Northern Periphery Programme 2007-2013 Advice to Lead partners for final reports Lead Partner Seminar 18th September 2013 Scandic Hotel, Skellefteå, Sweden.

Slides:



Advertisements
Similar presentations
MONITORING OF SUBGRANTEES
Advertisements

WELCOME! Agenda of the workshop
PRESAGE CTE FINANCIAL MANAGEMENT AND REPORTING PROCESURES
INTERREG IIIB CADSES NEIGHBOURHOOD PROGRAMME Transnational Training Seminar for potential Lead Partners and Partners, 3rd call November 9th-10th 2004,
PRESAGE-CTE Seminar MED Programme MED Programme Paris, 22 nd September 2009.
Financial Management and Auditing Reporting by the Lead Partner 3 rd round operations Rostock, Elise Oukka.
TUTORIAL Grant Preparation & Project Management. Grant preparation What are the procedures during the grant preparations?  The coordinator - on behalf.
Supported by Project Administration Second Project Meeting London, 10/11 March 2009 Liv Becker / Veit Bürger, Öko-Institut e.V.
How to make a Progress Report Activity Reporting Lead partner and partner seminar Voss, Norway June 2008 Maxi Nachtigall.
Financial Reporting Stefan Nyström, MA Per Dahlström, MA Lead Partner Seminar.
Activity Reporting Lead Partner and Partner Seminar 16 June 2009 – Laukaa, Finland Kirsti Mijnhijmer.
Project Implementation Monika Balode Joint Technical Secretariat Lead Partner Seminar 16 October 2009, Šiauliai.
Northern Periphery Programme Final Administrative Report Lead Partner Seminar 22 nd February 2012.
Financial management Management and control systems Training for Programme Operators March 2012.
NPP Information sources & guidance documents Niclas Forsling Kirsti Mijnhijmer First Level Control Event 6 November 2008, Copenhagen European Union European.
Green Partnerships Local Partnerships for Greener Cities and Regions 1st Reporting /Presage Other administrative issues Portugal, 8-10 July 2013.
Northern Periphery Programme How to Close a Preparatory Project Christopher Parker 20th March 2014 North Atlantic House, Copenhagen, Denmark.
Financial Reporting Procedure Lead Partner Seminar 28th September 2011 – Hotel Rica Alta, Alta, Norway Mattias Assmundson.
Matching Grants. Address humanitarian conditions that benefit a community in need Direct Rotarian involvement Match at least two countries (host and international)
INTERREG IVA 2 Mers Seas Zeeën Crossborder Cooperation Programme Part-financed by the European Regional Development Fund (ERDF) Project monitoring.
Northern Periphery Programme Final Project Claim 18th September 2013 Scandic Hotel, Skellefteå, Sweden Stefan Nyström.
Application Form Part 1, Sections 1-3 How to Apply Seminar 16 th September 2010 – Copenhagen Christopher Parker.
Wrap up and next steps Christopher Parker & Kirsti Mijnhijmer 28 January 2009 – Copenhagen, Denmark European Union European Regional Development Fund.
Wrap up and next steps Christopher Parker & Kirsti Mijnhijmer 23 February 2010 – Copenhagen, Denmark European Union European Regional Development Fund.
Charter School 2015 Annual Finance Seminar Grant Management Office of Grants Fiscal September 11, 2015.
Narrative reporting: good practices. Joint Technical Secretariat Seminar for Beneficiaries February 2012 Narva, Estonia.
HiLumi LHC is co-funded by the EU FP7 Capacities Programme, Grant Agreement Svet Stavrev (EU Projects Office, CERN) Administrative Manager 17.
Financial Reporting Niclas Forsling Lead Partner & Partner Seminar 13th of June 2008 – Voss, Norway European Union European Regional Development Fund.
Financial reporting Linda Wormö, MA Per Dahlström, MA 1st October,2015 Kuopio, Finland.
Green Partnerships Kick-off meeting Expenditure reporting procedure in PRESAGE- CTE JTS MED Programme cofinancé par le Fonds Européen de Développement.
Activity Reporting Lead Partner Seminar 20 th January 2011, Friars Carse Hotel, Dumfries, Scotland Rachel Burn.
MED PROGRAMME – – 2nd call MED PROGRAMME – Lead Partner Seminar – 2nd call Marseille – 26 th May 2010 Gianluca Ferreri, Project Evaluation and Monitoring.
Practical Information and Guidance to Applicants Green Industry Innovation Programme Romania July 2014 Practical Information and Guidance to Applicants.
Activity Reporting Lead Partner Seminar 22 February 2012 Copenhagen Rachel Burn.
Northern Periphery Programme Advice to Lead partners for final reports Lead Partner Seminar 14th November 2012 City Hotel, Londonderry/Derry,
Technical Assistance Office 1 SOCRATES - MINERVA GRANT AGREEMENT 2004 Kick-Off Meeting, Brussels 22 October 2004.
Project Management Birutė Markevičiūtė Joint Technical Secretariat Lead Partner Seminar 13 October 2008, Riga.
Orientation for new project Lead partners and partners Overview of the claim system Lead partners and partner seminar Voss, Norway June 2008 Maxi.
Overview of the claim system Lead partner and partner seminar Sundsvall, Sweden 5th February 2009 Maxi Nachtigall.
How to submit a complete claim Christopher Parker, Joint secretariat Stefan Nyström, MA Per Dahlström, MA Lead Partner Seminar 24th- 25th March, 2015,
The Lead partner responsibilities Stefan Nyström, MA Per Dahlström, MA Lead Partner Seminar.
Part II - Orientation for new project Lead Partners and Financial Officer Christopher Parker, Secretariat Lead Partner Seminar 24th- 25th March, 2015,
Technical Assistance Office 1 Contract, Reports and errors to avoid! GRANT AGREEMENT 2005 Comenius coordinators’ meeting, 17/10/2005 Maryline Fiaschi,
Technical Assistance Office TCP Projects 2005 Contractual and Financial Management Administrative and Financial Handbook Prepared by IA, 14/12/2001 SOCRATES.
Preparatory projects as tool for project development 4th February 2009 – Sundsvall, Sweden Maxi Nachtigall European Union European Regional Development.
Project financial reporting Linda Wormö April 20th, 2016 – Faroe Islands.
INTERREG III B CADSES Neighbourhood Programme Administrative and Financial Aspects of Hydrocare Project Dr. Janka Strakova Project contact.
Welcome. Contents: 1.Organization’s Policies & Procedure 2.Internal Controls 3.Manager’s Financial Role 4.Procurement Process 5.Monthly Financial Report.
Eligibility Rules Stefan Nyström, Managing Authority June 1, 2016 – Cork, Ireland.
FUSE TEMPUS Project Coordination Meeting Belgrade University, 27 and 28 November, 2014 INTERMEDIATE REPORT (IR) PREPARATION (+ Statement of the Costs Incurred.
Preparatory projects and funding opportunities 17 th June 2010 – Copenhagen, Denmark Christopher Parker and Rachel Burn European Union European Regional.
Lead Partner Seminar Christopher Parker 13 th of June 2008 – Voss, Norway European Union European Regional Development Fund.
NPP Financial Reporting Procedure Niclas Forsling Lead Partner Seminar Event Jyväskylä, Finland 16 th of June, 2009 European Union European Regional.
Project Financial Report Stefan Nyström September 29th, 2016 – Akureyri, Iceland.
Partner Financial Report
Partner Financial Report
SOUTH BALTIC CROSS-BORDER CO-OPERATION PROGRAMME
Activity Report in the Progress Report lifecycle
Application Form Sections 1-3 Christopher Parker & Kirsti Mijnhijmer 28 January 2009 – Copenhagen, Denmark European Union European Regional Development.
Preparatory projects and funding opportunities th August 2010 – Copenhagen, Denmark Christopher Parker and Rachel Burn European Union European.
PROJECT MANUAL Galina Georgieva Project Officer
PROJECT ACTIVITY REPORTING
Management Verifications & Sampling Methods
Kick-off meeting of the project UMBRELLA
PROJECT ACTIVITY REPORTING
Partner Financial Report
Eligibility Rules Stefan Nyström, Managing Authority
Management Verifications & Sampling Methods
PROJECT ACTIVITY REPORTING
Welcome address Christopher Parker, Joint Secretariat
Presentation transcript:

Northern Periphery Programme Advice to Lead partners for final reports Lead Partner Seminar 18th September 2013 Scandic Hotel, Skellefteå, Sweden Christopher Parker and Stefan Nyström

Advice to partners and lead partners – "Be pro-active" parters and lead partners - "Be pro- active" vice to partners and lead partners - "Be pro-active"  Plan ahead knowing that delays are expected from FLC 's and other members of the partnership consortium  Start working on final report before the project is due to be completed  Make sure all public match funding is accounted for both cash and In- kind  Submit budget changes to Desk officer before processing claim for each partner and whole project before END DATE ( i.e. 2 month before)

Advice to partners and lead partners – "Be pro-active" parters and lead partners - "Be pro- active" vice to partners and lead partners - "Be pro-active"  ONLY complete Final reports WILL BE processed, meaning.....ALL components of the Final Reporting Package with supporting documents must be received and correct. Ensure for example:-  that Fact sheets in the Final Content are for products and services and not activities.  that Final project claim is correct.  that promotional material has been sent  that project website is updated  Programme Secretariat will conduct an Admissibility check to determine if all components of the Final Reporting Package have been submitted, if missing…… The Final Reporting Package will not be processed until complete.

Advice to partners and lead partners – "Be pro-active" To avoid delays  Get Financial claims to partner FLC's in good time to avoid delays  Ensure - communications indicators are accumulative and not from the project's last progress report  Ensure - Indicators in Administrative and Final content reports match  Ensure - Final content report and Product and Service facts contain correct contact details  Ensure - Public match funding has been received

Lead Partner Principle  Role Lead Partner:  Acting as link between the project partners and the programme  Submitting the project progress reports and now your final report  Overall responsibility for project coordination  Formal beneficiary of ERDF and ERDF equivalent funding  Lead Partner has the responsibility to distribute the funding received from the NPP among the project partnership in accordance with the spending by the partners. The complete Lead Partner responsibilities are stipulated in Regulation: (EC) 1080/2006, Art 20 Advice to partners and lead partners – "Be pro-active"

Lead Partner Principle  Role Lead Partner:  Be the policeman of the project, ensure that all certified costs can be connected to eligible/approved project activities (Letter distributed) Northern Periphery Programme recommends that all partner Certificates of Expenditures (CoEs) to the LP are supported by a partner activity report, clearly outlining the individual partner activities, and a transaction list to demonstrate which costs are related to what activities. AND It is vital that the Lead Partner can extract the individual partner activities from the overall Work Package activity plan, potentially outline individual partner activities in the partnership agreement. Advice to partners and lead partners – "Be pro-active"

 1. Admissibility check List of priority 1 or 3 Complementary information from LP ? List of priority 3 – 2  2. Review of final claim Costs vs budget Eligible and sufficient funding Complementary information from LP ? Assessment Final report (secretariat)  3. Decision of payment. Managing Authority

COMMON ERRORS  Copies of Certificate of Expenditure and First Level Control checklists  Missing Blue-ink signatures, First Level Control and Lead Partner Certificate of Expenditure missing pages  Whole or part of document  Missing First Level Control checklist  Whole or part of document  Old template for the Certificate of Expenditure  Template from previous programme period  Not the latest version, i.e. missing budget lines 10 and/or 11  Statement of Expenditure instead of Certificate of Expenditure Advice to partners and lead partners – "Be pro-active"

Desk check errors  Wrong expense period on Payment claim  In relation to decision  In relation to Certificate of Expenditures  Wrong bank information, IBAN / BIC  In relation to application/decision  In relation to latest supplied information  Claim signed by person not authorized to sign for the organisation  In relation to enclosure 2 of decision  In relation to latest supplied information  Faulty Summary of CoE:s page  Partner listed on wrong funding source compared to the decision, mostly of the 20% flexibility area  Expenditure amounts entered in Summary of CoE:s not corresponding with Partner CoE.  Faulty 2nd page of project claim due to mistakes in Summary of CoE:s page  Match funding amounts entered in Summary of CoE:s not corresponding with Partner CoE:s  Costs certified in budget lines that has nothing budgeted for. Advice to partners and lead partners – "Be pro-active"

Desk check errors  Invalid Certificate of Expenditure  First Level Controller not approved by National Controller  Wrong expense period, expenses approved beyond the claim period  Deductions missing from page 3 of CoE  Wrong expenditure and match funding  Amounts in current CoE versus previous CoE, doesn’t correspond.  Insufficient First Level Control Check list  All answers not ticked  Answers on questions 8-12 “Not checked” or “Not applicable”, without specifying reason why. Advice to partners and lead partners – "Be pro-active"

 REMEMBER – All partners are counting on you meeting your deadline and avoiding finanical complexities.

Thank You for Listening!