ATC/ABOC days, 24 January 2007Edda Gschwendtner1 CNGS : Status and Outlook Edda Gschwendtner, AB/ATB Summary of CNGS 2006 Reflector Repair OPERA Brick.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

Now2008 Paola Sala for the CNGS SBWG CNGS status Paola Sala, INFN Milano on behalf of the CNGS Secondary beam working group.
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 1 I) CNGS status radiation damage on electronics strip line repair II) OPERA issues Based on the work.
1 The CNGS Reflector Water distribution system Outer conductor Inner conductor Drain connections  5 Drain tube Support and alignment frame Transport chassis.
ISS, 23 September 2005E. Gschwendtner, CERN1 Beam Instrumentation at CNGS 1. Introduction 2. Layout 3. Beam Instrumentation 4. Summary.
CNGS Operation Results 2008 Edda Gschwendtner AB/ATB on behalf of the CNGS team.
Performance and Operational Experience of the CNGS Facility Edda GSCHWENDTNER, Dario AUTIERO, Karel CORNELIS, Ilias EFTHYMIOPOULOS, Alfredo FERRARI, Alberto.
1 BMS activities and brick maniupulation Short summary of 2008 activities and results Extraction and filling activities foreseen in 2009 Black CS extraction.
The CNGS Operation and Perspectives l Edda Gschwendtner, CERN.
Status of the OPERA experiment Yoshiaki Nonoyama Nagoya Univ.
NBI March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration.
Preliminary studies for Muon shield modification to accommodate LCLS II Alev Ibrahimov December, 2010 BSY.
WIN’11 CERN Neutrinos to Gran Sasso: The CNGS Facility at CERN l Edda Gschwendtner, CERN WIN’11, Cape Town, South Africa, 31 st Jan – 5 th Feb 2011.
NuMI Horn Construction and Testing
Ans Pardons 30/11/2006CNGS Reflector Technical Review CNGS reflector: Status Work remains to be done… 30/10 Introduction Drain connection Event analysis.
NBI CNGS Horns Status Presented by Sandry Wallon 1 NBI 2003 – KEK, Japan 7-11 nov CNGS Horns : Status 8 nov
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
NuMI NBI2006 September 9, 2006 NuMI Repairs for Hot Components Jim Hylen / FNAL Page 1 NuMI Repairs for Hot Components (1 sievert = 100 rem) Problem On.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
The CNGS Horns Electrical Systems The CNGS Horns Electrical Systems 4th workshop on Neutrino Beams and Instrumentation 7 – 11 November 2003 at KEK Gilles.Maire.
CNGS ISSUES - THAT COULD DISTURB A SMOOTH OPERATION IN 2009 Thanks to colleagues who contributed to the slides: E. Gschwendtner, A. Pardons, H. Vincke,
1 18 July 2005 “Mini-Review” on CNGS Horns Introduction by K. Elsener 1 “Mini-Review” - Introduction Function of focusing horns “History” of CNGS horns.
NuMI NBI2006 September 6, 2006 NuMI Target Experience Jim Hylen / FNAL Page 1 Experience with the NuMI Target Max. Proton/spill Max. Beam Power Integrated.
Status of the NO ν A Near Detector Prototype Timothy Kutnink Iowa State University For the NOvA Collaboration.
OPERA Experiment, Brick Finding Program A. Chukanov Joint Institute for Nuclear Research ISU, 12 th February, 2007.
The CNGS Facility: Performance and Operational Experience Edda GSCHWENDTNER, Karel CORNELIS, Ilias EFTHYMIOPOULOS, Alfredo FERRARI, Ans PARDONS, Heinz.
1 Status of Neutrino Beamline Construction K. Nishikawa IPNS, KEK 2006 . 12 . 4.
Electrical Discharge Circuit for CNGS Horn & Reflector PH/DT1 Group Meeting, 23 October 2007 Gilles MAIRE PH/DT1-IC Section Leader.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
6 April 2006E. Gschwendtner, CERN AB/ATB1 CNGS Project: Secondary Beam 1. Layout 2. Beam Instrumentation 3. Commissioning Plans for the Secondary Beam.
Overview of the KEK Neutrino Beam Facility and its Operation Summary after September 2000 FNAL) K.H. Tanaka for the KEK-PS Beam Channel Group.
F NuMI Beamline Accelerator Advisory Committee Presentation May 10, 2006 Mike Martens Fermilab Beams Division.
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Status of LS1 collimator maintenance O. Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro.
Lau and Niels, NA62 TD meeting, 17 March Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
The CNGS Target Station By L.Bruno, S.Péraire, P.Sala SL/BT Targets & Dumps Section.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
CNGS Operation Summary Edda Gschwendtner, CERN. Outline Introduction CNGS Performance Highlights since last NBI 2010 in Japan Issues Summary 2E. Gschwendtner,
6 April 2006Malika Meddahi 1 CNGS Project: primary beam 1.Project Overview 2. Proton beam line overview and status 3. Target status 4. Commissioning preparation.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
T2K Status Report. The Accelerator Complex a Beamline Performance 3 First T2K run completed January to June x protons accumulated.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Users' Mtg - 4 Jun 08 FNAL Accelerator Complex Status Ron Moore Fermilab – AD / Tevatron Dept.
NUMI Flexible Joint/Floating Clamp WBS Power Supply System Level 3 Manager Nancy Grossman FNAL July 10, 2001.
OPERA Experiment, Brick Finding Program A. Chukanov Joint Institute for Nuclear Research Dubna, 25 th January, 2007.
29 June 2006 CERN Neutrinos to Gran Sasso Seminar for CERN guides, by K. Elsener 1 CNGS - CERN Neutrinos to Gran Sasso > “Neutrinos” and “Gran Sasso” >
NBI2006 Starting OPERA data-taking with the CNGS beam D.Autiero IN2P3/IPN Lyon 5/9/2006.
NUMI NUMI/MINOS Status J. Musser for the MINOS Collatoration 2002 FNAL Users Meeting.
Update: Puck and Gun Magnet March 1, Magnetized Gun 2 K 2 CsSb Preparation Chamber HV Chamber.
CNGS: First Year of Operation E. Gschwendtner AB/ATB on behalf of the CNGS team.
2008 European School of High-Energy Physics - Trest, Czech Republic - 19 August - 1st September Target Tracker Data Analysis In OPERA Experiment S. Dmitrievsky,
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Emulsion Test Beam first results Annarita Buonaura, Valeri Tioukov On behalf of Napoli emulsion group This activity was supported by AIDA2020.
HB2008 – WG F: 27 Aug. S. Childress – Diagnostics_2MW 1 NuMI Beam Diagnostics and Control Steps to 2 MW S. Childress Fermilab.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
V. Raginel, D. Kleiven, D. Wollmann CERN TE-MPE 2HiRadMat Technical Board - 30 March 2016.
X PS Internal Dump Core Review François-Xavier Nuiry Giulia Romagnoli
J. Musser for the MINOS Collatoration 2002 FNAL Users Meeting
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
CNGS Run 2007: Radiation Issues
News and brief overview of Beamline plans for the next few months
Conventional Neutrino Beams Day 2
The Quench Detection-Wire-Feedthrough Plug-In of W7-X
Status of muon monitor R&D and construction
CNGS Project Overview Konrad Elsener.
CNGS horn / reflector in 2005: The story of the glass ring insulator
Presentation transcript:

ATC/ABOC days, 24 January 2007Edda Gschwendtner1 CNGS : Status and Outlook Edda Gschwendtner, AB/ATB Summary of CNGS 2006 Reflector Repair OPERA Brick Production

ATC/ABOC days, 24 January 2007Edda Gschwendtner2 Hardware commissioning  Feb. – April 2006 ‘Dry runs’ from CCC  April – May 2006 Commissioning with beam  weeks 28, 30 and 33 in July/August 2006 Physics Runs:  August 2007  October 2007 CNGS Schedule 2006

ATC/ABOC days, 24 January 2007Edda Gschwendtner3 CNGS low intensity run: October: 9.5x10 15 p.o.t. CNGS operation II: October: 5.8x10 16 p.o.t. CNGS operation I: August: 7.8x10 17 p.o.t. CNGS Commissioning: Weeks 28, 30, 33: 7x10 15 p.o.t. 1x10 13 CNGS low intensity run: October: 9.5x10 15 p.o.t. CNGS operation II: October: 5.8x10 16 p.o.t. CNGS operation I: August: 7.8x10 17 p.o.t. CNGS Commissioning: Weeks 28, 30, 33: 7x10 15 p.o.t. 1x10 13 DateExtractionsProtons Commissioning W2810 – 14 Jul E14 Commissioning W3031 Jul. – 4 Aug E14 Commissioning W3314 – 18 Aug E15 Physics Operation I18 – 30 Aug E17 Low Intensity Tests12 – 13 Oct E15 Physics Operation II26 – 27 Oct E16 Maximum proton intensity reached in 2006: 3.5 ·10 13 /cycle at 400GeV While setting up high intensities for all 3 cycles, reflector leak appeared

ATC/ABOC days, 24 January 2007Edda Gschwendtner4 What Have We Learnt? Commissioning was very successful  Detailed hardware commissioning  ‘Dry runs’ Allowed early debugging of all systems Smooth start-up  Beam interlock system very good  Extraction channel well tuned  Beam well centered along beam line Beam position stability: 50  m rms Beam spot at target: 0.5 mm rms.  Centering of beam vs. target and horn important  Muon monitors: very sensitive to any beam changes Used as on-line feedback for quality control of neutrino beam.

ATC/ABOC days, 24 January 2007Edda Gschwendtner5 What Have We Learnt II ? Radiation Protection constraints to CNGS operation Cool down limit for starting access into CNGS  2hr + 4hr (i.e. 4 hr ventilation on) RP inspection mandatory before any access is granted:  Takes ~1/2 day (surveys, taking samples, etc.) Dose planning mandatory for any interventions  Emptying sumps before start-up amount of condensation water draining into TSG4 sump is completely different in ‘beam mode’ and in ‘access mode’.

ATC/ABOC days, 24 January 2007Edda Gschwendtner6 Issues Requiring more Studies TBID calibration:  Move target out Polarity change:  Understand different muon signals Muon detectors:  linearity effects with high intensity Alignment of beam with respect to target and horn  Might need to be done regularly (every month)

ATC/ABOC days, 24 January 2007Edda Gschwendtner7 The CNGS Reflector Water distribution system Outer conductor Inner conductor Drain connections  5 Drain tube Support and alignment frame Transport chassis

ATC/ABOC days, 24 January 2007Edda Gschwendtner8 Leaking Drain Connection Outer conductor (Al) Titanium joints Ceramic insulator (500V) (brazed to the Ti joints) Clamps for vapor tightness Rupture point – leak!! Bellows to give (some) flexibility

ATC/ABOC days, 24 January 2007Edda Gschwendtner9 New Design for Drain Connection Improvements of new design: Second welded bellows  Absorb better any misalignment errors Water and vapour tightness maintained  tightening the ceramic between flanges with bolts Brazing is avoided Rigorous QA during assembly  Tracing of equipment and record history ATC/ABOC days, 24 January 2007 Aluminum Stainless Steel CNGS Reflector Leak Review Meeting with AB, TS and RP experts, held on 29 Nov 06

ATC/ABOC days, 24 January 2007Edda Gschwendtner10 Next Steps Tests First Prototype of drain connection delivered end this week Mounting prototype on spare horn Transport to BA7 Perform tests with spare horn, starting Week 6:  Electrical tests: double pulse, 150kA  Vibration measurements on old drain connection Understand stress/displacement Free/fix connector  Vibration measurements on new drain connection Validation of new design Repair Radiation Issues  Careful dose planning needed Repair is not trivial All drain connections: (3 x 5 + spares)  Ceramic: ordered (6 weeks delivery)  Flanges + bellows: delivery end March

ATC/ABOC days, 24 January 2007Edda Gschwendtner11 Reflector Repair Schedule Start testing with spare horn in BA7 (nominal conditions: current / water) Start repair work for reflector Start repair work for horn Horn/reflector ready for beam Most optimistic scenario! No contingency…

ATC/ABOC days, 24 January 2007Edda Gschwendtner12 Repair Procedure The top and side shielding blocks are removed with crane  for the horn everything can be done remotely  for the reflector the side shielding requires manual intervention Repair cannot be done in the beam position of the reflector (horn)  access is limited  radiation levels higher inside the shielding The reflector and horn moved to upstream area of the target chamber  sufficient space available Chariot foreseen for the horn transport can be used as pedestal during the works Outer conductor part of reflector/horn has to be disconnected from the bottom chassis  bellows flexibility not sufficient to remove ceramic pieces.

ATC/ABOC days, 24 January 2007Edda Gschwendtner13 Repair Location

ATC/ABOC days, 24 January 2007Edda Gschwendtner14 CNGS Horns: Other Possible Weak Points Water inlet bellows  Thin stainless steel foil brazed on ceramic sleeve  Thin foil brazed to water tube Water sprayers  Double-walled  no leak when bellows failure  50% already replaced

ATC/ABOC days, 24 January 2007Edda Gschwendtner15 31 target planes / supermodule  Targets Magnetic Spectrometers SM1SM2 OPERA Experiment In total: bricks, 1766 tons Scintillator planes 5900 m m long drift tubes 3050 m 2 Resistive Plate Counters 2000 tons of iron for the two magnets

ATC/ABOC days, 24 January 2007Edda Gschwendtner16 Beam Events 2006 Muon from CC interaction in the material in front of the detector (BOREXINO, rocks) CC event in the first magnet

ATC/ABOC days, 24 January 2007Edda Gschwendtner17 BAM piling/pressing section BAM wrapping section Brick Production CS box Brick

ATC/ABOC days, 24 January 2007Edda Gschwendtner18 OPERA Outlook for 2007 Assumptions  Official SPS schedule: useful days  1.7 E13 pot/extraction, 70% efficiency of machines complex  Pedestal bricks on 15 January 2007: 1300  Week 3 and 4: 5 drums of 8 rows/week  Week 5 and 6: 10 drums of 8 rows/week  BMS MD, devoting 3 working days/month Options  SPS Supercycle with 3 CNGS, 39.6 sec, 1.56 E17 pot/day  SPS Supercycle with 1 CNGS, 16.8 sec, 1.22 E17 pot/day  Filling speed from 12 February 2007 on: 15 drums of 9 rows/week (= 15 x 9 x 26 =3510 bricks)  Filling speed from 12 February 2007 on: 10 drums of 9 rows/week (=2340 bricks) rows drum Courtesy of D. Autiero, Y. Declais

ATC/ABOC days, 24 January 2007Edda Gschwendtner19 OPERA Outlook for 2007 Option Integrated pot Bricks on 26/05/07 Bricks on 11/11/07 Bricks with interactions 3 CNGS cycles 15 drums/week 2.1 E CNGS cycle 15 drums/week 1.65 E CNGS cycles 10 drums/week 2.1 E CNGS cycle 10 drums/week 1.65 E  Will be presented in the next SPSC, 6 February 2007 Courtesy of D. Autiero, Y. Declais

ATC/ABOC days, 24 January 2007Edda Gschwendtner20 CNGS Perspectives for 2007 Repair of Reflector and Horn ongoing  Finished by week 21 for SPS Physics Start-Up …if everything goes well!! 2 weeks needed to complete the setting up schedule of October 2006 of the CNGS primary & secondary beam.  Understand polarity change, muon detector linearity, etc… MD slots during the run needed for the Secondary Beam Line

ATC/ABOC days, 24 January 2007Edda Gschwendtner21 Spare Slides

ATC/ABOC days, 24 January 2007Edda Gschwendtner22 1 st shot down proton beam line: beam is already well centered on screens 8 profile monitors (BTVG): Optical Transition Radiation screens: 75  m carbon 12  m titanium screens FIRST SHOT 11 July 2006

ATC/ABOC days, 24 January 2007Edda Gschwendtner23 E muon > 20GeV E muon > 50GeV Pit 1 On-line display pit 1, horizontal pit 2, horizontal pit 1, vertical pit 2, vertical Pit 2

ATC/ABOC days, 24 January 2007Edda Gschwendtner24 Radiation Levels inside Reflector Shielding 700  Sv/hr 1700  Sv/hr 2900  Sv/hr 1500  Sv/hr 31 st October 2006 Radiation x 5 for the horn

ATC/ABOC days, 24 January 2007Edda Gschwendtner25 Horn/Reflector Power System UnitHORN System REFLECTOR System Load Peak currentkA Pulse durationms Transformer ratio1632 Primary peak currentA Charging voltageV Water flow for delta T=5Cl/min50 Pressurebar1.2 In total: ~ pulses

ATC/ABOC days, 24 January 2007Edda Gschwendtner26 lead plates: massive target emulsions: micrometric precision 10.2 x 12.7 x 7.5 cm 3 8.3kg brick Brick Pb Couche de gélatine photographique 40  m  1 mm OPERA Experiment Basic unit: brick: 56 Pb sheets + 56 photographic films (emulsion sheets)