Presentation is loading. Please wait.

Presentation is loading. Please wait.

The LHC Beam Dumping System

Similar presentations


Presentation on theme: "The LHC Beam Dumping System"— Presentation transcript:

1 The LHC Beam Dumping System
This talk: Design and Safety of the system System requirements System description, interface to other systems Details on technical solutions chosen – effect on safety Operational procedures – effect on safety Expected availability of the system Next talk: Failure scenarios and dedicated protection devices of the beam dumping system (B. Goddard) Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

2 Beam Dumping System, MPS review, 11 – 13 April 2005
System Requirements Loss free extraction of one or both beams from the LHC onto an external absorber Fast extraction kickers and septa > 89 s extraction kicker flat top length: 1 LHC turn System must be SAFE: “Always” available “Always” adjusted to the correct beam energy (see talk E. Carlier: ‘Safe Beam Energy Tracking’) Abort gap without beam, for extraction kicker rise time, of 3 s Synchronisation to abort gap from RF Abort gap monitoring: similar system foreseen as in Berkeley (S. Hutchins) If necessary: abort gap cleaning (see talk W. Höfle: ‘Transverse Damper’) Dilution of the beam on absorber block Dilution kicker magnets Long dump lines between dilution kickers and dump block Maximum 3 turns delay between IL generation and beam dump (this includes delay due to beam interlock system) System must be available: not too many aborted fills due to beam dump Safe or “Always” … see  Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

3 System Requirements: Safety of the System
Safety: always be available No missing beam dump request No ‘bad dumps’ Requirement on the complete Machine Protection System is SIL 3 (see introductory talk R. Schmidt) Failure rate between 10-7/h and 10-8/h For 4000 hours of operation per year this means Mean Time to Failure > 2500 years The Beam Dumping system should contribute to this overall number in a balanced manner with the other elements of the MPS (BIS, BLMs etc.): it should not be the critical system See talk R. Filippini: ‘Will the Machine Protection System let the LHC Safely Operate’ Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

4 System Description Main Elements
TDE dump block 10 x MKB kickers DILUTION 15 x MSD septa Q4 Kick enhancement TCDS protection TCDQ protection 15 x MKD kickers EXTRACTION Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

5 Beam Dumping System, MPS review, 11 – 13 April 2005
Tunnel Layout 40 m Total length of ‘dumpline’ : 975m from kicker MKD to dump block TDE Dump cavern IP Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

6 Beam Dumping System, MPS review, 11 – 13 April 2005
Extraction of the beam 15 magnets, tape- wound C-shaped steel cores, with 15 generators (MKD): deflection in the horizontal plane Extraction can take place with either 14 or 15 magnets Nominal extraction angle with 15 magnets: mrad 30 % kick enhancement by standard quadrupole (Q4) Deflection in the vertical plane by 15 septa (MSD) System deflection angle: 2.4 mrad Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

7 Beam Dumping System, MPS review, 11 – 13 April 2005
Extraction kicker MKD Prototype magnet Strip-wound Core Conductor Ceramic vacuum chamber Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

8 Measured Extraction kicker Pulses: According to Design
Calibration of series magnets, ceramic chambers and generators: Overshoot: Individual magnets < 7.5 %; System < 10 % Rise time: Individual magnets < 2.8 s; System < 3.0 s Pulse length: More than 90 s MEASRUE effect of metalised ceramic chamber on absolute integrated magnetic field strength, overshoot, delay between current and magnetic field Measurement with calibrated, fast inductive probe Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

9 Vertical Extraction Septum MSD
15 units (3 types) per beam Laminated iron-dominated magnets Three different families: Different distance between apertures Different number of coil layers Positioned back to back for the two beam Total of 2.4 mrad (V) Circ. Chamber to 250ºC One power converter per beam Magnet coil Extracted beam Vacuum chamber Circulating beam Vacuum chamber Laminated yoke Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

10 Beam Dumping System, MPS review, 11 – 13 April 2005
Dilution of the Beam 10 modules of dilution kickers magnets with individual generators (MKB) Similar C-shaped steel cores as the extraction kickers MKD and similar generator technology In vacuum tank, no ceramic chamber System deflection each plane: ± 0.28 mrad Sinusoidal pulse shape 4 Magnets in the horizontal plane 6 Magnets in the vertical plane Initially only two in each plane Limit beam current to half nominal V H Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

11 Beam Dumping System, MPS review, 11 – 13 April 2005
Beam Dump Figure ds between consecutive bunches, 25 ns apart Minimum velocity  10 mm/s Dilution failures discussed in next talk Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

12 TDE Dump Block 0.7 m and 3.5 m of Graphite, 1.73 g/cm3 density Steel cylinders under N2 overpressure. No water cooling; forced air flow around cylinder. Monitor N2 temperature. 3.5 m of Graphite with 1.1 g/cm3 density  0.7m  7.7 m C cylinder 1 m Al, 2 m Fe 900 T of radiation shielding blocks Design such that no structural damage to be expected during 20 years of operation with ultimate LHC intensities Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

13 Beam Dumping System, MPS review, 11 – 13 April 2005
Beam Instrumentation BLMs BPM Position Interlock BPM Plus: – 2 BCTs per line at MKB – 4 screens (OTR) per line at MSD, MKB, (TD), TDE Used for System Post-Mortem Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

14 Beam Dumping System, MPS review, 11 – 13 April 2005
Functional Diagram Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

15 Safety Calculations of the System
Operational scenario Assume 200 days/year of operation, 10 hours per run followed by post mortem, 400 fills per year Systems includes MKD generators, magnets, electronics, beam energy tracking (assumptions), survey system, (re-)triggering system Not included: Septa, Q4, MKB, TDE Failure rates Assume constant failure rates Calculated in accordance to the Military Handbook 217F Others The system may fail only when it operates It cannot be repaired if failed unsafe  GAME OVER Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

16 Resulting Numbers Availability over one year: False dumps distribution per year: average 2 x ( 2.6 ± 1.6 ) Unsafety per year ( 400 missions): 2 x 1.4 10-7 Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

17 Gains in Safety due to Specific Design Features
Correct functioning with 14 out of 15 magnets If no redundancy on number of extraction kickers: Unsafety number of 1.4  10-7/year becomes 0.01 year Critical element is the extraction kicker magnet and its connectors No online surveillance before pulsing Assumed conservative failure rate of 2  10-7/h Stack of solid state switches GTO-stack failure rate 1.4  10-9/h (fail open), much better than gas tubes (thyratrons) Triggering and re-triggering of the system All trigger lines are doubled and ‘crossed’ Re-triggering: if a MKD switch closes it will automatically re-trigger all other MKD & MKB systems. Also adds as back-up for the normal trigger system Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

18 (Re-)Triggering Circuit
Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

19 Double branch extraction kicker generator
Main capacitors in parallel Main switches Comp. circuit Single branch generator would result in system unsafety of 2.4  10-6/year (instead of 1.4  10-7/year) Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

20 Safety Design Features, continued
System settings according to Beam Energy Self-surveillance (BET), see talk E.Carlier Redundant online monitoring of charged capacitors in the generator. Also online monitoring of the extraction septum and Q4 current with fast interlock system (supplementary to the power converter interlock). Without surveillance of the powering system of the extraction kickers (BET system) unsafety of the beam dumping system becomes 2.2  10-3/year (instead of 1.4  10-7/year ) Even though redundancy of the number of extraction kicker system allows for the wrong powering of one extraction unit ! Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

21 Operational Procedures
Beam dump system ‘post-mortem’ After every dump request the beam positions in the beam dump line and the beam dump figure will be analysed Also comparison of total current in the ring and in the beam dump lines and beam loss monitor readings will be checked After every dump request the redundancy of the trigger lines and double branches in the generators is verified Only if this is correct, beam is allowed in the LHC with a system which is assumed to be ‘as good as new’ Unsafety without post-mortem would be 5.4  10-5/year (instead of 1.4  10-7/year ) Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

22 Commissioning and Maintenance
After the equipment commissioning a three month ‘reliability run’ of the complete system is foreseen Find teething problems of the system Find bottom of ‘bath tub curve’ Confirm numbers for safety and availability Maintenance procedures will be defined Based on post mortem results and lifetime cycles of equipment components UPS system included Safe beam dump in case of power cut is designed into the system. The main energy is stored in the capacitors within the generators Power cut scenarios will be tested during the system tests Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005

23 Beam Dumping System, MPS review, 11 – 13 April 2005
Conclusions Safety inherent in design, due to: Redundancy Surveillance System post mortem Operational procedures Detailed quantitave safety analysis has been made Acceptable results Acceptable availability numbers Acknowledgements: The many people working on the beam dumping project. Jan Uythoven, AB/BT Beam Dumping System, MPS review, 11 – 13 April 2005


Download ppt "The LHC Beam Dumping System"

Similar presentations


Ads by Google