Shepherd University WV Route 480 Pedestrian Underpass August 3, 2011
Plan Rendering of Underpass Profile Plan of Detour Schedule Sample Pictures of Other Underpasses Sample Pictures of Possible Facades Lighting Topics to Be Covered
Pedestrian Underpass Plan
View from West Campus
View from Stadium
View from Popodicon
WV Route 480 Profile
Shepherd Grade Road Profile
February 2012 Begin Utility Relocation: Water, Sewer, Storm Sewer, & Overhead Utilities March 2012 Begin Detour Construction April 2012 Complete Utility Relocation Complete Detour Construction May 2012 Close Road & Open Detour Schedule
Mid-July 2012 Complete Retaining Wall, Underpass Structure & Roadway Open Rt. 480 to Traffic August 2012 Remove Detour at Campus Drive Connect Campus Drive and Shepherd Grade to Rt.480 Complete Excavation & Sidewalks on Both Sides of Underpass Open Underpass for Student Use September 2012 Remove Detour & Restore Bavarian Inn Property October 2012 Complete Wall Restoration, Cleanup, Seeding & Closeout Schedule
Detour Plan
Underpass with Stone Formliner
Golf Course Pedestrian Underpass
Antietam Drystack Facade
Missouri Old Cut Ashlar Facade
Colonial Stone Facade
Proposed Lighting
Q&A