ISOLDE: Status report building 508 69th ISCC meeting CERN, 31 March 2014 Erwin Siesling, Magda Kowalska.

Slides:



Advertisements
Similar presentations
LS1 & Buildings 115, 507 and 601. Building 601 Building 601 (kitchen & entrance): Power has been cut and disconnected (Patrick Gallay EL) All items removed.
Advertisements

Mechanical Engineering Department  Temperature Control  Cooling  Heating  Humidity Control  Humidification  Dehumidification  Air Quality Control.
9/17/07 ILC Detectors 1 Conventional Utilities Tom Lackowski.
Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
Status Report on the TSR building (and Infrastructure) Isolde workshop CERN, 27/28 April 2015 Isolde Erwin Siesling.
The Experimental Hall Layout 2nd HIE-ISOLDE Physics Coordination Group Meeting 6 May, 2011 Hie-Isolde Erwin Siesling.
Kaj Jørgensen, Aalborg University, Department of Production and Jørn Skauge, School of Architecture Aarhus, Department of Architectural Design Building.
MPE Workshop 14/12/2010 Building 107- project Raphaël Berberat
S.M.A.R.T. Project Proposal December 9, 2014 Referendum.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
27 Feb 2012 Erwin Siesling 1 TSR Max Planck Institute Heidelberg Hie-Isolde LOI endored Jan 2011 TDR submitted Jan.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
Aristotelis Botzios-Valaskakis MSc Mechanical Engineer Division of Development Programmes Building Energy Performance Reliable Predictions ESCO’s point.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
Elevator Installation, Window Replacement, HVAC, Sprinklers, Block wall skimcoating (resident rooms & 1 st through 4 th floor resident corridors). New.
CENF target facility civil engineering specifications – summary M. Calviani (EN/STI) for the CENF-SBWG team Neutrino Platform Meeting 30 th October 2014.
1. Outline:  Introduction.  Architectural Design.  Structural Design.  Environmental Design.  Mechanical & Electrical Design.  Safety Design. 
Design of HVAC systems for bld 3862 – LHCb control room and for bld 2885 – LHCb new workshop.
PSB MPS Building 245 CV Status EN-CV-PJMichel OBRECHT – Frédéric TEIXEIRA
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
ILC experimental area - How to ‘develop’ CFS details for TDP (cavern size, number of shafts, HVAC, EL spec etc) ? - KEK site specific issues CFS V.Kuchler.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
IT-4082 Design, Supply, Installation and Commissioning of the ventilation of the BAF3 building Alexandre Broche EN-CV-PJ.
ISOLDE: Status report building th ISCC meeting CERN, 22 October 2013 Maria Borge, Erwin Siesling.
Status of renewal of Buildings 115 & 507 Borge & Erwin Siesling.
N-TOF review HVAC and cooling systems YB-JIG 15/06/07.
Physics coordinator report: Shifts 2014 Schedule 2015 Access, safety and courses b508 and 275 Magdalena Kowalska.
B508 and 275 Magdalena Kowalska. b275 2 AEGIS laser lab ASACUSA test setup g-BAR? Storage of big parts, test stands? Test setups SSP, detector labs Electronics.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Computing Facilities CERN IT Department CH-1211 Geneva 23 Switzerland t CF CERN Computer Centre Upgrade Project Wayne Salter HEPiX November.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
ISOLDE Physics Coordinator Report Schedule Access to the hall Visits b275 and b508 Magdalena Kowalska.
Computing Facilities CERN IT Department CH-1211 Geneva 23 Switzerland t CF CERN Computer Centre Consolidation Project Vincent Doré IT Technical.
The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
2 Workshop 2014 Status of the Project Klaus Blaum, MPI for Nuclear Physics, Heidelberg for the Collaboration CERN, Geneva,
ISOLDE: Status report building th ISCC meeting CERN, 24 June 2014 Erwin Siesling, Magda Kowalska.
Floor plans, Infrastructure & Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling.
Plans and schedule for the Long Shutdown LS1 SGUI CERN, 2 February 2012 Hie-Isolde Erwin Siesling.
Layout Experimental hall Final status (?) 3rd HIE ISOLDE Physics Coordination Group meeting CERN, 3 September 2012 HIE-ISOLDE Erwin Siesling.
Technical Report for the ISCC Meeting 18 th May 2009 R. Catherall/ M. Lindroos.
Fire Recovery Facilities –Physics Computing Services is finally able to relocate back into 1301 as of this week. They will probably be completely off of.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design.
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
SCX5 – Proposed New Intermediate floor over existing CMS Rack Room J.Osborne CEMESTE 20 Feb 2008.
Plans and schedule for the Long Shutdown LS1 Hie Isolde Physics Coordination Group CERN, 1 March 2012 Hie-Isolde Erwin Siesling.
Task # 3 Task # kW Target Station Layout proposal Presented by L.Bruno CERN AB Experimental Areas, Targets and Secondary Beams Group.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
Installation at Isolde (and costs) TSR at Isolde workshop CERN, 29/30 October 2012 Isolde Erwin Siesling.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
Czech Technical University in Prague, Jan TYWONIAK, Kateřina SOJKOVÁ Additional Installation of Mechanical Ventilation in a Campus.
Update on the PSB Cooling and Ventilation Systems
CMS Centre Project - Green Light Meeting
I. Bergevoet - Training preparation
SR1 extension follow up 27-Mar-17 Marco Ciapetti.
St. George Infrastructure
Uppsala Commitment to ESS and FREIA Planning
Target and Horn status report
Magdalena Kowalska, CERN PH-SME-IS
ISA Prime Developments
User Facilities 2016 Users Group Board of Directors Update
Maintenance at ALBA facility: Strategy for the conventional services
Mount Vernon Community School
Presentation transcript:

ISOLDE: Status report building th ISCC meeting CERN, 31 March 2014 Erwin Siesling, Magda Kowalska

2 Outline Status new building 508: –Progress on the construction –Building layout (final) –Progress on infrastructure –Costs and timeline

3 New user facilities building 508 (replacing 507, 115, 601) Target zone and separators area ISOLDE experimental hall Reserved for TSR 508 New ISOLDE Control Room, 1 st floor 508 Present ISOLDE Control Room, basement 197 water station New building 508

4 Progress Progress during the winter: -Preparation of the terrain November -Pouring of the concrete floor (with disconnected workshop floor) December -Installation of the metal structure Feb-March -Installation of the isolated walls March -Ongoing: Installation of the windows and doors & inner walls

Building Layout Building 508 layout: Light metal structure with 2 concrete floors: Total surface 864m2 Ground floor (only accessible from within the classified area): 432 m2 - Solid state, Laser labs and workshop First floor (accessible outside the classified area): 432m2 - Data Acquisition rooms - Meeting room/Visitors Center - Kitchen - Isolde Control Room

6 Layout 508 Ground floor B508: Controlled Access ground floor and Isolde hall Access 1 st floor

7 Layout 508 1st floor B508: Access 1 st floor Courtesy Eliseo Perez-Duenas GS/SE

8 Infrastructure 508 Infrastructure: -Needs for the users have been collected by Maria and Magda -Implementation by the different groups and contractors ongoing (EL, CV, IT) -Finalized plans with regard to infrastructure to be ready asap (Urgent!) Courtesy Magda Kowalska

9 Infrastructure 508 Electricity: - Latest iterations user needs: 200kW - Waiting for estimate of Cooling& Ventilation needs: 130, 170, or 220kW

10 Infrastructure 508 Cooling and ventilation: -The proposed solution by the contractor contains two HVAC (Heating Ventilation and Air Conditioning) systems based on a refrigerant liquid: -General system for the whole building + Technical cooling for the ground floor labs => too expensive and requires new electrical design (=delays), suggestion: -Keep general system for the building as proposed -Technical cooling: Re-use available chilled water and install fan-coils; 4x7kW fan- coils (1 SSP, 2 COLLAPS, 1 CRIS) as used before in B507 Status: waiting for a price estimate

11 Costs: Total costs building 508 (incl. services): estimate 2MCHF Exact costs HVAC awaiting Timeline: -Building ready April Infrastructure ready June Installation controlled access June Installations users as of July 2014 (Move of the ICR during shutdown 2014/15) -Milestone: Protons to Isolde 10 July 2014; physics start 21 July Costs and Timeline