RMTTSEC – Rolling Monthly Trade and Transfer System Entry Capacity Auction Transmission Workstream, 2 April 2009.

Slides:



Advertisements
Similar presentations
Trades and Transfers Activity to Date. 2 Introduction  Trade and Transfer functionality added to RMSEC auction (renamed RMTTSEC) from July, applying.
Advertisements

Discretionary Release Interruptible Entry Capacity 1st November 2007.
UNC Modification Proposal 0116 Reform of the NTS Offtake Arrangements Transmission Workstream 5 th October 2006.
The Treatment of “Spare / Sterilised” Capacity – follow up Draft for discussion purposes only.
Transfer & Trades Special Transmission Workstream
The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream
Capacity Release Processes and Investment Planning Transmission Planning Code Workshop 2 1 st May 2008.
Draft CMP ROADMAP 19 SG meeting 30 th April 2013.
Transfer & Trades Special Transmission Workstream
Auctions recommendations GTE+ Capacity Product Coordination (CPC) Workshop on 26 November 2008 Matthew Hatch National Grid.
Entry Capacity Substitution Workshop 8 – 7 th April 2009.
Entry Capacity Substitution Workshop 7 – 10 th February 2009.
Entry Capacity Substitution Workshop 9 – 7 th July 2009 DRAFT PRESENTATION.
Transfers and Trades Transmission Workstream
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Classification: Statoil Internal Status: Draft Mod 156/156a Questions regarding the proposals…
Third Workstream meeting re Baseline Re-consultation and Substitution 12 September 2007.
1 Allocation of Baseline Reduction in the Substitution Methodology Draft Presentation aimed for 11 th June Substitution Workstream John Baldwin Gas Strategies.
Update on Entry Capacity Substitution Transmission Workstream 6 th March 2008 Summary of consultation responses.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Mod Clarifications Transmission Workstream 6 August 2009.
Review of Entry Capacity and the Appropriate Allocation of Financial Risk Review Group th Sept 2008.
Initial Thoughts on the Release of Non Obligated NTS System Entry Capacity Transmission Workstream 3 rd April 2008.
Capacity Methodology Statements Transmission Workstream 5 th July 2007.
Optimisation of Entry Capacity Strawman Transmission Workstream 4 th May 2006.
Entry Capacity Substitution Workshop 3 11 th June 2008 Substitution Example.
Implementation of Trades and Transfers National Grid NTS 5 th June 2008.
Entry Capacity Trading Transmission Work Stream, 5 April 2007.
September 2008 QSEC auction - Allocations Transmission Workstream
Entry Capacity Substitution Workshop 4 9 th July 2008 Entry Capacity Substitution Methodology Statement: Discussion Paper.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th March 2009.
Facilitating Release of Non-obligated Entry Capacity Draft – for discussion purposes only 22 November 2007.
Proposal to adjust investment lead times Transmission Workstream 4 th May 2006.
DRSEC Update Transmission Workstream 06 November 2008.
Entry Capacity transfers in the constrained period Transmission Workstream 5 th October 2006.
Trades and Transfers Workshop, 6 th November 2007.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.
Mod Entry Capacity Transfers Transmission Work Stream, 5 April 2007.
Initial Thoughts on Timeline for Entry Capacity Substitution Draft for discussion purposes only.
Transfers and Trades Special Transmission Workstream
The Entry Capacity Substitution Regime Transmission Workstream 7 th February 2008 Thoughts for discussion.
Exit Capacity Release Methodology Statement
Transmission Workstream, 01 October 2009
Non-approved draft Transmission Workstream, 6th December 2007
Transmission Workstream, 2nd March 06
Entry Capacity - update
DRSEC Update August 4th 2009.
Capacity Methodology Statements: Impact of Mod 452
Action from Workshop 3 – SUB010
Capacity Methodology Statements
Annual Review - Methodology Statements
COR1072 Enduring Transfer and Trade Arrangements
Exit Capacity Substitution and Revision
Update on Exit Capacity Substitution and Revision
EU/GB Charging Project – Delivery Timescales
QSEC auction timetable
Modification 501 slides for Workgroup
Review of Trade and Transfer Winter 09/10
Entry Capacity Transfer and Trade
Baseline Re-consultation
Transmission Workstream – 6th July 2005
Modification Proposal 0133 – “Introduction of AMTSEC auction”
Optimisation of Entry Capacity Modification Proposal
Review: Entry Capacity Transfer and Trade Methodology Statement
PRISMA General Information
IECR Incremental Step Size
Incremental Entry Capacity Release Methodology Statement
Modification 0043 – Limitation on offering for sale unsold capacity
Entry Capacity Transfers - Constrained Period
Gemini Contingency Guidelines
Presentation transcript:

RMTTSEC – Rolling Monthly Trade and Transfer System Entry Capacity Auction Transmission Workstream, 2 April 2009

2 Agenda  Compare Results for Winter (Nov – Mar) 07/08 to Winter (Nov – Mar) 08/09  Future RMTTSEC Auctions – Online processes – Review update of Methodology

3 Capacity Allocated Winter 07/08 Capacity Allocated (GWh) Location Nov- 07Dec-07Jan-08Feb-08Mar-08 Barrow Allocated from same ASEP Transfer & Trade Easington Allocated from same ASEP00000 Transfer & Trade Isle of Grain Allocated from same ASEP Transfer & Trade Teesside Allocated from same ASEP Transfer & Trade Single Auction (2 rounds) run in October for whole Winter 07/08 Run in addition to RMSEC 4 ASEPs allocated capacity

4 Capacity Allocated Winter 08/09 Capacity Allocated ( GWh) LocationStage Nov- 08 Dec- 08 Jan- 09 Feb- 09 Mar- 09 Easington 1 Surrendered Unsold Trade Transfer00000 Total Hatfield Moor 1 Surrendered Unsold Trade Transfer00000 Total RMTTSEC allocated at 8 ASEPs All Allocations met by unsold/surrendered at the ASEP except : Easington Hatfield Moor Storage

5 Comparison summary Winter 07/08 Winter 08/09 All bid satisfied Unable to satisfy all bids Additional capacity made available at some ASEPs requesting firm capacity Stimulated secondary trading Aggregate capacity allocations at Easington and Teesside exceeded obligated levels Stimulated secondary trading Aggregate capacity allocations at Easington and Hatfield Moor Storage exceeded obligated levels Winter 08/09 Specific Exchange Rates determined in advance (1:1 within zone within limits and up to 19.5:1 out of zone) All at 1:1 Exchange Rates Users at four ASEPs obtained additional capacity, two via T&T Users at eight ASEPs obtained additional capacity, two via T&T Capacity allocated for each of the five months for which it was available Capacity allocated for each of the five months for which it was available One single (2 rounds) auctionAuctions held monthly in two stages All bids satisfied Additional capacity made available at all ASEPs requesting firm capacity

6 CONCLUSION  The RMTTSEC has been successful in moving capacity to where it is valued most  Through undertaking Exchange Rate analysis after the auction, it has been possible to provide the best Exchange Rates  The process has worked smoothly and is now fully embedded into the commercial regime.  It also provides an additional “secondary trading” mechanism

7 Future RMTTSEC Auctions  No changes proposed to Methodology Statement  National Grid required to consult annually on MS  Expected implementation of online system process 17 th May 2009  Shortening of process timeline by 5 days  Surrender window opens approx 23 Business days before month end (currently approx 28 Business days)  RMTTSEC bid window opens approx 15 Business days before month end (currently approx 20 Business days)

8  Results of RMTTSEC can be found htm htm  Any Queries regarding RMTTSEC Auction contact the Entry Capacity Auctions team:- -on telephone number or on