Mu2e Cost and Schedule Ron Ray Mu2e Project manager Fermilab PAC Meeting November 3-4, 2008.

Slides:



Advertisements
Similar presentations
Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
Advertisements

US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
Muon Campus Projects Mary Convery 1. Background on Muon Campus plan Earlier Plan had 5 Common Projects:  MC1 Building (GPP)  MC Beamline Enclosure (GPP)
Mu2e WGM 2/22/2011 R. Ray Mu2e Project manager. CD-1 Our sole focus is on CD-1 and in particular, the Director’s Review scheduled for April 3-5. To be.
Mu2e WGM 6/15/2011 R. Ray Mu2e Project manager. Reviews We were on Lehman’s schedule for early August. We gave up that slot 2 weeks ago when it became.
Mu2e WGM 4/21/2010 R. Ray Mu2e Project manager. Project Team We have a L2 manager for the tracker!  Aseet Mukherjee has assumed this role  Experience.
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
Accelerator Systems Division FACET Project Management John Seeman for the FACET Study Group PPA Directorate Stanford Linear Accelerator Center DOE FACET.
Muon Campus Controls Update Brian Drendel 8/6/13.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Mu2e WGM 7/27/2011 R. Ray Mu2e Project manager. Director’s Review We have settled on date for the Director’s CD-1 Review; Oct Focus of review will.
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.
3 March 2009M. Breidenbach1 SiD LoI Costs M. Breidenbach.
Fermilab Neutrino Beamline to DUSEL Mike Martens Fermilab PAC November 3, 2009.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
AGS RSVP Weekly Meeting P. Pile 27 Jan 2005 AGS RSVP Weekly Meeting 27 Jan 2005 Useful Links: RSVP Project : C-AD.
Report from GG5, Dec. 20, 2005 Report from ILC GG 5: Cost and Engineering (Updates since Snowmass) Wilhelm Bialowons, Peter Garbincius and Tetsuo Shidara.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
Global Design Effort Americas Region Efforts and Resources Mike Harrison GDE.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
Management subcommittee closeout Jay Marx (chair, LBNL), Joel Butler (Fermilab), Stan Wojcicki (Stanford) Thanks to all for cooperation and openness!!
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Mu2e Experiment and Issues Rick Coleman, Fermilab RESMM’12, February 2012.
Project Overview Ron Ray Mu2e Project Manager Fermilab Sept. 26, 2008 Preliminary Director’s Review of mu2e Fermilab.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
AGS RSVP Weekly Meeting P. Pile 16 September 2004 AGS RSVP Weekly Meeting, 16 Sep 2004 AGS Project Office - status of funding, comments on RSVP
Mu2e WGM R. Ray Mu2e Project Manager Sept. 14, 2012.
Executive Session Director’s CD-1 Review of the Mu2e Project April 3, 2012 Elaine McCluskey.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Executive Session Director’s CD-1 Review of the LBNE Project September 25, 2012 Jim Yeck.
F Project X Overview Dave McGinnis October 12, 2007.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
U.S. Muon Accelerator Program: MICE Milestones & Resource-Loaded Schedule M. A. Palmer, Director October 31, 2012.
Director’s Review 5/5/03 Spalding DRAFT RLS 1 Project Planning  Documentation to DOE June 1  DOE Review ~July 22 Documents Summary Project Overview,
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Mu2e WGM 11/16/2011 R. Ray Mu2e Project manager. Review of the past few months In September it became apparent that the cost of Mu2e was well in excess.
Status Report on ILC Project in Japan Seiichi SHIMASAKI Director, Office for Particle and Nuclear Research Promotion June 19, 2015.
1 US Cost & Schedule Summary W. R. Edwards US Project Manager CD-2/3a Review January 8, 2008 BNL.
AGS RSVP Weekly Meeting P. Pile 2 December 2004 AGS RSVP Weekly Meeting 2 Dec 2004 Useful Links: RSVP Project : C-AD AGS Project: Office.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
Proton Improvement Plan: View from the Directorate (and the DOE) Stuart Henderson PIP Meeting Jan 3, 2012.
AGS RSVP Weekly Meeting P. Pile 24 Mar 2005 AGS RSVP Weekly Meeting 24 Mar 2005 Useful Links: RSVP Project : C-AD.
News Y2K June 25, Summary of June 12 Face-to-Face Meeting.
Plan to go forward Peter Wilson SBN Program Coordinator 27 September 2014.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Proton Driver Resources & Schedule (R&D Plan) Rich Stanek May 10, 2005.
AGS RSVP Weekly Meeting P. Pile 6 Jan 2005 AGS RSVP Weekly Meeting 6 Jan 2005 Useful Links: RSVP Project : C-AD.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
KA11 Contributions to Mu2e R. Ray Mu2e Project Manager 8/16/2010 1R. Ray.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
LARP Review, June 10, 2013Cost and Schedule Overview – M. Kaducak 1 Cost and Schedule Overview Marc Kaducak LARP Review June 10, 2013.
WBS – 30 Straight Section Reconfiguration g-2 Accelerator – 30 Straight Section Reconfiguration D. Still Fermilab Muon g-2 IDR, June 5-7.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
Executive Session Director’s Conceptual Design Review of Muon g-2 Project June 5-7, 2013 Jon Kotcher.
Comments on the February DOE Review
Resource Loaded Schedule and Budget Profile
SCT Project Management Issues
Head, Office of Project Management Oversight (OPMO)
News and brief overview of Beamline plans for the next few months
SiD LoI Costs M. Breidenbach 29 July 2010 M. Breidenbach.
Preparations for a Lehman Review
Preliminary Project Execution Plan
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

Mu2e Cost and Schedule Ron Ray Mu2e Project manager Fermilab PAC Meeting November 3-4, 2008

PAC Meeting - Nov Outline Cost Schedule Director’s Review Summary

PAC Meeting - Nov Cost Estimate We have seen that the actual cost of HEP projects almost always escalates from early cost estimates.  A reliable cost estimate requires years of effort by a large team to develop: A complete basis of estimate Final designs Risk analysis/mitigation  These activities almost always increase the cost. MECO had a team of people who dedicated several years of effort working their way through these tasks.  MECO was cancelled before these tasks were completed but the legacy of their work has given us a head start in many areas, but not all.

PAC Meeting - Nov Cost Estimate Strategy for the Proposal Use base costs from MECO for the detector and solenoids  Add 4 years of escalation at 3.5% per year Note: Many commodities and construction related items have escalated much faster than this in the past few years.  Global economic slowdown bringing them back down. “Prediction is very difficult, especially about the future” - N. Bohr  Adopt a conservative contingency of 50%, consistent with the last few reviews of RSVP. Very little scope contingency on this project. Cost and schedule contingency are the only available knobs. Many of the MECO parts were understood to a level that might justify a smaller contingency than 50%, but we think this approach is adequate and appropriate for a proposal.

PAC Meeting - Nov From the MECO MS Project File

PAC Meeting - Nov Cost Estimate Strategy (cont.) FESS did cost estimate on detector hall and beamline civil work. Use their contingency.  The building location and design are still preliminary. Value engineering and detailed integration of the building with the detector and beamline will lead to many changes over time. AD did cost estimate on accelerator modifications and beamline.  Use 100% contingency because design is at pre-conceptual stage. Assume Project Management costs of 8%  Recommended by Fermilab Office of Project Management Oversight. Industry standard is 10-15%, but 8% is more typical of Projects with off-Project scientists filling majority of management slots.

PAC Meeting - Nov Cost of Design and Construction Blue shaded boxes are costs extracted from MECO Cost & Schedule Updated since proposal Was $180,962 in proposal

PAC Meeting - Nov R&D This is money we need over the next 2 years Was $10,127k in proposal FNAL Labor added since proposal

PAC Meeting - Nov Updates Since Proposal Some double counting has been corrected. Proposal borrowed Project Management cost from NOvA. We dropped that and, pulled some project management costs out of the solenoid system and applied the 8% factor. We added an abort system for the accumulator ring We added the cost of removing the stochastic cooling system from the accumulator/debuncher ring. We added $3M to replace the lost SSC cable. Several other small adjustments.

PAC Meeting - Nov Cost - Longer Term Strategy We will develop a resource loaded cost and schedule from the bottom up.  L2, L3 managers will develop a cost and schedule that they must own and be responsible for. We will start from the MECO WBS, where relevant, and work out additional details to a level appropriate for CD process, supported by a full risk and contingency analysis and BOEs for every significant activity.  We will use OpenPlan, COBRA, WelcomeRisk, etc. as our basic set of scheduling, budget and reporting tools.

PAC Meeting - Nov Technically Limited Schedule Solenoids are the critical path. They drive the schedule.  We assume CD-0 in Feb  Finish Solenoid conceptual design in 1 year.  Final design takes 3 years. Overlaps with construction (tooling) - MECO WBS  Construction, installation, integration, testing takes almost 5 years - MECO WBS Our model for executing the Solenoid subproject will be different than the MECO model. We are looking for ways to advance the schedule. Technically limited schedule where $ and resources are available when we need them get us to Project completion in calendar 2016.

PAC Meeting - Nov Director’s Review We had a Director’s Review on September 26. The interaction with the Committee was very constructive. Charge to the Review Committee:  In preparation of the upcoming proposal of the mu2e experiment to the PAC on November 3 – 5 and in preparation for CD-0, we are appointing a team of Fermilab scientists and engineers to help us with this process. In particular we would like you to review the draft proposal to the PAC on the physics case, the proton source and beamline concept and the detector design to make a better proposal, and help identify critical R&D areas, and provide your recommendations.

PAC Meeting - Nov Director’s Review Committee Name (Organization) Rick Coleman (AD) Keith Gollwitzer (AD) Sergei Nagaitsev (AD) Vaia Papadimitriou (AD) Jim Amundson (CD) Rob Kutschke (CD) Paul Lebrun (CD) Bob Tschirhart (CD) – Chair Rich Stanek (Directorate) Brendan Casey (PPD) David Christian (PPD) Doug Glenzinski (PPD) Aseet Mukherjee (PPD) Vadim Rusu (PPD) Jim Kerby (TD) Peter Limon (TD)

PAC Meeting - Nov Director’s Review Agenda Mu2e Review – Hornet's Nest on 8th Floor Crossover 08:00 Executive Session 08:30 Physics Overview – Bob Bernstein (30 ’ +15 ’ ) 09:15 Project Overview – Ron Ray (30 ’ +15 ’ ) 10:00 Proton source, beam extraction and targeting – M. Syphers (20 ’ +10 ’ ) 10:30 Coffee Break (30 ’ ) 11:00 Muon beam transport – Jim Miller (20 ’ +10 ’ ) 11:30 Solenoid designs and procurement – Mike Lamm (20 ’ +10 ’ ) 12:00 Detector – Craig Dukes (20 ’ +10 ’ ) 12:30 Working Lunch (60 ’ ) 13:30 Review Team – Writing (75 ’ ) 14:45 Closeout / Discussion (45 ’ )

PAC Meeting - Nov Significant Quotes Space charge effects not modeled! This is a huge increase in beam [flux] (x300,000, debuncher) needed for mu2e. Get started on magnet conceptual designs ASAP! Need to develop a comprehensive MC platform that is the design tool for the experiment to determine issues such as the L vs T tracker, significance of high resolution calorimetry. Get Project Office staffed!

PAC Meeting - Nov Summary We have a conservative cost estimate that uses the MECO WBS as an initial basis of estimate. This is well in excess of the cost analysis that is typically available at the proposal stage.  We don’t expect significant cost escalation! We have a technically limited schedule driven by the solenoid system.  In reality, our schedule will be driven by funding and Lab/DOE priorities on resource allocation. We can use a strong endorsement from you to argue for more funds and resources sooner rather than later and progress more quickly.

PAC Meeting - Nov Backup slides

PAC Meeting - Nov Comparison of Mu2e and MECO Costs Total MECO cost in FY05$ - $85.3M Inflate by 15% to go from FY05$ to FY09$ (3.5%/yr)  Adds $12.6M Increase contingency to 50%  Adds $18.2M  MECO overall contingency was 23.7%. Too low by DOE standards. Does not adequately reflect risks or level of design. Add Civil Construction - New. Cost not included as part of MECO  Add $38.5M Add accelerator modifications and beamline - New. Cost not included as part of MECO  Add $21.8M Updated Project Management cost to DOE standards  Add $3.6M

PAC Meeting - Nov Comparison of Mu2e and NO A Buildings Simple scaling exercise using round numbers. Buildings are very different. NO A  ~$49.5M for building  ~34,765 sq. ft.   $1424/ft 2 Mu2e  Detector enclosure is $25.6M  ~16,500 sq. ft.   $1551/ft 2