Hydrogen Delivery System Schedule MICE Schedule Review 23 rd -25 th May 2011 M Hills STFC.

Slides:



Advertisements
Similar presentations
1 CM24 – 2 nd June 2009 LH2 Infrastructure M Hills M Courthold T Bradshaw I Mullacrane P Warburton.
Advertisements

1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Hydrogen Pre-Operation Safety Review 4 th October 2011 Hydrogen R&D System Operational Procedures and Test Plan M Courthold.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
MICE OsC – 22 nd June 2010 Liquid-hydrogen system and absorber M Hills T Bradshaw M Courthold S Ishimoto W Lau I Mullacrane P Warburton.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
AFC Schedules and Status Tom Bradshaw John Cobb Wing Lau Matt Hills MICE MICO Meeting 12 th October 2011 Elwyn Baynham Mike Courthold Victoria Bayliss.
1 Status of Hydrogen System Development MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov, Tom Bradshaw, Elwyn Baynham, Mike Courthold,
CM26 – 26 th March 2010 Step IV: Liquid Hydrogen Infrastructure M Hills M Courthold T Bradshaw I Mullacrane P Warburton.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
paul drumm; 3rd December 2004; AFC MM 1 Cost & Schedule Review I Terms of reference: –To review the Cost and schedule of the MICE Muon beam –To review.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
MICE Project Board 23 rd September 2010 Liquid Hydrogen and General Infrastructure M Hills T Bradshaw M Courthold S Griffiths T Hayler S Ishimoto A Lintern.
H2 Safety Review - response paul drumm MICE VC, March 29 th,2006.
Hydrogen Delivery System – R&D Activities T W Bradshaw M Courthold M Hills J Rochford Daresbury Controls Group etc…
MICE hydrogen review Summary of system hardware. System function To provide 22 litres of liquid hydrogen for use as a muon absorber within a superconducting.
Mechanical Safety Systems and DSEAR Compliance
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
The MICE Hydrogen System Summary Tom Bradshaw, Yury Ivanyushenkov, Elwyn Baynham, Tony Jones, Mike Courthold and Matthew Hills Rutherford Appleton Laboratory.
MICE CM30 7 th July 2011 Liquid Hydrogen Delivery System M Hills (STFC, RAL) T Bradshaw (STFC, RAL) M Courthold (STFC, RAL) S Ishimoto (KEK) A Muir (STFC,
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MOM Report Galina Vankova RAL, MICE Video Conference.
MICE Collaboration Meeting Frascati 26 – 29 June 2005 Work Group report On Design & Safety Review.
MICE Hydrogen Control System MICE Collaboration Meeting CM33 27 th July 2012 PJ Warburton – STFC Daresbury Lab.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
1 Preparation of the hydrogen test system Yury Ivanyushenkov for Elwyn Baynham, Tom Bradshaw, Mike Courthold, Matthew Hills and Tony Jones CCLRC Technology.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
1 MICE MPB/RLSR Integration of Step IV Readiness of the major subsystems Installation sequence and schedule considerations Logistics, staffing and local.
Hydrogen Pre-Operation Safety Review 4 th October 2011 Results from Helium Commissioning M Hills.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
CM 28 – 6 th October 2010 LH2 Infrastructure M Hills M Courthold T Bradshaw I Mullacrane P Warburton.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
Hydrogen Pre-Operation Safety Review 4 th October 2011 The Hydrogen Delivery System – An Introduction M Hills.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Progress on Hydrogen R&D System
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
Hydrogen System Update Video Conference 19 th January 2012 S Watson.
1 Status of infrastructure MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation.
Progress on Hydrogen R&D System Yury Ivanyushenkov on behalf of Elwyn Baynham, Tom Bradshaw, Mike Courthold Matthew Hills, Tony Jones MICE Collaboration.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 Liquid Hydrogen update CM33 S Watson P Warburton M Courthold.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE absorbers work package MPB – 27/10/15 Mike Courthold Mark Tucker Phil Warburton Steve Watson.
1 MICE Hydrogen system Working group mtg – 01/09/14.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Replacing hydride bed with bottle Advantages No risk of diminished bed capacity Following jobs no longer necessary – Move pressure gauge – Replace cracked.
Working group meeting 07/05/15. Agenda Overview of review and current action list Relief system – Summary of problem – Details of analysis, testing and.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
Jim Fast Pacific Northwest National Laboratory
Hydrogen System Update
Liquid Hydrogen Infrastructure Update
Status of the MICE Construction Project
Absorber progress MICE-ISIS review of the liquid hydrogen system will be held in early January; guidance from Nominated Engineers on the imported absorber.
MICE CM31 Schedule summary
Presentation transcript:

Hydrogen Delivery System Schedule MICE Schedule Review 23 rd -25 th May 2011 M Hills STFC

MICE Schedule Review 24 th May 2011 Outline i.Work package overview ii.Task breakdown iii.Staff resources iv.Schedule summary v.Schedule by task vi.Milestones vii.Risks viii.STEPS V & VI 2

MICE Schedule Review 24 th May 2011 Work package overview –The Hydrogen Delivery Systems will provide liquid hydrogen to the Absorbers in MICE –Each Absorber will have a dedicated delivery system (A, B & C) –The systems use metal-hydride storage and an R&D phase is planned to de-bug this novel part of the system –The R&D phase uses a dedicated test cryostat in place of the final MICE Absorber –Upon completion of the R&D, the system will be integrated with the AFC containing a KEK absorber for final commissioning 3

MICE Schedule Review 24 th May 2011 What we have to do...to test the system 4 Heater/Chiller units for the hydride bed Test Cryostat Ventilation System (continues on the roof) Hydrogen Charging Station Vacuum Pumps (more on the roof) View of MICE Hall South Side (mezzanine not shown) Gas Panel Enclosure AND Pass a pre-operation safety review Vacuum lines

MICE Schedule Review 24 th May to be ready for STEP IV 5 AFC module in STEPIV position Gas Panel Enclosure moved up the mezzanine New vacuum line Ventilation extract duct moved

MICE Schedule Review 24 th May 2011 What we have done so far 6 Test Cryostat Ventilation System Gas Panel Enclosure Vacuum Pump Enclosure Vent stacks Control System

MICE Schedule Review 24 th May 2011 Tasks –Controls –Mechanical Design –Safety –Hall Infrastructure and Installation –R&D Testing –STEP IV Preparation (AFC Commissioning) 7

MICE Schedule Review 24 th May 2011 People  M Hills - project management, cryogenic and mechanical design  M Courthold - cryogenic design, controls and testing  T Bradshaw – advice and consultation on cryogenic issues  I Mullacrane, P Warburton - control system design and implementation  A Muir, S Postlethwaite (with supervision from A Grant) – mechanical design  Hall technicians – installation and assembly 8

MICE Schedule Review 24 th May /12 Schedule Overview 9

MICE Schedule Review 24 th May 2011 Controls 10 –Controls for helium testing already in place –This work covers the additional tasks for hydrogen testing

MICE Schedule Review 24 th May 2011 Mechanical Design 11 Mostly laying the foundations for integration with the AFC

MICE Schedule Review 24 th May 2011 Safety 12 –Working closely with consultants to ensure DSEAR and IEC61508 compliance –Plenty of documentation to prepare

MICE Schedule Review 24 th May 2011 Infrastructure and Installation 13 EMR run will push back several tasks, but work can continue on external infrastructure during this period

MICE Schedule Review 24 th May 2011 Testing 14 –Helium testing to start once power and water in the Hall are restored –Second EMR run may delay some hydrogen testing

MICE Schedule Review 24 th May 2011 STEP IV Preparation 15 –Repositioning of Gas Panel Enclosure and related services is driven by completion of R&D testing –AFC commissioning extends into May 2012

MICE Schedule Review 24 th May 2011 Milestones 16 MilestoneDate Helium R&D testing completeJuly 2011 Safety Review passedAugust 2011 Hall infrastructure and installation completeSeptember 2011 Hydrogen R&D completeDecember 2011 Manufacture of items for AFC adaption complete November 2011 AFC Commissioning completeApril/May 2012

MICE Schedule Review 24 th May 2011 Risk Summary –Funding availability –Manpower restrictions/key staff availability –Would impact all aspects of the project –Hydride bed has been affected by long term storage –A concern given that a direct replacement is no longer available –Safety review recommends major design changes before R&D testing can commence –Significant knock-on effect for STEP IV –R&D system manufacturers are unwilling or unable to take on contract for systems B & C –Would result in delays to transfer knowledge and require closer oversight of the new contract from STFC 17

MICE Schedule Review 24 th May 2011 STEPS V & VI –This means Systems B & C in the context of the Hydrogen Delivery System –Most of the hall infrastructure (e.g. vacuum enclosure, ventilation system, gas supplies) will serve all three systems, so it is ‘only’ the hydride bed, gas panel, transfer lines and control system that are required –If R&D system is successful design can be carried over with very few changes –Type of hydride bed is currently the major unknown as the current manufacturer, Treibacher, no longer supply an equivalent model –Each system will take approximately 1 year to design, manufacture and test with an AFC module (full Gantt chart available) –Current assumption is that work in System B will start in April 2012 with System C following in April 2013, but this is highly dependent on the overall project schedule 18

MICE Schedule Review 24 th May 2011 Summary –Detailed schedule is known for System A installation and the R&D testing –This is due to be completed by the end of 2011 –MICE running to commission the EMR will impact the current plan and may delay this date –Significant work following R&D testing to prepare for AFC commissioning and STEP IV –Delivery of Systems B & C should be in line with their need-by dates, but hydride bed supply issues need resolving 19