1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
LHC Beam Dumping system
1 MKBH Erratic Jan Uythoven On behalf of the ABT team (Viliam, Nicolas M., Etienne, Laurent, Francesco etc…..) MPP meeting 8/5/2015.
Failure mode impact studies and LV system commissioning tests
LBDS Kicker Electronic and Slow Control Etienne CARLIER AB/BT/EC.
09/16/2010© 2010 NTUST Today Course overview and information.
Time Response of Reactive Circuits
LHC Beam Dumping System Status and Readiness for LHC Run II Evian Workshop 2-4 June 2014 Nicolas Magnin – TE/ABT/EC On behalf of TE/ABT team. Thanks to.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
“we believe the reason why the first bunch is more intense than the following 3 is that it's on that one that the SPS RF loops are locked” Philippe & Django.
1 Flux concentrator for SuperKEKB Kamitani Takuya IWLC October.20.
LBDS Audit Follow-up Jan Uythoven Thanks to: Etienne Carlier and Brennan Goddard 1.
1 Beam Plans for Accelerator Systems: The Machine Protection System Jan Uythoven On behalf of the MPWG and the MPS Commissioning WG Special thanks to R.Schmidt,
Etienne CARLIER, LBDS Audit, 28/01/2008 LBDS Environmental Aspects EMC, radiation, UPS… Etienne CARLIER AB/BT/EC.
What will we do for Beam Preparation: Injection and Beam Dump Jan Uythoven Thanks to M.Barnes, E.Carlier, L.Ducimetière, B.Goddard, R.Jones, Y.Kadi, V.Kain,
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
1 Reliability and Availability of the Large Hadron Collider (LHC) MachineProtection System Jan Uythoven CERN, Geneva, Switzerland Thanks to R. Schmidt,
MKD Reliability run Viliam Senaj TCM meeting 18/11/2014.
MKD dust related actions Viliam Senaj Technical Coordination Meeting 27/01/2015.
1 Will We Ever Get The Green Light For Beam Operation? J. Uythoven & R. Filippini For the Reliability Working Group Sub Working Group of the MPWG.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
Sketching Basic Kicker System Parameters W. Bartmann, T. Fowler, B. Goddard, T. Kramer.
LMC 27 November 2013 Status of LBDS LS1 activities and plans for 2014 reliability run Jan Uythoven for the many, many people working on the mentioned equipment.
LHC Beam Dumping System Experience from reliability run and Re-commissioning procedures MPP Nicolas Magnin – TE/ABT/EC.
Overview WP14 Developments Hardware  Interferometry on the spare TDIs, planned to be installed Christmas stop 2015/2016. Final acceptance tests ongoing.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
TRIGGER DELAY 100µs. G. Gräwer AB/BT/ECLBDS Trigger Delay2 The trigger delay is a back-up system that generates an asynchronous dump trigger for MKD and.
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
1 Run7 startup M. Sullivan MAC Review Nov , 2007 M. Sullivan for the PEP-II Team Machine Advisory Committee Review November 15-17, 2007 Run 7 Startup.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Commissioning / Reliability Runs / Dry runs 1 Jan Uythoven, LIBD meeting on LBDS Reliability Run 04/02/2014 Nov – Dec 2013 Commissioning individual MKDs.
LBDS MKD tracking related problems. Outline tracking problems: Exchange of MKD compensation/principal PS Same BETS limit for all generators.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Electrical Current & Circuits. Components of an electrical circuit Source of electrical energy (battery) A conductor of electrical energy (wire) Device.
Readiness for RF capture Cavities – all 16 cavities commissioned with RF feedback loops closed klystron polar loop still to commission on 2 cavities 2.
PSB extraction and transfer kickers LIU TE-ABT review, 20 November L. Sermeus.
Session 8: What we will do for beam preparation in 2009 G. Arduini, R. Giachino 1Session 8 – Summary - GA24/02/2009.
LBDS YETS activity report Viliam Senaj MKD meeting, 19/01/2016.
The Survey of the Power Supply Reliability at SSRF
Data providers Volume & Type of Analysis Kickers
Dependability Requirements of the LBDS and their Design Implications
Minimum Hardware Commissioning – Disclaimer
The LHC Beam Dumping System
Fast retrigger path What threshold level we need for the fast trigger path?
Proposition of MKD & MKBH modification with the goal to reduce maximum voltage (and risk of erratic) Viliam Senaj, 05/05/2017.
LHC beam dump 7.56 TeV operation
LHC Beam Dumping System Reliability Run Summary
MKD/MKB Review Meeting Scope and Definition
Jan Uythoven For discussion
Viliam Senaj MKD meeting 23/05/2017
J. Uythoven for the MPE-MI & MS Teams
1v0.
LHC Risk Review: Kicker Magnet Reliability
FCC hh dump kicker - switch topologies and impact on beam
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Beam Dumping System and Abort Gap
Dry Run 0 Week 13: BI test of...everything circulating beam: all fixed displays and BI applications OP directories for 2009, concentrators running Need.
Sunday/Monday & :30 Stable beams. Fill #1851.
Machine Protection System Commissioning plans
Will We Ever Get The Green Light For Beam Operation?
Jan Uythoven For the LBDS Team
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Hardware Commissioning
Review of hardware commissioning
Presentation transcript:

1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections

Jan Uythoven, AB /BT LBDS Audit, 28 January Outline MKD and MKB Systems Testing before installation Calibration in the laboratory Testing in the machine Calibration Reliability run Testing of the complete LBDS System From local operation to running the complete system from the CCC Conclusions

Jan Uythoven, AB /BT LBDS Audit, 28 January Calibration in the Laboratory before Installation MKD: 2 x 15 Magnets 2 x 15 Generators + 2 x 2 Spares MKBH: 2 x 6 2 MKBV: 2 x metal coated ceramic chambers: partly calibrated! Inductive field probe !

Jan Uythoven, AB /BT LBDS Audit, 28 January Why Calibration? MKD and MKB Systems Calibration of individual components Test all magnets with the same reference generator Test all the generators with the same reference magnet Test some of the ceramic chambers (different resistance of the coating) on the same magnet and the same generator Determine the relation between measured field and current Precise measurements of the magnet and generator performance gives: Quality assurance Find the “bad” magnets / generators and fix them, measure again and see if its better  Weak components were detected and replaced during the calibration process Critical parameters determined Method for the analysis of current waveforms developed  Later used by IPOC and XPOC Comparison with specification / design  Just ok on rise time and overshoot For MKD determination of individual trigger voltages as function of ‘beam energy’  Necessity ‘discovered’ during the calibration process Used for sorting and assigning equipment positions in the LHC

Jan Uythoven, AB /BT LBDS Audit, 28 January Results: Some MKD Calibration Results

Jan Uythoven, AB /BT LBDS Audit, 28 January MKBH Calibration Results

Jan Uythoven, AB /BT LBDS Audit, 28 January Measurements once installed in Tunnel Repeat same calibration measurements in tunnel Comparison of Reference Measurements Example for measured Pulse Length Typical MKD generator Pulse length comparison calibration hall and two measurements in tunnel Measurement of pulse which is too short and continues to become shorter: Compensation capacitor replaced

Jan Uythoven, AB /BT LBDS Audit, 28 January Results XPOC over Several Weeks of Running (25/11/07 to 12/01/08) 15 MKD systems, beam 1, at 2 TeV Downwards trend on Amplitude not understood Pearson transformer Hysteresis Comm. of Rogowski trans. Capacitors Temperature effects Pulse length: replaced capacitors 100 % point, relative [%] End point, after 91  s [%] Overshoot 2 [%] OverShoot 1 [%] Compensation capacitor replaced

Jan Uythoven, AB /BT LBDS Audit, 28 January Reliability Run A testing policy can be applied to 2x15 MKD generator branches per LBDS, 60 in total, in order to accept or reject the hypothesis that they are SIL3 at least. The test considers the branch failures only and not the system failure. A test of three months with 1 hour missions ensures that the system is SIL3 or better at 95% confidence level if less than 6 generator branch failures are observed. MKD SIL3 Decision threshold Failures for a 3 months test is the assumed failure rate of one generator branch in order that MKD system is SIL3 Failure rate Observed failures Started running in November So far no failures detected !

Jan Uythoven, AB /BT LBDS Audit, 28 January Energies Used during Reliability Run Philosophy is 12 hours stable at 7 TeV settings followed by one pulse, and series of 5 pulses at different energies (average ~ 1/hour). Always following realistic ramp rates.

Jan Uythoven, AB /BT LBDS Audit, 28 January System Commissioning Connect up to non MKD – MKB equipment. Add equipment when they become available Timing – Beam Interlock System (BIS) To be done in the coming weeks, as LBDS – BIS is a safety critical link Close BIS loop locally in point 6 MSD: ramp synchronously with MKD/MKB TCDQ: position to follow ramp Beam Instrumentation (XPOC) RF (synchronisation) Q4 – possibly run in short circuit when magnet not cold Main dipoles for BEM: connect when cold and available Once connected up to the BIS, running from the LHC Control Room Test as much of the equipment as possible Operator experience with the LBDS equipment First tests to start in two weeks

Jan Uythoven, AB /BT LBDS Audit, 28 January Conclusions For the MKD and MKB systems standard, precise measurements have been made before installation and, once installed, during ’continuous’ pulsing They have been successfully used to detect weak components during initial testing and also for one generator once installed They will also be used for the IPOC and XPOC analysis Today, the systems have been pulsing for several weeks as part of the reliability run No failures detected so far. Would expect about two failures on the switches, according to dependability model. Some trends are observed which are not yet fully understood No risk to safety, as trends are slow and captured by the pulse analysis Reliability run ongoing for the coming months, in parallel with other works System commissioning starting in two weeks