Construction Phase October 21, 2014.  City of Palm Coast Brian Rothwell, Purchasing Manager Team Leader Stephen Flanagan, Utility Development Manager.

Slides:



Advertisements
Similar presentations
Short-Term Alternatives for City Offices. Background and History Citys current lease for City Marketplace offices ends October 31, 2014 For 22,221 square.
Advertisements

Palm Harbor Golf Course Golf Cart Purchase October 29 th, 2013 Presented by Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director.
The Phoenix IDA 2012 Arizona Housing Forum October 2-4, 2012 Presentation by: Juan Salgado, Executive Director.
GFOAz May 11, 2007 The ABC’s of Municipal Financing.
Parks GO! 2020 December 3, How Municipalities Issue Bonds Bond Referendum Seeking Approval Step 1 Engage Financing Team: Bond Counsel, Financial.
OLD KINGS ROAD Special Assessment District. Overview History Phased Project Initiating Special Assessment Next Steps.
OLD KINGS ROAD Special Assessment District. Overview History Phased Project Current Status.
Amateur Sports Development at Bojangles Coliseum & Ovens Auditorium June 5, 2014 Economic Development & Global Competitiveness Committee.
February 15, Master Plan for Facilities & Infrastructure Master Plan for Facilities and Infrastructure Whittier | Lenexa | Country Club Hills | Birmingham.
STATE ROAD 100 CORRIDOR COMMUNITY REDEVELOPMENT AREA Property Acquisitions June 15, 2010 Presentation for SR 100 Board/City Council Meeting.
STATE ROAD 100 CORRIDOR COMMUNITY REDEVELOPMENT AGENCY Bulldog Drive Improvements Right-of-Way and Design September 21, 2010 Presentation for SR 100 CRA.
Creating New Opportunities
HOLLAND PARK, COMMUNITY CENTER, AND CENTRAL PARK COMMUNITY WING.
CITY OF MERIDIAN FY08 BUDGET HEARING Mayor – Tammy de Weerd Council President – Joe Borton Council Vice President – Charlie Rountree Council – Keith Bird.
1. TABLE 1 GOVERNOR'S BUDGET PROPOSAL Projected State Deficit Rebuild State Reserve Total Resolutions Needed Budget Reduction Initiatives: e.g., Budget.
Property Tax Hearing August 12, Purpose Of Public Hearing Meet Requirements of State Law Explain the City’s reasoning for the proposed tax increase.
Large Public Works Projects and the General Contractor/ Construction Manager (GC/CM) Procedure: A New Way to Save Money, Time and Aggravation.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Tuesday, July 7, 2015.
Team Presentation November 12,  City of Palm Coast Brian Rothwell, Purchasing Manager Team Leader Stephen Flanagan, Utility Development Manager.
CITY OF MERIDIAN FY07 BUDGET HEARING Mayor – Tammy de Weerd Council President – Shaun Wardle Council Vice President – Joe Borton Council – Keith Bird Council.
City Council Workshop Tuesday, July 30 th Current General Fund Budget Rent Expense$240,000 Interest Revenue$280,000 (CRA Loan) Rent Expense$240,000.
ANGELO STATE UNIVERSITY FINANCE AND ADMINISTRATION Sharon K. Meyer Vice President.
Finance Department Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst.
January 24, …a delivery method which entails a commitment by the Construction Manager to deliver the project within a Guaranteed Maximum Price (GMP).
“So You Want a Grocery Store...” Florida Redevelopment Association 2011 Annual Conference Don Paight Fort Myers CRA Executive Director.
Like a Home Mortgage Refinancing:. Issued to construct HS 2004 Bonds (mature 2013 – 2029) 4.8% average interest rate Call Date Bonds.
STATE ROAD 100 CORRIDOR COMMUNITY REDEVELOPMENT AREA Bulldog Drive Right-of-Way Acquisition Status March 9, 2010 Presentation for City Council Workshop.
Proposed SAHA Fiscal Year Consolidated Budget.
1 Management Report on Bradley West Project BOAC Meeting October 5, 2009.
Cleveland Medical Mart and Convention Center Progress Update January 7, 2010 Presented By: Jeffrey R. Appelbaum, Esq.
STATE ROAD 100 CRA FY 2012/2013 Annual Report October 29, 2013 Workshop.
City Council Workshop Presentation July 26, 2011.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst Tuesday, July 28 th 2015.
January 14, The NAMC LCDP Will Provide A Proven Contractor Capacity Building Program For The Public and Private Sector.
Business Inclusion and Development Program Overview Business Development and Procurement Services Budget, Finance and Audit Committee Monday October 5,
Sources: US Census and Bureau of UF Economic and Business Research.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst Tuesday, July 14 th 2015.
STATE ROAD 100 CRA Update to City Council November 13, 2012 Workshop.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst Wednesday, September 9 th 2015.
City Council Presentation September 5,  April ◦ Departments begin line item budgets and projections ◦ Departments submit new program, personnel.
Department of Housing and Community Development Mobilehome Park Rehabilitation and Resident Ownership Program (MPRROP).
1. FY Proposed Budget Jamie Justice, Town Manager & Piet Swart, Finance Director April 26, 2016 Fiscal Year Proposed Budget 2.
Construction Management At Risk Process
Civic Center/City Hall Public Information Meeting March 20, 2007.
Measure N Modernization IMPLEMENTATION PROCESS Planning, Bidding, Construction, and Occupancy.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Tuesday, May 3 rd, 2016.
CONSTRUCTION MANAGEMENT AT RISK Prepared by: Nancy Fouad Carey Attorney AGC Alabama Birmingham Section Meeting November 5, 2012.
1 EASTERN MUNICIPAL WATER DISTRICT Temecula Valley Recycled Water Pipeline Joe Mouawad Sr. Director of Engineering September 2, 2015.
City Council Presentation September 19,  April ◦ Departments begin line item budgets and projections ◦ Departments submit new program, personnel.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst.
Avondale City Center & American Sports Centers Amendment No. 2 Sports Facility Construction City Council January 4, 2010.
City Council Meeting June 21,  Conduct Public Hearing  Adopt 3 Resolutions As City Council 1.Adopt Annual Budget, 5-Year Capital Improvement.
Pier Partial GMP Proposal for Marine Structural June 1, 2017
Stockton Event Center Audit Recommendations and City Response
Application for Project Approval
Case Road Sewer Joe Mouawad, P.E. October 27, 2016.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA
Utility Revenue Bonds Series 2016 March 29th, 2016
Pre-Construction Services
CRESTWOOD LOCAL SCHOOL DISTRICT FIVE YEAR FORECAST
Need to Revise the State College Contracts Law
Valley & Third Streets Redevelopment
Kincaid Hall Renovation
Financial Considerations
St. Marys Intracoastal Gateway.
Example of Public Private Partnership
Presentation transcript:

Construction Phase October 21, 2014

 City of Palm Coast Brian Rothwell, Purchasing Manager Team Leader Stephen Flanagan, Utility Development Manager Carl Cote, Construction Manager Dianne Torino, Contracts & Risk Manager Christopher Quinn, Finance Director Virginia Smith, City Clerk Beau Falgout, City Administration Coordinator  C.T. Hsu & Associates, Inc. Jim Hughes, Principal Tim McNicholas, Principal  Gilbane Building Company Joe Frisco, Senior Project Executive

 Appropriate Project Size and Scope Built for Immediate Needs  No Increase in Existing Residents’ Taxes  Use Existing Financial Resources City Hall Offices = $6.9 Million  Building Permit Fund Excess Revenues=$1.1 Million  Repayment of SR100 CRA (Town Center) Loan=$5.8 million Central Park Community Areas  Allow for phasing as CRA (Town Center) revenues are available  Available CRA Funds in FY2015=$0.5 million

 Completed Space Needs and Cost Analysis  Refinanced Inter-Fund Loan  Allocated Funds for Project  Approved Service Contracts Architectural Services Construction Management Services (at-risk)  City Council Preliminary Design Presentation  Marketing Efforts to Encourage Local Bidders  Final Design Completed  Construction Manager Bids Project  Guaranteed Maximum Price  Ground Breaking  Occupancy

Presented to City Council on March 11, 2014

PHASES | City Hall and Community Spaces Community Event Lawn Future Parking as Needed Future Additional Offices City Hall 32,000 s.f. Phase 1 Parking CommunityMeeting 8,000 s.f. AdditionalParking Promenade and and Public Plaza

LAKE VIEW IN CONTEXT

LAKEFRONT PLAZA VIEW

Phase 1 – City Hall Offices Phase 2a – Infrastructure for Central Park Community Areas

1 st Floor

2 nd Floor

 Vendor Roundtables  Vendor Pre-Qualification  Local & Market Area Participation  17 Vendor Packages (e.g. Concrete, Elevators, etc.)  8 Likely Awards to Local and Market Area Vendors

 Guaranteed Maximum Price of $6,613,743  33,420 s.f. City Hall Office Building  Includes Furnishings, Fixtures, and Equipment  1,697 s.f. of Unfinished Areas for Future Build Out  Phase 2a: Infrastructure Work for Central Park Community Areas  LEED Certification

 Existing Contract  Construction Manager (CM) At-Risk  Cost Overruns CM Responsibility, Not City  Cost Savings Returned  80% to City  20% to CM  Amendment to Contract  Establishes Guaranteed Maximum Price of $6,613,743

PROJECT COSTS PROJECT FUNDING  Design Fees$794,230  Pre-Construction Fees $41,890  Construction$6,613,743  Total$7,449,863 Approved Project Budget  Loan Repayment$5,792,529  Bldg. Reserves** $1,111,334  CRA Funds***$546,000  Total$7,449,863 **Building Department Reserves for Building Function of City Offices ***CRA Funds for Design and Phase 2a Project Costs

 GMP ApprovalOctober 21, 2014  GroundbreakingOctober 29, 2014  ConstructionNov – Aug  Substantial CompletionAugust 2015  FFE InstallationSeptember 2015  City OccupancyOctober 2015  Marketplace Lease EndsNovember 2015