Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division www.europeanspallationsource.se April 2, 2014.

Slides:



Advertisements
Similar presentations
PROJECT RISK MANAGEMENT
Advertisements

State of Indiana Business One Stop (BOS) Program Roadmap Updated June 6, 2013 RFI ATTACHMENT D.
Ensure Vendor/Engineer of Choice Product Quality
Project Management Process. Project Complexity means that: a team of people are needed to supply expertise the work needs to be broken into manageable.
Avra Software CMPUT Process Quality and Software Assessment Case Study - slide#1©P. Sorenson and Amr Kamel Assessment Plan for Assessment Plan for.
Dominion Radio Astrophysical Observatory DVA-1 Reflector Development Timeline Gary Hovey NRC-HIA Dominion Radio Astrophysical Observaotry.
Systems Engineering Management
Planning. SDLC Planning Analysis Design Implementation.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
Don Cole Risk Assessment and Mitigation Project Management for ARA Engineers and Scientists.
Project Life Cycle Introduction and Overview © Ed Green Penn State University All Rights Reserved.
The ESS vacuum team has overall responsibility for all technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and.
What is Business Analysis Planning & Monitoring?
What If I Must Go Beyond a Preliminary Assessment? (the example of a USAID EA under Reg. 216) [DATE][SPEAKERS NAMES]
Server Virtualization: Navy Network Operations Centers
Global Design Effort 1 Conventional Facilities and Siting Overview A. Enomoto, J-L. Baldy, V. Kuchler GDE.
Introduction and Charge to the Review of ESS Target building and Instrument Hall design requirements Roland Garoby November 2014, Lund
NIST Special Publication Revision 1
© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
Prof. Roy Levow Session 9.  Defining the APF  An Overview of the APF  The APF Core Values.
In-Kind Contribution Management Update Allen Weeks March 20, Lund.
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 8 Project Resource Management Resource Planning.
Certification and Accreditation CS Phase-1: Definition Atif Sultanuddin Raja Chawat Raja Chawat.
1 SPSRB Decision Brief on Declaring a Product Operational Instructions / Guidance This template will be used by NESDIS personnel to recommend to the SPSRB.
Target Project Progress and Plans Eric Pitcher TAC-10 November 5, 2014.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
J. G. Weisend II Deputy Head of Accelerator Projects April 2, 2014 Actions at ACCSYS Resulting from the Recommendations of the Annual Review.
Project Life Cycle.
© Mahindra Satyam 2009 Configuration Management QMS Training.
Develop Project Charter
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
Project Management Methodology
ITER- TBM Planning and Costing Activity DCLL TBM Mechanical Design ( ) & TBM-Port Interface ( ) Presented by Mo Dagher December
1 EMS Fundamentals An Introduction to the EMS Process Roadmap AASHTO EMS Workshop.
Business Analysis. Business Analysis Concepts Enterprise Analysis ► Identify business opportunities ► Understand the business strategy ► Identify Business.
WP 12.3 Moderator & Reflector Systems D. Lyngh, M. Kickulies, J. Ringnér, J. Jurns, Y. Bessler (FZJ), M. Klaus (TUD), H. Quack (TUD) TAC12 Presenters:
Utility Financial Management AWWA Intermountain Section Leadership Forum Session Two November 10, 2015.
Configuration Management Romuald Duperrier Head of Systems Engineering Division April 22, 2015.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
Project Management Project Integration Management Minder Chen, Ph.D. CSU Channel Islands
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
Neutron Chopper Technologies Work Package
State of Georgia Release Management Training
ANALYSIS PHASE OF BUSINESS SYSTEM DEVELOPMENT METHODOLOGY.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
Copyright © 2015 John Wiley & Sons, Inc. All rights reserved. Information Technology for Management Chapter 13: Project Management and SDLC Prepared by.
Multistate Research Program Roles & Responsibilities Eric Young SAAESD Meeting Corpus Christi, TX April 3-6, 2005.
23-Nov-1999STScI Projects Monthly Status Review1 of 8 SpaceTelescopeScienceInstitute COS Status Report for period December, 1998 to November, 1999 Tony.
Project Management Processes for a Project Chapter 3 PMBOK® Fourth Edition.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Introducing the INS Master Schedule Wayne Baggett.
Introduction to Project Management Darren Trofimczuk.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
IV&V Facility 7/28/20041 IV&V in NASA Pre-Solicitation Conference/ Industry Day NASA IV&V FACILITY July 28, 2004.
Information Technology Project Management, Seventh Edition.
Tailoring the ESS Reliability and Availability needs to satisfy the users Enric Bargalló WAO October 27, 2014.
Instrument Construction Phase 1 and beyond Rob Connatser Chief Instrument Project Engineer September, 2014.
Responses to Recommendations from tTAC-10 John Haines Head of Target Division April 1, 2015.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
Making Difficult Decisions in a Transparent Way –
Systems Analysis and Design in a Changing World, 4th Edition
Software Configuration Management
TechStambha PMP Certification Training
Bunker Internal Review Welcome & Charge
DOE Review of the LCLS Project October 2006
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014

TAC-8 Recommendation (1 of 3) Recommendation: Regarding System Engineering Approach: Minimize formal constraints to the technical contributors, but be strict of what is mandatory (e.g. quantified progress report). Create a high level, readily accessible parameter list immediately. Response: SE requirements are being tailored to meet the needs of the Target Project. Near term system engineering expectations and deliverables (Preliminary Design Review and Critical Design Review) identified and communicated to Work Package Leaders. Tailoring of longer term deliverables remains to be done. Established high level parameter list for Target Station that has been posted to the TAC-9 site (ESS ) 2

Excerpt from Target Station Parameters List 3

TAC-8 Recommendation (2 of 3) Observations The target safety system is not clearly defined. Recommendations A credible monitoring system has to be specified, capable to guarantee that “the target is ready for beam”. Early definition of this system is important for the design and control of the target instrumentation. Response: Process to derive the set of safety credited controls is in place and being worked (See Linda Coney’s presentation for details) (ca. 2016) In general, Target MPS items will be identified in P&IDs that will be part of the Preliminary Design Review deliverables (ca. 2014) 4

TAC-8 Recommendation (3 of 3) Recommendation: Prioritize the list of EDD‘s considering the budget constraints; identify what is mandatory or needed, and when. Response: – EDD Plan developed and iterated several times to settle on a set of activities that address critical issues in a timely fashion (ESS ) – Activities are included in Target Project plan with a total budget of approximately 5 M€ 5

List of approved EDDs included in Performance Measurement Baseline Target System Gas Flow Erosion (WBS ) Target Rotary Seal (WBS ) Moderator Neutronics Benchmark (WBS ) Test of Remote Handling Procedures (WBS ) Tungsten Fatigue Studies (WBS ) Helium Purification (WBS ) Ortho Hydrogen Fraction in Moderator (WBS ) 6

Recommendations from Nov 2013 Annual Review Target received seven recommendations from the 1 st ESS Annual Review held in Nov 2013 – Responses and final closure of items is being tracked – The May 2014 Update Review will focus on responses to the recommendations – A document addressing the current status of these responses was posted to the TAC-9 site and the next seven slides provide a high level summary

Recommendation and status of response Recommendation: Only two years are being allowed for the moderator and reflector plug build; this may not be enough. Interactions with vendors may be helpful. Response: Activity: Attempt to understand why the SNS plug design and fabrication approach takes so much longer than for similar facilities. Also, seek input from vendors. Document findings. Deliverable: Report and possible adjustment to plan. Status: On track for June 2014 completion 8

Recommendation and status of response Recommendation: The price of off-spec steel is important; a supplier should be located and a price negotiated. This is currently in the project schedule for Response: Activity: Better understand the availability, quantities, and cost of off-spec steel available within partner countries. Explore possibility of an in-kind partner supplying steel. Deliverable: Report and possible adjustment of cost estimate. Status: On track for May 2014 completion 9

Recommendation and status of response Recommendation: The target/instrument, target/accelerator, and target/conventional facilities interfaces are important and appear to be improving. These need to continue to improve, and a timely decision on the new moderator design is a first test. Response: Activity: Work with NSS to finalize moderator concept and establish monthly meetings between interfacing Project Leaders to raise visibility. Deliverable: Submit moderator design change request package for CCB approval. Monthly Project Leader level interface management meetings established. Status: Monthly meetings being held. On track for April 30, 2014 decision on moderator concept. 10

Recommendation and status of response Recommendation: Planning of the remote-handling schemes for target & moderator-reflector replacement needs to be completed. Response: Activity: Moderator concept will be decided in the spring of Ease of remote handling is one aspect being considered in this selection process. Following this decision, the remote handling scheme will be established during the preliminary design process for the Moderator-Reflector Plug and Target Wheel. Deliverable: Report documenting maintenance schemes for Moderator and Reflector Plug and Target Wheel. Status: On track for completing in Nov

Recommendation and status of response Recommendation: Spare components are currently delayed to operations. Make sure to manage this. Response: Activity: Compile a list of critical spares and update periodically to be prepared to factor into operations planning. Establish priority for purchasing based on impact on operations, lead time needed to obtain replacement equipment, and probability of failure. Deliverable: Critical spares list including expected lifetime, probability of premature failure, replacement time, and cost documented and transmitted to Ops, ES&H, and QA Director. Status: Complete (ESS , document posted to TAC-9 site) 12

Recommendation and status of response Recommendation: Consider consolidating neutronics and shielding efforts into one group to avoid duplication of efforts. Response: Activity: Develop proposal for conducting neutronics and shielding analyses across all projects and establish a well- documented, rigorous process. Deliverable: Proposal for EPG on organizational aspects and release of document describing rigorous shielding analysis process Status: EPG approved appointment of Günter Muhrer as ESS Shielding Coordinator and shielding analysis process description nearing completion (See Günter Muhrer’s presentation) 13

Recommendation and status of response Recommendation: The water-cooled target backup study of beam power versus need for emergency coolant is important. This study should be completed as soon as possible. Response: Activity: Complete study by May 2014 Deliverable: Report documenting power limit Status: On track for meeting May 2014 plan (see slide in John Haines presentation on Target Status) 14