Status Report of activities in LNF Soldering procedure 1.Status of soldering machine 2.Measurement of wire position Chamber prototypes 1.Construction of.

Slides:



Advertisements
Similar presentations
Status of test beam data analysis … with emphasis on resistive coating studies Progress and questions 1Meeting at CEA Saclay, 25 Jan 2010Jörg Wotschack,
Advertisements

Muon EDR: Chamber design M2/3 R1/2 16/04/20031T.Schneider/LHCb Muon EDR 1.General description - AW read out -Cathode pad read out -HV supply 2.Details.
Technical Board, 12 July 2005Børge Svane Nielsen, NBI1 Status of the FMD Børge Svane Nielsen Niels Bohr Institute.
sTGC for ATLAS Small Wheel upgrade
Status Update on Mechanical Prototype in Rome November 6,
Status of the LHCb RPC detector Changes with respect to Note cm strips instead of 3 cm (cost optimization) All gaps same size (standardization)
PNPI in LHCb A.Vorobyov HEPD Scientific Board meeting, December 26,2003 Status report for 2003.
TRD Status meeting GSIClemens Adler Chamber production Production status/ Material status.
Fiber Bragg Grating (FBG) Sensors For Micromegas
CERN PH/DT 30/01/14 Francisco Perez Gomez CERN PH/DT.
Large-size micromegas for ATLAS (MAMMA) Status and prospects RD51 mini week, 17/01/2011Joerg Wotschack (CERN)1.
Production Readiness Review of Frascati MWPC Production Site December 4 th, 2003 – P. Campana.
June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R.
LHCb MUON MPWC STATUS OF TOOLING, SITES, PRODUCTION AND MATERIAL PROCUREMENT.
BANDGEM Demonstrator: conceptual design and state of the art.
G. Martellotti CERN 22/04/20021 Tooling / Test Stations for MWPC (Meeting LNF, Roma1/Pz ) Production rate : 408 chambers (Fe + LNF) :192 R4 M1.
G.Bencivenni LNF/INFNMuon Meeting 21-October-2002 Status Report on triple-GEM detector M.Alfonsi 1, G. Bencivenni 1, W. Bonivento 2,A.Cardini 2,C. Deplano.
Atsuhiko Ochi Kobe University 25/06/2013 New Small Wheel MicroMegas Mechanics and layout Workshop.
Mickael Frotin– 07/06/2009 Demonstrator - Assembly ECAL meeting - London.
Status of CERN M1R2 production LHCb Muon meeting sept.061Thomas Schneider -Beginning of 2006 two visits to Erbicol because of several reasons: -Material.
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
Tracker QA Paul Kyberd Quality Assurance A status report: A procedure for ensuring the quality of the finished tracker has been designed following our.
M. Alfonsi LNF/INFN Cagliari 5 May 2006 M1R1 mechanical requirements  Space constraint Frame and pannel Pads readout and trigger sectors Gas inlet and.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
Production Readiness Review Production steps and quality control 1.Panel production 2.HV bar gluing 3.Preparation of side material 4.Wiring and gluing.
Calliope ENEA Casaccia MON = monitor MWPC (CH1) T1 = test MWPC (CH3) T2 = test MWPC (BTF,CERN1,CERN2) T = temperature sensor P = atmospheric.
First results of an aging test of a full scale MWPC prototype for the LHCb muon system Workshop on “Aging Phenomena in Gaseous Detectors”, October 2-5.
T.Schneider/LHCb Muon EDR
September 9, 2003A. Cardini / INFN Cagliari1 M. Alfonsi 1, G. Bencivenni 1, W. Bonivento 2, A.Cardini 2, C. Deplano 2, P. de Simone 1, F. Murtas 1, D.
Status of production at LNF E. Dane, C. Forti, D. Pinci, A. Sarti – LHCb Muon CERN 25-may-04 Monday 24-may: closed chamber 30. Will close 2 more this week.
MWPC sandwich panels C.Forti INFN-LNF / LHCb-MUON EDR CERN 16 th April sandwich panels typologies of cathodes the mould the production procedure.
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
Status of RICH mechanical design at PNPI E.Vznuzdaev for PNPI group: V.Dobyrn, A.Khanzadeev, E.Kormin, V.Lebedev, N.Miftakhov, V.Polyakov, V.Samsonov,
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
Assembly Procedure ALICE Outer Barrel Stave 14 Module 2 Cold Plates 1 StaveMarco Kraan Paul Kuijer.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.
Panel production status Panels needed according to official plan Oct-05 A rate of 250/month is mandatory to match the chamber production schedule.
Total Cross Section, Elastic Scattering and Diffraction Dissociation at the LHC January 17, 2003TOTEM plenary meeting -Marco Bozzo1 CSC detectors for T1.
Hybrid panel heated plate study Currently the curing of the ASIC glue for the hybrid panels are done at room temperature. This is a study to determine.
CERN adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of Production of support panels - Things to be settled.
Plans for MPGD Radiation hardness tests for full detectors and components Matteo Alfonsi,Gabriele Croci, Elena Rocco, Serge Duarte Pinto, Leszek Ropelewski.
Production Readiness Review at PNPI Chamber assembling: Main production and quality control steps 30 January 2004 – G.Alkhazov 1.Input components control.
22/04/20011Wire Chamber Working Group Status on O-ring closed Prototype Foam panels from Frascati (size: 279mm*341mm) No pad structure 4 independent gas.
Muon Meeting April 2004JsG Status of Chambers Production at CERN Jean-Sebastien Graulich o Open Questions from the PRR O-ring Aging, Aging tests, Storage.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
Radioactive source and cosmic-ray test for the MWPC Davide Pinci on behalf of the Frascati-Roma1 MWPC group.
QA/QC in MM SM1 Mod 0 Production at INFN QA/QC MM SM1 Mod 0 - G. Maccarrone 19-Jan
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
30 October 2003V.Souvorov / B.Schmidt - MWPC PRR CERN site1 MWPC Aging Studies Outline: Overview of aging tests done Results in terms of gain variations.
Chamber Quality Control Before the construction several checks are performed on:  Panels (cathode and pad PCB)  GEM foil Tests on assembled detector.
10/7/2003Thomas Schneider1 Status report of CERN/PNPI Tooling support for PNPI M2R2 Prototype Plans towards the PRR.
Marc Anduze – CALICE Meeting – KOBE 10/05/07 Mechanical R&D for Technological EUDET ECAL Prototype.
G. PassalevaFirenze - September 8, 2004 Production Readiness Review Firenze MWPC Production Site G. Passaleva.
28-Feb-16S.Movchan Straw manufacturing and QC1 Straw machine status straw welding machine QC by microscope control by computer straw welding speed optimization:
11/02/2005M. Alfonsi - LNF1 DETECTOR CONSTRUCTION M. Alfonsi - LNF.
Trigger efficicency on double tracks Trigger efficiency on isolated tracks Final results of the Trigger Test on the 25ns beam Bx NUMBER Fraction of Triggers.
Results on a Large Area triple-GEM Detector at LNF 5 th RD51 Collaboration Meeting Freiburg, 25 May 2010 D. Domenici - LNF.
Final results from an extensive aging test on bakelite Resistive Plate Chambers Stefano de Capua University of Rome II “Tor Vergata” and INFN.
T2 GEM Production in Helsinki Kari Kurvinen TOTEM T2 EDR meeting Radiation Detector Laboratory of Helsinki Institute of Physics (HIP) and Department.
Activity report from LNF Panels Soldering tests Production site and tooling status WPC miscellanea (+7 cm layout, cathode costs, aging tests)
XI Workshop on Resistive Plate Chambers and Related Detectors, INFN, 5-10 February, Aging test of high rate MRPC Wang Yi Department of Engineering.
Marc Anduze – EUDET Meeting – PARIS 08/10/07 Mechanical R&D for EUDET module.
Update on Pavia MM mechanical prototype
Quality Control Chamber Production
An extensive aging study of bakelite RPC
G. Carboni for the Muon Group
Investigation on tray MID 063 Back
Report on radiation test done in Casaccia on January 11, 2006
PNPI – M3R4 – Panels 70% - HV bars 100% - FR4 frames 100%
Presentation transcript:

Status Report of activities in LNF Soldering procedure 1.Status of soldering machine 2.Measurement of wire position Chamber prototypes 1.Construction of new prototypes 2.Possibility of opening the chambers 3.Status of mould 4.Mini-ageing test Chamber panels and quality control 1.Planarity measurements 2.Frame height respect to cathode 3.Radiation resistance 4.Thermal resistance LHCb Muon meeting – CERN Jan 30, 2002 (C.Forti, A.Saputi)

Soldering machine 1.Status of the setup Final mechanics ready (see pictures) One head completely assembled and operational Labview software (IMAQ of National Instruments) for soldering and automatic wire pitch measurement under preparation (~ 15 days required) 2.Short film 3.Next steps Soldering tests on larger scale (up to 150 cm) 2 nd head (ready in ~ 2 months) Study of the possibility to determine automatically the soldering quality using reflection of light.

Soldering test

Control of wire positions A frame wired at CERN was transferred on a “dummy” chamber. We compared the measurements of the steps between 140 contiguous wires, from a set of 140 soldered wires (139 steps), obtained from the camera of the soldering machine (in pixel) and from an independent optical measurement (in micron). We found the best conversion factor: 12.5 micron/pixel. We converted the camera measurements from pixels to microns and compare the two measurements (in micron). Conclusions: 1.Excellent agreement between analog and digital measurements: the 2 methods show the same RMS; RMS of difference analog – digital = 17 microns; then we can estimate RMS of digital measurement ~ 12  m 2.Only one wire over 140 is in bad position (easily identified).

Step between wires: conversion from pixel to micron The ratio analogic/digital has a very small RMS 0.09 micron/pixel !!

Step between wires: analogic vs. digital measurement

Step between wires: comparison of analogic and digital mean RMS

Step between wires: difference analogic - digital

Construction of chamber prototypes 3 quadrigaps wired at CERN (10-20th december) (each of area ~ 28x34 cm 2 n.tot wires=1920) 2 of them have been tested and assembled: each single gap (without cover) tested at HV=3.2 kV in air: current is 0 nA assembled (not glued yet) and tested at 3.0 kV (no current) Wires of third quadrigap are being currenlty soldered (ready in few days). Including the quadrigap previously constructed, we will have a total number of 2560 wires, equivalent to one large chamber. Up to now:no wires broken no HV problems never current going up These prototypes were very helpful in understanding construction procedures and HV critical tests.

Test on possibility of opening the chambers As you know, Frascati approach is to use glue for closing the chambers. We are considering the possibility of opening the chambers in case of malfunctioning, using a circular cutter to remove the glue (see drawings). The conclusions of a first test are encouraging: the operation is easy; it is easy to re-close the chamber (usual gluing procedure); the cutter will be provided with a exhaust fan (low dust); short time needed: few minutes.

Test on possibility of opening the chambers

Status of the new mould (big one) Mould for M3R3 chamber: the company has straightened the mould planes (in Al alloy); within a few days, the mould contruction will start (about 20 days required); then, we will start production of large panels (150 x 40 cm 2 ) 1500 mm 500 mm

Ageing test with X rays A B C D 5.9 keV X ray Gaps A and 3300 V, irradiated for 1 month (21 dec-21 jan). They were always on. We monitored the currents in gaps A and B 5  A 15 nA Dose = 5.7  A x 30 days = 14.8 Coulomb The irradiated zone was too large = 3x3 cm 2. So we have ~ 65 cm of wires irradiated. Dose/cm of wire ~ 0.23 C/cm of wire, corresponding to : 4.6 LHC years equivalent in M1R3 or M2R1 while a 10 years test is necessary.

Ageing test with X rays: currents Relative variation of currents, in gap A (TOP) and B (BOTTOM) in one month of test (~ 720 h). Currents always went to 0 when switched off Gap A was stable over this period. The behaviour of Gap B is not well understood. The current was too low and gap B could not to be used as reference. Attenuation from A to B was ~ 300, while ~ 10 could have been OK.

Our ageing test is encouraging, even if not conclusive: the current in Gap A (at 3.3 kV) is stable over one month of test, equivalent to ~ 4.6 LHC years. There is the possibility to perform a complete ageing test, using the Co60 source at ENEA-Casaccia. The distance of the detector from the Co60 sources can be changed to tune the current drawn in test and reference detectors. However, this test is expensive: negotiacions are pending. Ageing test with X rays: conclusions

Chamber panels Total number of panels produced: 52 panels (28 x 34 cm 2 ) Now, we check systematically the panel quality (from last 22 panels produced) Measurement of planarity 1.all panels measured, just after delivery 2.2 panels: after thermal stress (oven and/or refrigerator) 3.3 panels: after radiation stress (gammas of Co60 source) Height of HV bar respect to cathode Tests of fire resistance are being performed by italian fire corps Mechanical tests (Will be performed in Potenza in the first half of february) 1.Flatwise tensile strength (ASTM C297) 2.Flatwise compressive properties of sandwich cores (ASTM C365) 3.Flexural properties of sandwich constructions (ASTM C393) 4.Facing cleavage of sandwich panels (ASTM E2004)

PANELTYPEPRODUCTION DATEDESTINATION 1PAD30-NOV-01PROTOTYPE CONSTRUCTION 2PAD30-NOV-01PROTOTYPE CONSTRUCTION 3PAD30-NOV-01PROTOTYPE CONSTRUCTION 4GROUND30-NOV-01PROTOTYPE CONSTRUCTION 5GROUND30-NOV-01PROTOTYPE CONSTRUCTION 6GROUND30-NOV-01PROTOTYPE CONSTRUCTION 7GROUND30-NOV-01PROTOTYPE CONSTRUCTION 8GROUND30-NOV-01PROTOTYPE CONSTRUCTION 9GROUND30-NOV-01PROTOTYPE CONSTRUCTION 10GROUND30-NOV-01PROTOTYPE CONSTRUCTION 11GROUND30-NOV-01PROTOTYPE CONSTRUCTION 12GROUND30-NOV-01PROTOTYPE CONSTRUCTION 13PAD4-DEC-01PROTOTYPE CONSTRUCTION 14GROUND4-DEC-01OVEN (70 C) + MECHANICAL TEST 15GROUND4-DEC-01PROTOTYPE CONSTRUCTION 16GROUND4-DEC-01PROTOTYPE CONSTRUCTION 17GROUND12-DEC-01RADIATION TEST (10**4 Gray) 18GROUND12-DEC-01RADIATION TEST (10**4 Gray) 19GROUND12-DEC-01MECHANICAL TEST 20GROUND12-DEC-01MECHANICAL TEST 21GROUND12-DEC-01OVEN (40 C) + MECHANICAL TEST 22GROUND12-DEC-01RADIATION TEST (10**4 Gray)

Planarity measurement: method From a set of measurements(x,y,z) defines a reference plane For 65 (x,y) values,measures the distance of the point from the plane 16 points belong to panel border and show larger deviations from the reference plane

Planarity measurements: all panels together ~ 1800 points measured For each panel, if we exclude the points nearest to the border (at ~ 18 mm from it), we get RMS=16.6  With the border included we get RMS=26.9 

Planarity measurements: best panel (n.18) GROUND Side 1 Side 2

4 panels with frames For each panel we measured 12 points (6 on each side) glue HV bar panel Precise bar 2.49 mm Check of HV bar positioning

Frame height respect to the cathode Well within specs Could be better with a rectified bar

Radiation test at ENEA Casaccia (near Rome) with a powerful Co60 source E  =1.25 MeV; the source can operate at 10 4 Gray/hour = 1 Mrad/hour. We chose to irradiate 3 panels at ~80 cm of distance (400 Gy/hr), because a smaller rate causes a bigger damage in polyurethane (Schonbacher and Tavlet, CERN). Test duration ~ 25 hours Total ionising dose ~ 10 4 Gray. Radiation test setup

Radiation effect on planarity: panel 17 (GROUND)

Thermal effect: 77 hours at 62 degrees

First test on final setup of the soldering machine are positive and confirm validity of technical choices Panels are (slowly) continuing the quality tests: no problem found up to now; in the meantime the production has reached a good quality (at least for small ones) A “mini” production of chambers has taken place, where procedures and quality tests have been “trained”. We can afford now with more confidence the construction of larger chambers Conclusions