M. Gilchriese ATLAS Pixel Upgrade Thoughts on US Role.

Slides:



Advertisements
Similar presentations
M. Gilchriese US ATLAS Pixel Meeting July 18-19, 2002 UC Santa Cruz.
Advertisements

Summary of the SVD session 19 March 2009 T. Tsuboyama (KEK)
02/10/2004 Minimum Bias Trigger Scintillator Counters (MBTS) for early ATLAS running M.Nessi ATLAS week, Freiburg.
Sept. 18, 2008SLUO 2008 Annual Meeting ATLAS Detector Upgrade Opportunities M. G. D. Gilchriese Lawrence Berkeley National Laboratory.
Outer Stave Prototype Update E. Anderssen, M. Cepeda, M. Garcia-Sciveres, M. Gilchriese, N. Hartman, J. Silber LBNL W. Miller, W. Shih Allcomp, Inc ATLAS.
ATLAS detector upgrades ATLAS off to a good start – the detector is performing very well. This talk is about the changes needed in ATLAS during the next.
Pixel Upgrade Local Supports Based on Thermally Conducting Carbon Foam E. Anderssen, M. Cepeda, S. Dardin, M. Garcia-Sciveres, M. Gilchriese, N. Hartman,
Performance of the DZero Layer 0 Detector Marvin Johnson For the DZero Silicon Group.
D. Lissauer, BNL. 1 ATLAS ID Upgrade Scope R&D Plans for ATLAS Tracker First thoughts on Schedule and Cost.
U.S. ATLAS Executive Meeting Upgrade R&D August 3, 2005Toronto, Canada A. Seiden UC Santa Cruz.
M. Gilchriese Upgrade Stave Assembly and Robotics August 3, 2007 LBNL.
VELO Upgrade Critical Issues Two step upgrade with installation around 2013/2017 Implies a detector which can sustain 5/20/120 fb -1 Very tight schedule.
SLHC Pixel Layout Studies S. Dardin, M. Garcia-Sciveres, M. Gilchriese, N. Hartman LBNL November 4, 2008.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
M. Gilchriese ATLAS Upgrade Mechanics/Cooling and System Design by LBL January 2008.
M.Oriunno, SLAC Stave cable and module options. M.Oriunno, SLAC Background - module The IBL electrical unit for data output is a single chip The use of.
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
M. Gilchriese SLHC Pixel Local Supports Based on Thermally Conducting Carbon Foam E. Anderssen, M. Cepeda, S. Dardin, M. Garcia-Sciveres, M. Gilchriese,
M. Gilchriese - November 12, 1998 Status Report on Outer Support Frame W. Miller Hytec, Inc E. Anderssen, D. Bintinger, M. Gilchriese LBNL.
SLHC SG: ATLAS Pixel G. Darbo - INFN / Genova SLHC SG, July 2004 ATLAS Pixel at SLHC G. Darbo - INFN / Genova Talk overview: A table with different High.
1 US Pixel Mechanics Role Global support structureIntermediate support structureLocal support structure Stave SectorDisk Barrel x (9-11) x5 x (22,40,56)
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Phase 2 Tracker R&D Background: Initial work was in the context of the long barrel on local tracklet- based designs. designs of support structures and.
Muon trigger upgrades, missing since not aimed towards DOE funding PHENIX upgrades: view presented to DOE R&D $3.5M Construction $16.6M Au-Au p-p 200 Si-Si.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
2 Silicon pixel part Done and to be written Written! Under way To be done Introduction 1.Hybrid Pixel Assembly Concept 2.Silicon sensor 1.First thinned.
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
Thin Silicon R&D for LC applications D. Bortoletto Purdue University Status report Hybrid Pixel Detectors for LC.
Communications G. Darbo – INFN / Genova IBL MB#15, 5 October 2009 o Bump Bonding Selex / INFN Roma, October, 30 th 2009 G. Darbo - INFN / Genova.
PHASE-1B ACTIVITIES L. Demaria – INFN Torino. Introduction  The inner layer of the Phase 1 Pixel detector is exposed to very high level of irradiation.
Jorgen Christiansen, CERN PH-ESE 1.  Spokes persons and Institute chair elected ◦ SP’s: ATLAS: Maurice Garcia-Sciveres, LBNL CMS: Jorgen Christiansen,
PHENIX Silicon Vertex Tracker. Mechanical Requirements Stability requirement, short and long25 µm Low radiation length
AMS HVCMOS status Raimon Casanova Mohr 14/05/2015.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
SLHC Local Support Requirements Summary M. Gilchriese November 4, 2008.
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
Tilt angles reloaded, and status of some other things.
M. Gilchriese - November 14, Module Decision - To Do List By pixel meetings associated with February 22-26, 1999 ATLAS week Beyond making and testing.
Peter Sharp CERN CMS Tracker Summary of the Tracking Trigger Working Group Peter Sharp 21 November 2008.
CMS pixel telescope at MTEST 1 A. Kumar, S. Kwan, A. Prosser, R. Rivera, M. Turqueti, L. Uplegger.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
Pixel power R&D in Spain F. Arteche Phase II days Phase 2 pixel electronics meeting CERN - May 2015.
Local Supports to IDR Discussion ATLAS Upgrade Week November 2014.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
WG3 – STRIP R&D ITS - COMSATS P. Riedler, G. Contin, A. Rivetti – WG3 conveners.
1 KU MRI What is the MRI? What is KU doing? Firmware/testboards Optical hybrids Sensors.
PS Module Ron Lipton, Feb A bit of History During much of the conceptual design phase of the outer tracker we had focused on the “long barrel”
Ideas for Super LHC tracking upgrades 3/11/04 Marc Weber We have been thinking and meeting to discuss SLHC tracking R&D for a while… Agenda  Introduction:
M. Gilchriese - September 2000 Pixel Insertable Layouts September 2000.
M. Gilchriese Towards Fabrication of a Mechanical Prototype Stave.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
M. Gilchriese 1 Pixel R&D The useful lifetime of the innermost pixel layer is expected to be limited to a few years at design luminosity. However, there.
RD program on hybrids & Interconnects Background & motivation At sLHC the luminosity will increase by a factor 10 The physics requirement on the tracker.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
RD42 Status Report W. Trischuk for the RD42 Collaboration LHCC Meeting – June 12, 2013 Development of CVD Diamond Tracking Detectors for Experiments at.
Upgrade plans for ATLAS. Nigel Hessey (Nikhef) is overall ATLAS upgrade coordinator.
Straw man layout for ATLAS ID for SLHC
CMS Phase 2 Tracker R&D R. Lipton 2/27/2014
Detector building Notes of our discussion
FBK / INFN Roma, November , 17th 2009 G. Darbo - INFN / Genova
Some input to the discussion for the design requirements of the GridPixel Tracker and L1thack trigger. Here are some thoughts about possible detector layout.
Technical Design for the Mu3e Detector
P. Morettini Towards Pixel TDR PM - ITk Italia - Introduction 8/2/2017.
SVT – SuperB Workshop – SLAC 6-9 Oct 2009
TK Upgrade report.
Work packages status in Torino and perspectives
Valerio Re (INFN-Pavia) on behalf of the RD53 collaboratios
SVT – SuperB Workshop – Frascati Sept. 2010
Perugia SuperB Workshop June 16-19, 2009
Presentation transcript:

M. Gilchriese ATLAS Pixel Upgrade Thoughts on US Role

M. Gilchriese 2 History The US had lead or co-lead roles in the fabrication of the current detector in –Integrated circuit electronics –Module design and lab/test beam irradiations and verification of design –Module fabrication coordination, equal role in fabrication –Module hybrid design/fab –Optical readout –Mechanics –Services –Systems integration(such as it was) –Off-detector readout(RODs) Upside – US only country that covered most bases, “vertically integrated” – vital to project Downside – lots of work, take on risk

M. Gilchriese 3 Upgrade Considerations SLHC scale currently about x 3 of current detector in area Uncertainty about B-layer replacement (what is it?) likely to add to scope ATLAS not well positioned for relatively early luminosity upgrade to 2-3x10 34 (Phase I, 2013?) => more upgrade pressure? Stated SLHC upgrade schedule ( ) very, very difficult In short, upgrade is a challenge! US involvement in pixels has expanded since construction ….SLAC, Columbia, UT Dallas, OK State… Can imagine some additional expansion for upgrades In what follows, I assume US role in upgrade similar in spirit to previous role in current detector

M. Gilchriese 4 Sensors Two, parallel developments? Small radius, very high dose –3D? –Diamond? Larger radius, high dose –Planar that survives. Large areas –Down to what R? –Cheap, compared to 3D or diamond, is critical Fundamental sensor R&D – all But sensors + electronics + irradiation + test beam + lab tests….this was huge amount of work in past, will be again – really will need people! Common tests(3D, planar…) US: New Mexico(3D), OSU(diamond), SLAC?(3D?), Santa Cruz(planar), LBL(only at lab/beam test level)

M. Gilchriese 5 ICs and “Off-Detector” FE-I4 –Development launched with Bonn, Genoa, CPPM, Nikhef –LBL hopes to have enough resources to be “core” but overall effort very thin –FE-I4 is only step on the way! System design –MC chip for pixels(not currently) –SMC for pixels(what does this mean?) –Optical drivers/receivers – where are they, what are the specs… –Integration with powering –New RODs Architecture doc (Alex) is start but system design needs vast amount of work. Tightly coupled with FE, modules. Apart from FE-I4, what is appropriate to actually prototype? US: LBL, Santa Cruz(but only overall arch. at moment). Penn? Weak

M. Gilchriese 6 Modules Conceptual level(Maurice + minor input from Gil) + Bonn Just started working with Bonn to understand cost/practicalities of high volume, planar? sensors + FE-Ix. How cheap could it be => determines outer radius of pixels(I think) Interconnects(hybrids, microcables) were a miserable experience in current detector Coupled with system design US not involved in key technology – bump bonding. Should we even try? US: LBL. Weak

M. Gilchriese 7 Optical Component-level R&D underway VCSELs and PINs survivability under irradiation IC driver/receivers design and prototypes In my view, really needs very much to have system level view imposed to avoid wasting time What are the practical options for location of optical transition? Two extreme models: end of stave(or equivalent) – very hard at low R or outside of ID volume and use cables. Very different R&D for these extremes. Maybe right answer is in middle but focus is lacking so far(I think) US: OSU, OK and OK State. Connection to SMU?

M. Gilchriese 8 Mechanics I think I have a clear view of how to develop a “menu” of options for basic mechanical structure for modules over the next some months –Radius dependent –Don’t know cooling yet(not our decision only), so look at both CO2 and C3F8 –Constraints (who holds up what and how) –Thermal FEA for different options –Enough mechanical FEA to estimate material –Materials characterization and small prototypes US: LBL(+ W. Miller), U. of Washington?(contact underway), SLAC?. Interface to CERN-based ID upgrade engineering organization(Catinaccio) – N. Hartman(LBL) stationed at CERN

M. Gilchriese 9 Services/Systems Services for current pixels was painful Coupled to electronics system design, modules, optical and mechanics – overall system design Need to make sure any R&D that touches on electrical or cooling services takes into account overall important concepts –Low radiation length but –Reliability! –Easier to make and connect than now –Replacement requirements This is not R&D, it’s engineering Again need interface to CERN-based structure that is developing, for now also Hartman but need electrical side…

M. Gilchriese 10 Layout/Simulation Layout –Simplistic view: 4 pixel hits, minimum feasible B-layer radius(determined by radiation damage and practical matters) and maximum outer radius(determined by cost and practicalities eg. disk size) +2 other layers, to give about equal spacing –What is “easily” replaceable and what is not –Strawman layout exists –Alternatives being studied –Needs considerable optimization from a practical point of view and engineering input –A lot of this can be done in the US and soon Simulation –I’m ignorant –Some work(Nevksi, Jason…) –Double-b-layer?

M. Gilchriese 11 Practicalities R&D is underway. Keep it going But should we instigate any new ATLAS R&D EoI/projects? There is close connection among many aspects of the R&D Need big picture on regular basis to guide R&D May upgrade meeting at LBL first attempt in US Afterwards? Commonality with silicon strips – what is it? Looking towards upgrade project, how organized(depends on ATLAS not just US) –Pixels –Strips –RODs, optical, powering....how much is separate and how much specific to pixels or strips –What part of mechanics/services should be common?