WS Infrastructure Programme Quarterly Workshop GAUTENG REGION Presented by: Jabulani Maluleke RBIG Project Manager: Date: 31 – 01 October 2013.

Slides:



Advertisements
Similar presentations
WELCOME TO OUR CHALLENGES! Where we would like to be...
Advertisements

WS Infrastructure Programme Quarterly Workshop KWAZULU-NATAL Presented by: M. Ngxongo Regional Project Manager: WSRBIP Date: 31 October 2013.
WS Infrastructure Programme
WS Infrastructure Programme Quarterly Workshop Northern Cape Presented by: K.I. Kgarane RBIG Manager: WSS Directorate Date: 31 – 01 October 2013.
DWA CORPORATE IDENTITY Presented by: Johan Maree Deputy Director: Media Production 12 December 2012 RBIG, NTP, ACIP, MWIG Quarterly Workshop North West.
QUARTERLY REGIONAL WORKSHOP WATER SERVICES SUPPORT PROGRAMMES PROGRESS / LATEST DEVELOPMENT OF ALL PROGRAMMES Presented by: Mr G Constantinides Date: 30.
Regional Bulk Infrastructure Grant / Programme (RBIG) Grant and Policy
DWA CORPORATE IDENTITY Presented by: Johan Maree Deputy Director: Media Production 12 December 2012 RBIG, NTP, ACIP, MWIG Quarterly Workshop Free State.
BUCKET ERADICATION PROGRESS SELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS HEARINGS 22 & 23 February 2007 Presented by Ms. T. Mpotulo Department of.
1 SOUTH AFRICA’S BUCKET ERADICATION PROGRAMME WISA AFRICA Iris Lebepe DWAF 22 November 2007.
SAVANNA CITY - Gauteng’s largest privately initiated development Background information to the Premier.
PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATION 19 OCTOBER 2010.
111 HIGH LEVEL OVERVIEW WATER SECTOR FINANCIAL PERFORMANCE APRIL - DECEMBER 2010 Masibambane Coordinating Committee Meeting.
DWA CORPORATE IDENTITY Presented by: Johan Maree Deputy Director: Media Production 12 December 2012 RBIG, NTP AND ACIP Quarterly Workshop GAUTENG Presented.
1 COMMUNITY LIBRARY CONDITIONAL GRANT 4 th Quarter Performance: 2011/12 Financial year.
MINISTRY OF WATER AND IRRIGATION REVIEW OF FINANCIAL FLOWS TO WATER SECTOR BY ENG. P. MANGITI DIRECTOR LAND RECLAMATION/HEAD DONOR COORDINATION UNIT.
FREE STATE DEPARTMENT OF SPORT, ARTS, CULTURE AND RECREATION Presentation to Select Committee on Conditional Grants and Capital Expenditure on Under-Spending.
Progress achieved in the PRESIDENTIAL PACKAGE IN THE IDENTIFIED MINING TOWNS BOJANALA DISTRICT MUNICIPALITY 13 November 2013.
WS Infrastructure Programme Quarterly Workshop North West Presented by: Neo Thulo Programme Manager North West Date: 31 October 2013.
PRESENTATION ON OPEN TOILETS 1. This presentation serves to provide background and report on progress regarding the construction of toilet top structures.
Water Services Bulk Infrastructure Programme January 2008.
WS Infrastructure Programme
TECHNICAL OVERSIGHT MONITORING AND SUPPORT VISITS ON REGIONAL PROJECTS: 2014/15 Prepared by: R. Gillmer Chief Engineer : Technical Support 21 August 2014.
1 KZN SOCIAL WELFARE AND POPULATION DEVELOPMENT PUBLIC HEARINGS ON CONDITIONAL GRANTS 18 TH JAN 2006.
1 MPUMALANGA PROVINCE DEPARTMENT OF HEALTH AND SOCIAL SERVICES PUBLIC HEARING ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 18 JANUARY 2006.
DWA CORPORATE IDENTITY Presented by: Johan Maree Deputy Director: Media Production 12 December 2012 RBIG, NTP, ACIP, MWIG Quarterly Workshop Northern Cape.
REPORTING, MONITORING AND PERFORMANCE EVALUATION PROVISIONS ON NON-FINANCIALS – 2013/14 1 MIG Quarterly Workshop 3 – 4 September 2013.
1 Water Services to Schools and Clinics Programme 20 June 2007 Presentation to Select Committee on Education and Recreation By DWAF.
QUARTERLY REGIONAL WORKSHOP WATER SERVICES SUPPORT PROGRAMMES PROGRESS / LATEST DEVELOPMENT OF ALL PROGRAMMES Presented by: Ms L Mokoena Date: 31 Oct 2013.
DWA CORPORATE IDENTITY Presented by: Johan Maree Deputy Director: Media Production 12 December 2012 RBIG, NTP, ACIP, MWIG Quarterly Workshop Western Cape.
DEPARTMENT OF LABOUR Expenditure – 30 JUNE MAIN DIVISIONS OF THE VOTE.
1 Department of Education Presentation to Standing Committee on Appropriations: Expenditure and Budget Implementation for the First Quarter of 2009/10.
1 PROGRESS MADE AND RECOMMENDATIONS OF THE PORTFOLIO COMMITTEE ON THE RURAL HOUSING IINFRASTRUCTURE PROGRAMME 09 NOVEMBER 2011.
RBIG WORKSHOP 1 Supply Chain and Asset Management.
ACCELERATED COMMUNITY INFRASTRUCTURE PROGRAMME MOKGALAKA.
DEPARTMENT OF CULTURE, SPORT AND RECREATION MPUMALANGA PROVINCE COMMUNITY LIBRARY CONDITIONAL GRANT 2009 / 2010 FINANCIAL YEAR.
Presentation of the Property Rates Debt to the Port Folio Committee on Cooperative Governance & Traditional Affairs 25 October 2011 Presented by: Cathy.
1 Presentation to the Portfolio Committee: Water & Environment Presentation by Mr Trevor Balzer Programme Manager: Special Projects 16 – 17 March 2010.
P UBLIC H EARING O N C ONDITIONAL G RANTS & C APITAL E XPENDITURE PRESENTATION BY MEC GRACE PAMPIRI 1.
CONDITIONAL GRANT EXPENDITURE 3RD QUARTER Select Committee on Appropriations Parliament of the Republic of South Africa 19 May 2010.
Progress Report: Bulk Infrastructure Task Team Premier’s Co-ordinating Forum November 2009.
QUARTERLY REGIONAL WORKSHOP WATER SERVICES SUPPORT PROGRAMMES SUMMARY OF DAY 3 Presented by: Date: 1 Nov 2013.
Presentation to Portfolio Committee Progress on the Departmental Under-Expenditure and Recovery Plans -Mr. T. Zulu Director-General 1.
Integrated National Electrification Programme (INEP): Overall Performance (End of January 2012) Dr Wolsey Barnard.
11 PUBLIC HEARINGS ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 2008/2009 PARLIAMENT 27 AUGUST 2008.
Presentation to the Select Committee on Finance 26 FEBRUARY 2006.
NATIONAL DEPARTMENT OF HEALTH National Health Insurance Grant Select Committee on Appropriations Hearing on 3 rd and 4 th Quarter Expenditure 4 th June.
1 PRESENTATION expenditure for the 2008/09 financial year.
QUARTERLY PERFORMANCE OF THE MUNICIPAL INFRASTRUCTURE GRANT (MIG) – 2005/06 AND 2006/07 FINANCIAL YEARS Presentation to the Select Committee On Finance.
6/3/11 1 DEPARTMENT OF WATER AFFAIRS “Progress in the Accelerated Community Infrastructure Programme (ACIP)” Briefing to the Select Committee on Land and.
Performance of the Integrated National Electrification Programme as at 30 June 2008 (4 rd Quarter) Presentation to the Select Committee on Finance 14 August.
1 Overview The Expanded Public Works Programme (EPWP) 17 Aug 2010 EPWP incentive update for Select Committee on Public Services.
Public Hearings on Division of Revenue Bill, 25 February 2009 Presentation by Department of Water Affairs and Forestry 1.
Parliamentary submission on the eradication of the Bucket Toilet System 22 & 23 February 2007 Cllr. Derrick Ndlovu.
1 Select Committee on Economic Development Progress relating to the implementation of Integrated National Electrification Programme (INEP)
REPORT TO THE NCOP ON HOSPITAL REVITALISATION GRANT PERFORMANCE AS AT END OF 2010/11 QUARTER 2 DR S DHLOMO MEC FOR HEALTH- KWAZULU NATAL AND Ms M GOVENDER.
PERFORMANCE REVIEW Outlook for 2005/06 Financial Year Performance/Expenditure Expenditure review 2001/02 – 2007/08 Department of Local Government & Housing.
Presented by Wiseman Sibiya
Briefing on Current Expenditure and their Performance Trends
National Department of Health Presentation to the Standing Committee on Appropriations Public Hearings on the Adjustments Appropriation Bill 05 November.
FIRST QUARTER ANALYSIS REPORT
WASTEWATER MANAGEMENT 19 September 2018
PRESENTATION ON THE FINANCIAL MANAGEMENT INFORMATION 3rd QUARTER IRO 2007/ FEBRUARY 2008.
Best Practices in Operation and Maintenance of Waste Water Treatment
MASILONYANA LOCAL MUNICIPALITY
MANGAUNG METROPOLITAN MUNICIPALITY
Gauteng Department of Local Government
EPWP PROGRESS REPORT TO PORTFOLIO COMMITTEE ON PUBLIC WORKS
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
Presentation transcript:

WS Infrastructure Programme Quarterly Workshop GAUTENG REGION Presented by: Jabulani Maluleke RBIG Project Manager: Date: 31 – 01 October 2013

WS Infrastructure Programme: Quarterly Workshop Contents A: Expenditure Status 2013/14 1.RBIG 2.MWIG 3.ACIP 4.NTP B: Key Challenges C: Feedback on letter sent on 9 September 2013 regarding RBIG/ACIP Programme management developments and requirements. D: Project to be “Fast Track” E: Projects to be Launched F: Way forward

A1. RBIG : Expenditure 2013/14

A3. ACIP : Expenditure 2013/14

A4: NTP – Expenditure 2013/14 To date we have spent R at Ekangala WWTW. 2013/14 budget is R (schedule 5) R has been transferred by now and the remainder will be transferred in the last quarter of our financial year. Schedule 6 – R Fund are committed for the decommissioning of the Ekangala ponds. Environmental aspects such as EMP & Deregistration of the ponds with DWA will be done by the appointed consultant.

B: Key Challenges Court order interdicting against the second phase of SRSS implementation Delays to issue EIA approvals – (Meyerton WWTW upgrade) Delays to appoint contractors – delayed programme (Westonaria, HVN) Co-funding – delayed implementation (Westonaria, Zuurbekom) Political influences – (SRSS, Emfuleni/ Midvaal LM) Lack of RBIG funding for deteriorating bulk infrastructure in Metros(CoT & CoJ) Lack of commitment on O&M (Westonaria LM) Bulk water supply schemes with no Water Utility (Western Highveld Scheme)

B: Key Challenges(ACIP&NT) ACIP PROJECTS Involvement of councillors in appointment of SMME in the project. IA submitting the invoices that are not talking to what has been done or report submitted not talking to the invoice. Transfers Eskom application - The municipality has paid commitment fees but Eskom delaying in giving a way forward with regard to design & quotes for installation of power lines to the plant. WULA – Mpumalanga office to avail themselves in guiding CoT with the application as the catchment is theirs. Strikes in Ekangala (Region 7 of CoT) – site was closed for 2 days last month.

C: Feedback on letter sent on 9 September 2013

D: Project to be “Fast Tracked” Westonaria Scheme, both Hannes van Niekerk and Zuurbekom : unlock economic activity and service delivery (housing) SRSS, Sebokeng WWTW upgrade : relieve the Vaal system of sewage inflows and improve service delivery (Sanitation)

E: Projects to be Launched Westonaria, Hannes van Niekerk – Fourth quarter of financial year 2013/14) Ekangala WWTW upgrade – Fourth Quarter of Financial year 2013/14)

F: Way forward Approval for funding (RBIG) to continue with Phase II, Westonaria Scheme – Zuurbekom WWTW construction RBIG Policy re-consideration to fund Metro bulk infrastructure – probably more stricter conditions for Metros MMC Infrastructure (Ekurhuleni Metro) will be meeting the councilors to clear the issues delaying progress on the continuation of WCWD project.