Purpose of Work Shop Share Ohio’s experience with a full closure reconstruction: the rationale, challenges, implementation and benefit.

Slides:



Advertisements
Similar presentations
Capital Beltway HOT Lanes Project Project Update March 2009.
Advertisements

Capital Beltway HOT Lanes Project Project Update April 2009.
New York State Department of Transportation Region 11 Reconstruction of Jamaica Avenue Bridge over I-678 Van Wyck Expressway The Roll-in/Roll Out Method.
Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.
Ohio QuickClear Ohio Fire Chiefs' Association Annual Conference
Retroreflectivity: Raising the Nighttime Brightness of Traffic Signs and Markings Office of Technology Applications Peter Hatzi.
Construction Communications. Communication is an expectation Inform our customers about improvement projects Raise awareness of: Construction zone locations.
Chapter 12 Freeway Driving.
I-96 Reconstruction/Bridge Repair Project City of Livonia and Redford Township Wayne County May 10, 2013 Association of the Council of Western Wayne Yankee.
CEM-512 Value Engineering Highway Project: South Interchange.
Capilano Road Improvement Project WELCOME TO THE OPEN HOUSE.
Project Construction Update August 30, 2011 I-5 North Stockton Freeway Widening and Pavement Reconstruction Project Between Dr. Martin Luther King Jr.
August 18, 2011 State Route 99 Auxiliary Lanes Project Route 32 to East 1st Avenue.
I-10 Exercise. Project Description Current and anticipated congestion due to rapid growth, one lane in each direction will be added to Interstate 10 from.
LANE CLOSURE CHARTS CHART DEVELOPMENT AND DELAY DAMAGES (District 3) OBJECTIVE To become familiar with the lane closure chart development process.
1 Corey W. Hill Chief of Public Transportation May 20, 2008 May 20, 2008.
S.R. 256 Road Reconstruction Project From City of Austin to S.R. 203 Thursday, February 6, 2014 Austin Elementary School 6:00 p.m.
North Carolina’s Integration of 511 and Workzone Information Jo Ann Oerter State Technology Implementation and Maintenance Engineer North Carolina Department.
The North Carolina Department of Transportation. An 11.5-mile stretch of a major highway in Raleigh is in dire need of repair after a construction problem.
Ramp Metering Pilot Project May 11th, 2010 E. Jason Sims, P.E. Kansas City Scout TMC Manager.
Introduction Transportation System Objectives : Military; Knit together the inhabitants of a territory by providing mutual access and communication; Economic.
Detours – Selection and Design Highways & Engineering Conference March 2, 2006.
Bridge Rehabilitation W Interstate 290 over CSX Railroad and 4 City Streets I-290 Viaduct Reconstruction.
Phoenix International Raceway (PIR) Presented By: Nicolaas Swart Traffic Engineering & ITS Program Manager Maricopa County DOT April 26, 2006 Presented.
MAINTENANCE & TRAFFIC OPERATION INCIDENT MANAGEMENT.
Determining Innovative Contracting Methods to Reduce User Costs Stuart Thompson Utah Technology Transfer Center.
Schools Jobs Revenues Services Recreation Environment Transportation Transportation Connectivity Housing Public Safety Pontiac’s.
Expressway Driving. Characteristics of Expressway Driving Roadway Speed Interchanges No cross traffic Median Tollbooths Entrance/exit ramps Limited access.
Illinois state line to Madison Dane and Rock County
Page 1 MINISTRY OF TRANSPORTATION Cyrville Road Bridge Replacement at Highway 417 (Ottawa Queensway) Detail Design Study Group Work Project
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation.
Alameda Creek Bridge Replacement Scoping Meeting March 4, 2014.
1 Dixie ITS Architecture Study Section ? Utah ITS History.
Fast Forward Full Speed Ahead Presented at the Joint ITS Georgia / Tennessee Annual Meeting September 25, 2006 by Carla W. Holmes, P.E., PTOE Georgia Department.
© 2014 HDR, Inc., all rights reserved. COUNCIL BLUFFS INTERSTATE SYSTEM MODEL Jon Markt Source: FHWA.
TEA, Portland, Maine Travis Koestner Missouri Department of Transportation October 20, 2006 Alternate Paving Update $$ Cost Control at MoDOT $$
Incident Management in Central Arkansas: Current Settings and Proposed Extensions Weihua Xiao Yupo Chan University of Arkansas at Little Rock.
WSDOT SW Region, Vancouver, WA December 7, 2009 WSDOT SW Region, Vancouver, WA December 7, 2009 Tolling Study Committee.
July 29, 2009 George Saylor, PE ODOT Senior ITS Engineer.
Project Scoping Fundamentals Alan Lively Project Delivery Specialist Local Government Section April 6, 2010.
TRANSPORTATION ENGINEERING Planes, Trains, Automobiles and More Ardrey Kell High School February 23, 2012.
PROJECT SCOPING FOR LOCAL AGENCY FEDERAL AID PROJECTS.
Managed Lanes CE 550: Advanced Highway Design Damion Pregitzer.
Office of Traffic, Safety and Technology Module 4 Work Zone Applications Traffic Control Plan Development Course.
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
1 Some Findings on Public Outreach for Work Zones.
FULL FREEWAY CLOSURES RECENT SUCCESS STORIES IN KENTUCKY.
Materials, Pavements & Transportation Operations CONCEPTS FOR ENHANCING THE EFFECTIVENESS OF TRAFFIC CONTROL PLANS Stuart Anderson Gerald Ullman Making.
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Public Information Meeting.
1 Using Intelligent Transportation Systems (ITS) Technologies and Strategies to Better Manage Congestion Jeffrey F. Paniati Associate Administrator of.
Regional Concept of Transportation Operations: The Hampton Roads Experience Presented by: Camelia Ravanbakht, PhD Talking Technology & Transportation (T3)
The BIG DIG Team Summit Topic Presentation April 19th, 2005
Corridor Congestion Management Innovation for better mobility sm.
THE EL MONTE HOV / BUSWAY: A Policy Driven Experiment in Congestion Management Frank Quon Division of Operations Deputy District Director HOV LANES IN.
Transportation Operations Group Designing for Speed, Congestion, and Delay in the Work Zone Gerald Ullman Research Engineer Texas Transportation Institute.
TEAM Presentation January 21, Overview Top MoDOT Priority Top MoDOT Priority A Funding challenge A Funding challenge Desperately needed Desperately.
INCORPORATING INCOME INTO TRAVEL DEMAND MODELING Brent Spence Bridge Case Study October 13, 2015.
Briefing for Transportation Finance Panel Nov 23, 2015 Economic Analysis Reports: 1.I-84 Viaduct in Hartford 2.I-84/Rt8 Mixmaster in Waterbury 3.New Haven.
I-66 Corridor Improvements Morteza Farajian Interstate 66 Corridor Improvements From US Route 15 in Prince William County To Interstate 495 in Fairfax.
Transportation Systems Management and Operations: Why It Matters Presenter Name Date AGENCY LOGO Photo: © Shutterstock.com/iofoto ( )
Comprehensive Highway Safety Plan Leadership and Management Getting buy in … Getting started … Managing the process …
Intelligent and Non-Intelligent Transportation Systems 32 Foundations of Technology Standard 18 Students will develop an understanding of and be able to.
Unit 2 DEVELOPMENT OF THE LONG RANGE TRANSPORTATION PLAN (LRTP) LCTCC Educational Program.
STAFF’S FINDINGS OF INCONSISTENCY Section 30233(a) Wetland Fill Staff’s basis for denial centers on the determination if the project meets the incidental.
I-5/Genesee Avenue Interchange Project. Project Purpose Improve east and west traffic flow on Genesee Ave. Enhance access to and from I-5 Replace and.
MPO 100 Presented by Erica Tait. What is an MPO?  MPO stands for Metropolitan Planning Organization  Mandated by the federal government for urbanized.
TH36 Closing Options Study Presented by: Market Research March, 2006 Maps from Google.
The I-465 West Leg Reconstruction Project
Florida Transportation Commission FY 2009
Fortify: The I-40/440 Rebuild Project
Presentation transcript:

Purpose of Work Shop Share Ohio’s experience with a full closure reconstruction: the rationale, challenges, implementation and benefit

Background Statewide interstate reconstruction effort underway in Ohio to rebuild aging, heavily traveled highways and make them safer for 21 st Century traffic. ODOT is looking for creative ways to repair these roads while minimizing the negative impact to our customers

Interstate 670 When originally built during the ’60s, the 1.7 mile stretch of urban highway was considered state of the art. However traffic long outgrew the original design making it difficult to navigate and a high-accident location

Map of SSI Projects

Project History I-670 segment one of 15 projects worth $225 million to rebuild and redesign the downtown Columbus innerbelt and complete the missing link in Ohio’s interstate system.

More History … The work stalled for decades due to environmental regulations, lawsuits and lack of funding. Work began on the projects during the early ’90s using operating-cost savings from ODOT. Today only two projects remain.

Benefit When the work is completed in the fall, motorists will be able to travel directly from the west to east side of Columbus on a newer, safer, wider highway.

Why Full Closure? Given the long history of the project, ODOT and Columbus eager to complete remaining projects quickly ODOT could cut construction schedule by more than half using full closure vs. part- width

Project Scope Reconstructing and building new 1.7 miles of urban freeway including 21 bridges and 10 ramps Cost: $50 million Highway tightly bordered by historic neighborhoods, convention center and emerging business and arena districts

Existing Condition Two narrow lanes in each direction with little shoulder area Geometric deficiencies: sharp curves, short merge areas and ramps spaced too close Disrepair: crumbling concrete on bridges, medians and shoulders, rough road surface

Pix disrepair

Why Full Closure on I-670 Cut Construction from 4 years to 18 months Reduce the potential for accidents Worker Safety (difference in elevation) Reduce Driver Confusion Better Quality and Reduced Cost Experience with Full Closure (SR 315)

Process To pursue a full-closure approach, ODOT had to gather the facts and “build the case,” then present the information to key decision makers for support.

Analysis Traffic – where will the traffic go? Can the system support it? User Delay Costs – closing vs. maintaining traffic Life-cycle costs

Building Support Once we gathered the data, we had to “sell” the idea to key decision-makers. Mayor and Local Public Officials ODOT Executive Leadership Public Support was relatively easy to come by given the clear benefits.

Implementation Enacting the closure was easy. One week of prep for signs One day to close (weekend) Two weeks of traffic monitoring (Field, TMC and LEOs)

Public Outreach The hardest part of the full closure is the outreach needed to prepare the public. This effort began about six months in advance and continued at a steady pace leading up to and after the closure. It also involved the public relations AND construction staff.

Key Audience Motorists Businesses Residents Public Officials/Opinion Leaders Emergency Responders Schools Media

Type of Communication Fact Sheets Custom Flyers for nearby businesses Web site ( Group and One-on-One Presentations Media (pitched various news angles) Government Channel Updates – progress reports and traffic info

Key Messages Benefits of work (new, safer, wider highway, direct connection, completes interstate, design enhancements) Efforts to minimize construction delays (4 yrs to 18 mos, incentives/disincentives) Alternate Routes and Commuting Strategies

Construction Progress Work is currently 2/3 complete and on-time thanks to: $20,000 per day Liquidated Savings High-community profile Contractor has unrestricted access to work site

Would you use the full closure again? Yes! ODOT’s experience has been positive and we would use a full closure again under the right conditions.

Right Conditions Small section of roadway Tight physical constraints Variety of good alternate routes Clear public benefit “Building the case” and communicating the benefits is key!

Future Contracting Innovation Increasing public demand for less work zone congestion and the success of innovative projects have given ODOT the courage to try new techniques. Innovative Contracting Policy Fast Track Bridge Construction

QUESTIONS?