany, Rossano Giachino, Delphine Jacquet, Verena Kain, Belen Salvachua Ferrando, Matteo Solfaroli Camillocci.
Running scenario 2009/10 Run through components – and then synthesis.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
16-17 January 2007 Post-Mortem Workshop Logging data in relation with Post-Mortem and archiving Ronny Billen AB-CO.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
1 Commissioning and Operation of the machine protection system L. Ponce Acknowledgements: M. Zerlauth, J. Wenninger, D. Wollmann, V. Chetvertkova, G. Valentino,
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
1 Machine Checkout and Setup Periods Jan Uythoven Thanks to: O.Aberle, R.Bailey, F.Bordry, O.Brunner, L.Bottura, E.Carlier, P.Charrue, E.Ciapala, S.Claudet,
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
LBOCM. ZerlauthMarch 06 th 2012 Acknowledgements : B.Todd, C.Martin, I.Romera, E.Carlier, J.Wenninger, C.Zamantzas, S.Redaelli et al. 1v0 MPS Commissioning.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
E. Hatziangeli – LHC Beam Commissioning meeting - 3 rd March 2009.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
LHC Beam Commissioning Meeting V. Kain & R. Alemany
Data providers Volume & Type of Analysis Kickers
DRY RUNS 2015 Status and program of the Dry Runs in 2015
LHC schedule.
J. Uythoven for the MPE-MI & MS Teams
Summary of week 7 Hardware Commissioning:
Monday 11/07: Recovery Plenty of accesses.
MPSC Procedures An update
Machine Protection Xu Hongliang.
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Dry Run 0 Week 13: BI test of...everything circulating beam: all fixed displays and BI applications OP directories for 2009, concentrators running Need.
Week 35 – Technical Stop and Restart
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Machine Protection System Commissioning plans
1v1.
Can operation put the MPS in a unsafe state?
New page for summary of test status
Another Immortal Fill….
Review of hardware commissioning
Presentation transcript:

LHC Machine Checkout & Dry Runs Strategy Acknowledgements: R.Alemany, R.Giachino M. Albert LHC Beam Operation Workshop June 2014

2 Outline Introduction Machine Checkout Dry Runs Conclusions

3 LS1 modifications Vacuum UPS 18 kV & 3.3 kV circuit breakers Cryogenics P7 enclosure Pumping stationACS transport + personnel changes, including OP/LHC !

4 The coordination team Dry Runs Sector Test Preparation Machine Checkout Close collaboration to achieve common objectives + Delphine, Matteo

5 Machine Checkout Succeeds individual system test (IST) period Driven from the CCC (remote equipment control) Vital for a smooth transition from shutdown to beam commissioning 2014/2015 exercise: similar to start-up 2008 & restart 2009 → early start & long preparation Definition: Period between end of shutdown and start of beam commissioning during which all systems are tested by OP and equipment experts, in order to prepare the LHC for beam operation.

6 Machine checkout - timeline Information collection, planning Meetings with equipment experts (started in Q1/2014) Optimize test scheduling Preparation of MC planning Basis for following phases Start of Dry Runs March – July Test equipment needed for sector test(s) Test & validation of equipment according to MC planning “sectorised” - machine checkout More Dry Runs 1 st readiness deadline for most system August - December Testing of complete machine Final tests of complete machine Run full LHC cycle Daily coordination & progress report meetings with close follow up January

7 Machine checkout – current status Information collection, planning Meetings with equipment group representatives to discuss: Readiness Test schedules Already covered: Access system, BIS, Collimators, Cryogenics, General Services (EL, CV), LBDS, MKI, PC, PIC, RF, Vacuum, WIC Minutes: Result: Machine Checkout test planning Ready by end of July

8 Machine checkout – sector test Test equipment needed for sector test(s) 1 st milestone with beam before full LHC commissioning Pre-conditions: Full readiness of access system (4 th /5 th Oct) Global DSO test: 11 th /12 th Oct Objective: Test substantial subset of LHC equipment Check-out all other systems as they become available Dry runs continue in parallel to HWC Reduced BIS configuration Powering group of circuits (PGC) of available sectors Software testing & debugging

9 Machine checkout – the final Testing of complete machine Pre-condition: Machine closed All SC magnet circuits ready PIC & QPS operational Beam vacuum system operational BIS operational Objectives: Heat runs (warm magnets) Test of full LHC cycle (injection, pre-cycle, ramp up/down) Close beam permit loop with all BIS users connected Final LBDS checks, energy tracking tests MKI tests Interlock tests without beam Final machine protection tests (all BIS inputs) Daily 8:30 - meetings (access requests, test plan)

10 A typical MC test Pre-conditions: IST on vacuum system done, valves in remote control Straight section and adjacent sectors < bar, T cold mass < 5K BIC and supervision available Logging of vacuum valve status Valve alarms operational NO powering tests in affected area Test sequence: Simulation of vacuum problem to check correct valve behavior Systematic individual valve closure/opening With LHC ready to take beam: full verification of interlock logic vacuum valve interlock verification

11 Dry Runs Complementary preparation for sector tests and beam commissioning proven to be very efficient and useful tools in successfully qualifying the LHC for beam operation (start-up 2008, re-start 2009) 3 phases: preparation – execution – follow up Tight collaboration with equipment experts Involve complete controls chain (software debugging) Definition: A dry run (or a practice run) is a testing process where the effects of a possible failure are intentionally mitigated. (wikipedia.org)

12 Dry Runs Beam Dump: local BIS loop + application, arming sequence, BETS simulator Timing: stress test Beam Instrumentation + AC Dipole+ Tune/Aperture kicker + feedbacks: sequencer tasks, applications, logging, concentrators Injection: timing, sequencer, MKI, applications, IQC (BI), synchronization/re- phasing Hardware & Software Interlock System + Safe Machine Parameters (SMP): sequences, flag generation SPS, forcing,… Collimators + TCDQ + roman pots: applications, settings, MPS tests, sequencer tasks, logging, roman pots (simulated energy and b*) Damper + RF + Damper pickups: sequencer tasks, settings, MCS checks Experiments: handshakes, beam modes, injection inhibits, interlocks,… Power converters: test “prepare circuits” sequence tasks,… Postmortem (PM), Beam Dump External Post-Operational Checks (XPOC) Details & schedule:

13 2 Dry Duns so far … ProgramComments/Issues Dry run 1 (7-8 May) 1.Timing 2.TI 2 upstream BI 3.All BPM concentrators 4.Experiments beam modes and handshakes 5.Experiments frequency ramp 6.LHC RF re-synchronization (with experiment clocks) Test - hypercycle (2012 optics) Old timing system (upgrade in autumn, but no change of interface nor functionality) Mastership couldn’t be taken (prevented some tests) TI2 upstream BI not received at IQC (dynamic destination not available) Some issues with RF re-synchronisation only LHC tasks, SPS part wasn’t ready RF frequency ramp without ALICE no TI2 SETUP handshake with ALICE no EXP data on DIP browser Dry run 2 (21-22 May) 1.BIS-beam dump arming for B2 (local permit loop + two B2 P6) 2.Revised arming sequence 3.Include arming of CIBDS (new BIS board) Only B2 tested (B1 at next occasion) Some sequence modifications Communication with XPOC and “Inject & Dump” not yet tested Trigger from CIBDS not arriving on IPOC No serious problems – very successful

14 Next Dry Runs DateProgram W24 - W29LBDS reliability run B1 & B2, from CCC for several weeks W25 / th JunLHC re-synchronisation (Linux FECs), LHC mastership (dynamic destination in test mode), TI2 – BI with IQC (possibly also TI8), SDDS, AC dipole, tune & aperture kicker, MCS checks, SMP for beta* and energy W29 / th JulPM and XPOC Parallel to HWCSequence to reset circuits, arm switches, LSA (trim, incorporation,…) W33 / th AugCollimators (+ similar devices), RF beam control, ADT settings, injection cleaning, abort gap cleaning,… W38 / th Sep“old” implementation of feedbacks, BLM continuous, global permit loop + LBDS arming + XPOC, experiment interlocks & injection permits, BI sequencer tasks, ALICE frequency ramp, BQM, LHC BTVs, BRANs Start checking EVERY task in nominal sequence W42, W44 OctVacuum, BIS checks, BCTs, MKI, BLM triggered buffers, new timing system, sector test preparation (injection requests, inject & dump, set machine to injection…) Until end of 2014profile measurement systems (BSRT, WS), RF cavity control, ADT, new feedbacks

15 Conclusions LS1 = huge quantity of changes (LHC 2.0) Preparation for beam commissioning similar to start-up 2008/2009 Sector tests as 1 st major beam deadline to checkout most equipment General MC + DRs constitute a proven recipe to prepare the machine for beam commissioning