Installation and Testing of Optical Harnesses John Matheson Rutherford Appleton Laboratory Schedule for test and assembly Outline of required tests Acceptance.

Slides:



Advertisements
Similar presentations
Endcap assembly update C Buttar UK-SCT-MB RAL 2 nd Sept 04.
Advertisements

Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
CricketSat Assembly.
EMB PAR, 23 nov P. Perrodo, LAPP, Annecy1 ATLAS EMB SERIE MODULE CABLING Experience started with three successive prototype modules (module 0) in.
ATLAS Pixel Detector February 2003 N. Hartman LBNL 1 Pixel Support Tube PRR: Assembly, Production, Schedule February 2003.
Opto Harness FDR 19/10/01 T. Weidberg1 Opto Harness FDR Scope and aims of review, system overview Available documentation Status of Project & Schedule.
Plan for MRPC Production Yongjie Sun Center of Particle Science and Technology University of Science and Technology of China.
1.ATLAS and ID 2.SCT 3.Commissioning 4.Integration 5.Latest Runs 6.Conclusions Commissioning the ATLAS Silicon Microstrip Tracker IPRD08 - Siena Jose E.
GLAST LAT ProjectLAT Mgr’s Meeting LAT Planning Meeting Mechanical/Thermal Systems March 17, 2005 Marc Campell.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
Walls crates cables gas chambers electronics CERN adb.
LightABLE Production Status ID Week October 2014 Tony Weidberg1.
Target Design – Status and Plans Chris Booth Sheffield 12 th January 2005.
B W Kennedy, CCLRC Rutherford Appleton Laboratory VPTs for the CMS experiment B W Kennedy CCLRC Rutherford Appleton Laboratory St Petersburg, 26 April.
CMS ECAL End Cap EDR Meeting CERN 28 Nov. to 29 Nov 2000 A.B.Lodge - RAL 1 ECAL End Cap CMS ECAL End Cap Engineering Design Review. EDR meeting held 28.
DPF 2013 R. Kass 1 P. Buchholz, M. Ziolkowski Universität Siegen OUTLINE Lessons learned… IBL/nSQP opto-board overview assembly experience radiation hardness.
Larg. Week, April 2002, Electronics Meeting1 Progress Report On Electronics Activities in Paris Bertrand Laforge LPNHE Paris CNRS/IN2P3 – Universités Paris.
Tierra Holcomb Found. Tech 3B.  A solar panel (also solar module, photovoltaic module or photovoltaic panel) is a packaged, connected assembly.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
K.K. GanUS ATLAS Review1 Optical Hybrids K.K. Gan The Ohio State University WBS
Hybrid Integrated Circuit
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000 A.B.Lodge - RAL 1 ECAL End Cap High Voltage Cards and 2000 Electrical/Thermal Model. Progress on.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia DAQ, DCS, Power Supply and Cables Review CERN, March Electrical PP1 Basic features Electrical.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
I Wilmut CCLRC1 End-cap Engineering 8 September 2004 Ian Wilmut, RAL.
HPD Development Project is DONE! The Future is Quality assurance Database management Alignment Production of cookies and mounts Electronics interfacing.
ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined.
CMS ECAL End Cap Meeting CERN 18 Oct to 22 Oct ECAL End Cap High Voltage and Fibre Optic Monitoring Systems Progress. Progress on High Voltage and.
Neil JacksonUK-V RAL 8th September Module to Disc Assembly Infrastructure –Services and test box –Evaporative cooling system –Disc Handling Tests.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
S Temple CLRC1 End-cap Mechanics FDR Power Tapes and Optical Fibres Steve Temple, RAL 1 November 2001.
Neil Jackson University of Liverpool Hiroshima Symposium June THE ATLAS SEMICONDUCTOR TRACKER (SCT) A PRESENTATION ON BEHALF OF THE ATLAS.
ATLAS 1 Beam Pipe Support Structure (BPSS) Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman LBNL.
4-Jan-16S.Movchan Straw manufacturing and QC1 Straw tracker manufacturing procedure Dubna: assembly halls procedure conclusion Presented by S.Movchan.
Tony WeidbergOpto WG April '081 SCT Links Long Term Monitoring Summary quality installed links Techniques for monitoring long term performance –Data links.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
End-of-stave region. 2 Space Z-dimension is critical –Keep gap small (might help getting rid of stubs) Edge of last barrel silicon (at corner) is 1277.
M. Gilchriese Items from Talks U.S. Pixel Meeting Santa Cruz July 2003.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
TRIO-CINEMA 1 UCB, 2/08/2010 CINEMA Solar Array Design Review Yashraj Khaitan David Glaser Kevin Jenkins Chris Pasma Space Sciences Laboratory University.
M. TYNDEL 1 LHCC Interactions May 2003 ATLAS SCT SCT Production Status ‘Snap-shot’ of the status of the SCT production (May 2003) 1. Barrel Modules 2.
EOS and type I Prototype Service Modules Mike Dawson (Oxford), Rob Gabrielczyk (RAL), John Noviss (RAL) 19 th January 2015 ATLAS Upgrade Activities, Oxford.
High Voltage Cards & 2000 Electronic/Thermal Model. CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000A.B.Lodge - RAL -1 ECAL End Cap 1 EE End Cap Engineering.
H. Katajisto RE EDR 10/10/02 Enclosures for the RPC Link Boards Outline Introduction Periphery General Services Components, materials Manufacture, Assembly.
1. Take HV harnesses with label (IHV2) and transfer on the Stacking table. 1.1 Inspect HV harnesses visually. 2.1 Insulate HV Flex with 3M™ VHB™ Tape.
D. Greenfield CLRC1 End-cap Mechanics FDR Baseline Design Overview Debbie Greenfield, RAL 1 November 2001.
Development of optopackage at NIKHEF Fred Hartjes Contents u Geometry uEfficiency VCSEL to fibre coupling uPin diode uConclusions Optical links session.
1 10-Jul-03 Ken Bell - Rutherford Appleton Laboratory Dee Installation and Commissioning  Reminder – installation concept (A.Surkov)  Some remarks 
24 September 2012 Immanuel Gfall (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
1 Status of RPC Construction & Cassette Assembly Qingmin Zhang Argonne National Laboratory
Chiho Wang ATLAS TRT Duke University Dubna, May Barrel integration status May 24, 2005.
DATABASE ARCHITECTURE PROPOSAL Fabien Jeanneau – 19 jan 2015.
SCT Links Operation Performance from QA and operation
Stator Plan & Schedule Chris Booth 2nd March 2009
ATLAS Internal ID Service Integration
Light Emitting Diode: LED
End-cap Mechanics FDR Overview of the Project
Mechanics: (Tim).
Status report of the ATLAS SCT optical links
SCT On-detector VCSELs
Services Layout – Update
Old ROD + new BOC design plans
BaBar IFR Upgrade Mark Convery SLAC 7 Jun 06.
UK CMS Oversight Committee Mtg
Safety, reliability and maintainability
After service guide for changing PCB
Presentation transcript:

Installation and Testing of Optical Harnesses John Matheson Rutherford Appleton Laboratory Schedule for test and assembly Outline of required tests Acceptance testing Assembly to discs Final testing

Schedule for Test and Assembly: Barrel B3: 64 harnessesB3: 64 harnesses B4: 80 harnessesB4: 80 harnesses B5: 96 harnessesB5: 96 harnesses B6: 112 harnessesB6: 112 harnesses B3: 50 days April 02 -> June 02 B4,B5,B6: Oct 02 -> Mar 03 delivery -> installation ~35 days 1 man hour for acceptance test 2hr for assy to barrel / final test

Schedule for Test and Assembly: Forward D1,D7,D8: 16 harnesses/discD1,D7,D8: 16 harnesses/disc D2,D3,D4,D5,D6: 24 harnesses/discD2,D3,D4,D5,D6: 24 harnesses/disc D9: 12 harnesses/discD9: 12 harnesses/disc Total 360 (2 end caps)Total 360 (2 end caps) services to discs 7/10/02 on (90 days) => 10hr/harness 3 full-time technical staff foreseen for assembly/testing of services for barrels and discs

Barrel Harness DORIC and VDC opto package power tapes, redundancy system many traces and connections

Forward Harness forward harness consists of opto packages and optical fibres only latest version - no plastic cover test LI, responsivity in DC conditions

Test Fixture for Forward Plug-ins equivalent to forward module design will be transferred to 6 PCBs allows testing of BER

What measurements do we need ? VCSEL LI curves pin diode responsivity radiation hardness (batch acceptance) BER scan/BER long term thermal cycling/burn-in (during manufacture) power tape continuity ? power tape insulation ?

BER testing: TTC link SLOG SLOG LITMUSLITMUS OPTIFOPTIF

TTC link results: BER scan vary light power into p-i-n diode allows definition of working range BER scans < 5 min

VCSEL LI Curves SCTLVSCTLV SLOGSLOG SCTLVSCTLV scan I using SCTLV measure photocurrent in LAPD 50% duty cycle 5 min. setup/run time LAPD DMM

PIN Responsivity SCTLVSCTLV SCTLVSCTLV LEDLED DMMsupply LAPD measure I in pin bias line LEDs for reproducibility LAPD used to calibrate LEDs 10 min. setup/run

Acceptance testing at RAL Both harnesses: responsivity 10 min VCSEL L-I curve 5 min BER scans data and TTC 30 min Barrel harness additional: HV insulation resistance 5 min continuity/shorts 5 min redundancy system 10 min Total time: barrel = 1 hr, forward = 45 min

Forward harness installation: assembly former services assembled to former former used to populate quadrant after 4 quadrants, align cooling blocks

Forward harness installation: procedure cooling pipes soldered on jig mount services on front former 1. dummy modules 2. cooling pipes 3. power tapes 4. opto-harnesses transfer services to disc fix cooling blocks temporarily connect patch panels test each quadrant whilst re- populating the former because: 1. quicker 2. next step, align and glue blocks turn disc over and repeat

Final testing during installation Both harnesses: responsivity 0 min VCSEL L-I curve 0 min BER scans data and TTC 30 min BER long-term 60 min Barrel harness additional: HV insulation resistance 0 min continuity/shorts 5 min redundancy system 10 min Total time: barrel = 1 hr 45 min, forward = 90 min

procedures for installation and testing are well defined expect 3 technicians for harnesses 1 man-hour/harness, acceptance 2 hours / harness, test + installation Schedule is achievable but requires care in execution first barrel will arrive April 02, timescale less critical will allow refinement of procedures